|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to attachments for broadband service on utility poles |
|
owned by an electric cooperative. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. The heading to Chapter 252, Utilities Code, is |
|
amended to read as follows: |
|
CHAPTER 252. CABLE ATTACHMENTS TO ELECTRIC COOPERATIVE'S |
|
DISTRIBUTION POLES |
|
SECTION 2. Title 5, Utilities Code, is amended by adding |
|
Chapter 253 to read as follows: |
|
CHAPTER 253. BROADBAND ATTACHMENTS TO ELECTRIC COOPERATIVE'S |
|
DISTRIBUTION POLES |
|
SUBCHAPTER A. GENERAL PROVISIONS |
|
Sec. 253.0001. DEFINITIONS. In this chapter: |
|
(1) "Broadband provider" means an entity that provides |
|
broadband service either directly or through an affiliate that uses |
|
the entity's communications facilities, regardless of whether the |
|
entity: |
|
(A) provides additional services in addition to |
|
broadband service; or |
|
(B) uses its facilities in whole or in part to |
|
provide broadband service. |
|
(2) "Broadband service" means Internet service with |
|
the capability of providing: |
|
(A) a download speed of 25 megabits per second or |
|
faster; and |
|
(B) an upload speed of three megabits per second |
|
or faster. |
|
(3) "Communications space" means the lower usable |
|
space on a pole that is typically reserved for low-voltage |
|
communications equipment. |
|
(4) "Large order application" means an application |
|
submitted by a broadband provider under this subchapter requesting |
|
access to attach pole attachments to a number of poles: |
|
(A) that exceeds the lesser of 300 poles or a |
|
number equal to 0.5 percent of the electric cooperative's poles; |
|
and |
|
(B) that is not more than the lesser of 3,000 |
|
poles or a number equal to five percent of the electric |
|
cooperative's poles. |
|
(5) "Pole" has the meaning assigned by Section |
|
252.001. |
|
(6) "Pole attachment" means an affixture of cables, |
|
strands, wires, and associated equipment used in the provision of a |
|
broadband provider's services attached to a pole directly or |
|
indirectly or placed in a right-of-way owned or controlled by an |
|
electric cooperative. |
|
(7) "Simple make-ready activities" means work to |
|
accommodate a new pole attachment on a pole and includes work where |
|
existing attachments in the communications space are moved without |
|
any reasonable expectation of: |
|
(A) service outage or facility damage; |
|
(B) a need to splice an existing communications |
|
attachment; or |
|
(C) a need to relocate an existing wireless |
|
attachment. |
|
Sec. 253.0002. APPLICABILITY AND CONSTRUCTION OF CHAPTER. |
|
(a) This chapter applies to a pole attachment affixed by a |
|
broadband provider to a pole owned and controlled by an electric |
|
cooperative. This chapter does not apply to a pole attachment |
|
regulated by the Federal Communications Commission under 47 U.S.C. |
|
Section 224. |
|
(b) This chapter does not abrogate or affect a right or |
|
obligation of a party to a pole attachment contract entered into by |
|
a broadband provider and an electric cooperative before September |
|
1, 2021. |
|
(c) A broadband provider that attaches a pole attachment to |
|
a pole owned by an electric cooperative under the terms of this |
|
chapter is subject to Sections 252.006, 252.007, and 252.008 in the |
|
same manner as if the broadband provider were a cable operator. |
|
(d) This chapter does not limit a right of a party to a pole |
|
attachment contract to request modification, amendment, or renewal |
|
of such contract to conform it to the provisions of this chapter. |
|
Sec. 253.0003. NO STATE CERTIFICATION; NO REGULATORY |
|
AUTHORITY. (a) This chapter does not constitute state |
|
certification under 47 U.S.C. Section 224. If a court determines |
|
that this chapter constitutes certification under that section, |
|
this chapter is not enforceable and has no effect. |
|
(b) This chapter may not be construed to subject an electric |
|
cooperative to regulation by the Federal Communications Commission |
|
under 47 U.S.C. Section 224. |
|
(c) This chapter does not authorize a department, agency, or |
|
political subdivision of this state to exercise enforcement or |
|
regulatory authority over attachments to electric cooperative |
|
poles. |
|
Sec. 253.0004. CONSTRUCTION OF TERMS AND PHRASES. |
|
Technical terms and phrases in this chapter, other than those |
|
defined by Section 253.0001, shall be construed using the term's or |
|
phrase's usual and customary meanings in the electric and broadband |
|
industries. |
|
Sec. 253.0005. COST-BASED NON-RECURRING CHARGES. |
|
Non-recurring charges authorized by this chapter must be |
|
cost-based. |
|
SUBCHAPTER B. APPLICATION FOR ACCESS TO POLES |
|
Sec. 253.0101. APPLICATION FOR POLE ACCESS. (a) A |
|
broadband provider may not access a pole owned by an electric |
|
cooperative for the purpose of placing a pole attachment unless the |
|
provider applies for that access in accordance with this |
|
subchapter. |
|
(b) An electric cooperative shall: |
|
(1) establish a timeline for a broadband provider to |
|
apply for and obtain access to poles for placing a pole attachment |
|
under this chapter; and |
|
(2) make available an explanation of the information |
|
reasonably required for an application for access to poles for |
|
placing a pole attachment under this chapter to be considered |
|
complete. |
|
Sec. 253.0102. REVIEW OF APPLICATION FOR COMPLETENESS. (a) |
|
An electric cooperative shall review an application for |
|
completeness before the cooperative reviews the application on the |
|
merits. |
|
(b) An electric cooperative shall notify an applicant |
|
whether an application is complete not later than: |
|
(1) the 10th business day after the date the |
|
cooperative receives the application; |
|
(2) the 25th business day after the date the |
|
cooperative receives a large order application; |
|
(3) the fifth business day after the date the |
|
cooperative receives a resubmitted application; or |
|
(4) the 20th business day after the date the |
|
cooperative receives a resubmitted large order application. |
|
Sec. 253.0103. TREATMENT OF MULTIPLE APPLICATIONS BY SAME |
|
APPLICANT. For purposes of this chapter, an electric cooperative |
|
may treat as a single application for pole access an application the |
|
cooperative receives from the same applicant before the 31st day |
|
after the cooperative receives that applicant's most recent |
|
previous application. |
|
Sec. 253.0104. GRANT OR DENIAL OF APPLICATION. (a) Except |
|
as provided by Sections 253.0204 and 253.0302, an electric |
|
cooperative shall grant or deny an application for pole access |
|
under this chapter and provide to the applicant a survey of the |
|
poles affected by the application not later than: |
|
(1) the 45th day after the date the cooperative |
|
receives a complete application; or |
|
(2) the 60th day after the date the cooperative |
|
receives a complete large order application. |
|
(b) An electric cooperative may deny an application for |
|
access to a pole under this chapter if: |
|
(1) generally applicable safety, reliability, or |
|
engineering requirements established for the protection of public |
|
health, safety, or welfare prevent granting access; or |
|
(2) the pole lacks sufficient capacity. |
|
(c) Notwithstanding Subsection (b)(1), an electric |
|
cooperative may not deny access to a pole if the capacity, safety, |
|
reliability, or engineering consideration may be remedied by |
|
rearranging, expanding, replacing, or otherwise safely |
|
reengineering the pole or pole attachments through make-ready |
|
activities. |
|
(d) An electric cooperative's denial of an application to |
|
access a pole under this chapter must: |
|
(1) be specific; |
|
(2) include all relevant evidence and information that |
|
supports the denial; and |
|
(3) explain how the evidence and information relate to |
|
the denial. |
|
Sec. 253.0105. DEADLINES NOT APPLICABLE TO CERTAIN |
|
APPLICATIONS. (a) An electric cooperative is not required to meet |
|
the deadlines under this subchapter for an application for pole |
|
access to place pole attachments on more than 3,000 poles or more |
|
than 5 percent of the electric cooperative's poles. |
|
(b) An electric cooperative may not act under Subsection (a) |
|
to delay an application unreasonably and shall negotiate in good |
|
faith with the applicant regarding the time required to fulfill the |
|
cooperative's duties. |
|
SUBCHAPTER C. MAKE-READY ACTIVITIES |
|
Sec. 253.0201. DEADLINES FOR MAKE-READY ACTIVITIES. (a) |
|
Not later than the 15th day after the date an electric cooperative |
|
grants an application, the electric cooperative shall provide to |
|
the broadband provider a detailed and itemized estimate of the |
|
expected costs of all necessary make-ready activities. |
|
(b) An electric cooperative shall complete all make-ready |
|
activities in the communications space and send a detailed, |
|
itemized final invoice to the broadband provider not later than: |
|
(1) the 30th day after the date the electric |
|
cooperative receives payment of the estimated make-ready cost from |
|
the broadband provider; or |
|
(2) for a large order application, the 75th day after |
|
the date the electric cooperative receives payment of the estimated |
|
make-ready cost from the broadband provider. |
|
(c) An electric cooperative shall complete all make-ready |
|
activities above the communications space, including pole |
|
replacements, and send a detailed, itemized final invoice to the |
|
broadband provider not later than: |
|
(1) the 90th day after the date the electric |
|
cooperative receives payment of the estimated make-ready cost from |
|
the broadband provider; or |
|
(2) for a large order application, the 135th day after |
|
the date the electric cooperative receives payment of the estimated |
|
make-ready cost from the broadband provider. |
|
Sec. 253.0202. EXTENSION OF MAKE-READY ACTIVITIES |
|
DEADLINE. (a) An electric cooperative may extend a deadline under |
|
Section 253.0201(b) or (c) for a cause that renders the deadline |
|
infeasible. A cooperative that chooses to extend a deadline shall: |
|
(1) immediately and in writing notify the broadband |
|
provider and each person with an affected existing pole attachment |
|
about the delay; and |
|
(2) identify the affected poles and provide a detailed |
|
explanation of the reason for the delay and an estimated new |
|
completion date to the broadband provider and each person with an |
|
affected existing pole attachment. |
|
(b) An electric cooperative may not extend a deadline under |
|
this section for a period longer than is necessary to complete |
|
make-ready activities on affected poles. |
|
(c) An electric cooperative may not extend a deadline under |
|
this section because of a preexisting violation on an affected pole |
|
caused by a person other than the broadband provider. The |
|
cooperative shall correct a preexisting violation as part of the |
|
make-ready process and before the applicable deadline at the cost |
|
of the responsible person. |
|
(d) An electric cooperative shall resume make-ready |
|
activities without discrimination when the cooperative returns to |
|
routine operations. |
|
Sec. 253.0203. DEADLINES NOT APPLICABLE TO CERTAIN |
|
APPLICATIONS. (a) An electric cooperative is not required to meet |
|
the deadlines under this subchapter for an application to place |
|
pole attachments on more than 3,000 poles or more than five percent |
|
of the electric cooperative's poles. |
|
(b) An electric cooperative may not act under Subsection (a) |
|
to delay an application unreasonably and shall negotiate in good |
|
faith with the applicant regarding the time required to fulfill the |
|
cooperative's duties. |
|
Sec. 253.0204. CONTRACTORS FOR MAKE-READY ACTIVITIES. (a) |
|
A broadband provider may hire a contractor approved by the electric |
|
cooperative to complete a survey under Section 253.0104 or perform |
|
a make-ready activity under this subchapter that is not timely |
|
completed by the electric cooperative or a person with an existing |
|
pole attachment. |
|
(b) The broadband provider shall provide reasonably timely |
|
notice to the electric cooperative and each person with an existing |
|
pole attachment on an affected pole that the provider intends to |
|
hire a contractor as authorized by Subsection (a). |
|
(c) The broadband provider shall provide reasonably timely |
|
notice to the electric cooperative and each person with an existing |
|
pole attachment on an affected pole of the contractor's completion |
|
of the make-ready activities. |
|
(d) An electric cooperative may not act under Subsection (a) |
|
unreasonably to withhold approval of a contractor for purposes of |
|
this section. |
|
(e) Not later than the 90th day after the date a broadband |
|
provider provides notice as provided by Subsection (c), the |
|
cooperative or person may inspect the make-ready work. |
|
(f) Not later than the 14th day after the date that an |
|
electric cooperative or person completes an inspection under |
|
Subsection (e), the cooperative or person may notify the broadband |
|
provider of any damage or code violations caused by such work. The |
|
notice must include specific documentation. |
|
(g) The electric cooperative or person that completes an |
|
inspection may: |
|
(1) remedy any defective make-ready work at the cost |
|
of the broadband provider; or |
|
(2) require the provider to remedy the defect not |
|
later than the 14th day after the provider receives the notice under |
|
Subsection (f). |
|
Sec. 253.0205. LIST OF APPROVED CONTRACTORS. (a) An |
|
electric cooperative shall maintain and make available a list of |
|
approved contractors for work above the communications space and |
|
pole replacements. An electric cooperative may require any work |
|
above the communications space and pole replacements to be |
|
performed by contractors on this list, including work performed by |
|
a contractor hired under Section 253.0204. |
|
(b) An electric cooperative may not act unreasonably to |
|
withhold consent for a requested addition of a qualified contractor |
|
to the list described by Subsection (a). |
|
SUBCHAPTER D. OPTION FOR SIMPLE MAKE-READY ACTIVITIES |
|
Sec. 253.0301. OPTION: SIMPLE MAKE-READY. A broadband |
|
provider may choose to perform simple make-ready activities using |
|
one-touch make-ready procedures in place of the process outlined |
|
under Subchapter C. |
|
Sec. 253.0302. GRANT OR DENIAL OF APPLICATION: SIMPLE |
|
MAKE-READY. (a) A broadband provider that chooses to perform |
|
simple make-ready activities as described by Section 253.0301 must |
|
indicate that choice and describe the work to be performed as part |
|
of the provider's initial application under Subchapter B. |
|
(b) An electric cooperative shall grant or deny an |
|
application for simple make-ready activities under this section not |
|
later than: |
|
(1) the 15th day after the date the cooperative |
|
receives a complete application; or |
|
(2) the 30th day after the date the cooperative |
|
receives a complete large order application. |
|
Sec. 253.0303. SIMPLE MAKE-READY ACTIVITIES PERFORMED BY |
|
CONTRACTOR. (a) If an application for activities under Section |
|
253.0302 is granted, a contractor hired by the broadband provider |
|
shall perform all necessary surveys. |
|
(b) The broadband provider and contractor shall provide a |
|
reasonable opportunity for the electric cooperative and a person |
|
with an existing pole attachment on an affected pole to be present |
|
for any field inspections. |
|
(c) A contractor hired by the broadband provider may perform |
|
all simple make-ready activities. Not later than the 15th day |
|
before the date the contractor begins performing simple make-ready |
|
activities, the contractor shall provide to the electric |
|
cooperative and a person with an existing pole attachment on an |
|
affected pole written notice that: |
|
(1) identifies the contractor performing the |
|
activities; and |
|
(2) sets out reasonable opportunities for the |
|
cooperative and person to be present for the activities. |
|
Sec. 253.0304. INSPECTION OF WORK AND REMEDIATION OF |
|
DAMAGES. (a) A broadband provider immediately shall notify the |
|
electric cooperative and a person with an existing pole attachment |
|
on an affected pole of any damage to the cooperative's or person's |
|
facilities reasonably likely to interrupt the entity's service. |
|
(b) An electric cooperative or person that receives notice |
|
under Subsection (a) may: |
|
(1) complete any remedial work at a reasonable cost to |
|
the broadband provider; or |
|
(2) require the broadband provider immediately to |
|
remedy the damage at the provider's own expense. |
|
(c) Not later than the 15th day after the date a broadband |
|
provider or contractor hired by the provider completes simple |
|
make-ready activities on a pole, the provider shall notify the |
|
electric cooperative and a person with an existing pole attachment |
|
on the pole of the completed work. |
|
(d) Not later than the 90th day after the date an electric |
|
cooperative or person receives notice under Subsection (c), the |
|
cooperative or person may inspect the work. Not later than the 14th |
|
day after the date of the inspection, the cooperative or person may |
|
provide notice to the broadband provider, with specific |
|
documentation, of any damage or code violations caused by the work. |
|
(e) An electric cooperative or person that provides notice |
|
under Subsection (d) may: |
|
(1) remedy any defective make-ready work at the cost |
|
of the broadband provider; or |
|
(2) require the provider to remedy the defect not |
|
later than the 14th day after the date the provider received the |
|
notice under Subsection (d). |
|
SUBCHAPTER E. POLES AND POLE ATTACHMENTS |
|
Sec. 253.0401. DUTIES OF ELECTRIC COOPERATIVE. An electric |
|
cooperative shall rearrange, expand, replace, or otherwise safely |
|
reengineer any pole at the request of a broadband provider whose |
|
application for access to a pole is granted if the change is: |
|
(1) consistent with the National Electrical Safety |
|
Code; and |
|
(2) reasonably necessary to safely accommodate a pole |
|
attachment. |
|
Sec. 253.0402. RECOVERY OF COSTS FOR REPLACING POLES. (a) |
|
If an electric cooperative is required under Section 253.0401 to |
|
replace a pole that has been in service for longer than 75 percent |
|
and less than 100 percent of the average service life of a pole |
|
owned by the cooperative, the cooperative may not require |
|
reimbursement of costs associated with replacing the pole from the |
|
broadband provider that exceed the cooperative's reasonable costs |
|
of advancing the retirement of the existing pole. |
|
(b) The costs under Subsection (a) shall be determined by |
|
adding: |
|
(1) the remaining undepreciated value of the existing |
|
pole; |
|
(2) any interest expense of advancing the replacement |
|
of the pole relative to replacing the pole at the end of the average |
|
service life of a pole owned by the electric cooperative; and |
|
(3) any reasonable incremental cost of increasing the |
|
capacity of the replacement pole relative to the installation cost |
|
of the average new pole installed by the electric cooperative. |
|
(c) If an electric cooperative is required under Section |
|
253.0401 to replace a pole that has been in service for the average |
|
service life of a pole owned by the electric cooperative or longer, |
|
the cooperative may not require reimbursement of costs associated |
|
with replacing the pole from the broadband provider that exceed any |
|
reasonable incremental cost of increasing the capacity of the |
|
replacement pole relative to the installation cost of the average |
|
new pole installed by the electric cooperative. |
|
(d) An electric cooperative shall determine the average |
|
service life of a pole as the period of time during which an |
|
electric cooperative's books maintained for tax and accounting |
|
purposes consider an average pole to have positive value, after |
|
depreciation. |
|
Sec. 253.0403. SHARING COSTS OF MODIFICATION TO POLE. (a) |
|
The following entities must share proportionately in the costs of |
|
modifying a pole under Section 253.0401: |
|
(1) the broadband provider who obtains access to a |
|
pole through a modification to the pole; and |
|
(2) a person who directly benefits from a |
|
modification, including: |
|
(A) the electric cooperative; |
|
(B) a person with an existing attachment on the |
|
pole who adds to or modifies the person's attachment after |
|
receiving notice of the modification; and |
|
(C) a party that makes an attachment to a pole |
|
after the completion of a modification that made the attachment |
|
possible. |
|
(b) This section does not affect the responsibility of the |
|
electric cooperative under Sections 253.0401 and 253.0402. |
|
Sec. 253.0404. EXTENSION ARMS AND TEMPORARY POLE |
|
ATTACHMENTS. (a) A broadband provider may use extension arms and |
|
temporary attachments pending the completion of make-ready |
|
activities if use of extension arms and temporary attachments |
|
complies with the National Electrical Safety Code or other |
|
applicable safety codes. |
|
(b) An electric cooperative may require a broadband |
|
provider to convert a temporary attachment to a permanent |
|
attachment not later than the 60th day after the date of the |
|
completion of make-ready activities and may require the provider to |
|
comply with the National Electrical Safety Code or other |
|
applicable safety codes. |
|
Sec. 253.0405. POLE ATTACHMENT SPECIFICATIONS. (a) A |
|
broadband provider may not be required to meet pole attachment |
|
specifications that exceed the specifications in the National |
|
Electrical Safety Code, applicable fire safety codes, and any |
|
building code or similar code of general applicability for the |
|
protection of public health, safety, or welfare a political |
|
subdivision adopted before the provider submitted an application to |
|
the cooperative. |
|
(b) This section may not be construed to expand the power of |
|
any local government jurisdiction. |
|
Sec. 253.0406. OVERLASHING. (a) A broadband provider with |
|
an existing pole attachment may not be required to obtain advance |
|
approval from an electric cooperative to overlash or permit a third |
|
party to overlash the provider's existing wires. |
|
(b) An electric cooperative may require a broadband |
|
provider to provide notice before and after overlashing. The |
|
cooperative may not require notice before overlashing to be |
|
provided before the 15th day before the date of the overlashing |
|
activities. |
|
(c) An electric cooperative may require a broadband |
|
provider to modify an overlashing proposal to address specific and |
|
identified capacity, safety, reliability, or engineering issues. |
|
The cooperative may not prohibit the provider from overlashing |
|
because of a preexisting violation caused by another person. |
|
(d) An electric cooperative may require a broadband |
|
provider to remedy damage or code violations caused by overlashing |
|
if the electric cooperative: |
|
(1) inspects the overlash not later than the 90th day |
|
after the date the cooperative receives notice that an overlash is |
|
complete; and |
|
(2) informs the provider of the damage or violation |
|
not later than the 14th day after the date of the inspection. |
|
Sec. 253.0407. USE OF POLE ATTACHMENTS FOR MULTIPLE |
|
SERVICES. A broadband provider that attaches a pole attachment |
|
under this chapter may use the attachment for any service delivered |
|
over the provider's facilities, including cable service. |
|
SUBCHAPTER F. POLE ATTACHMENT CONTRACTS |
|
Sec. 253.0501. POLE ATTACHMENT CONTRACTS WITH BROADBAND |
|
PROVIDERS. (a) A broadband provider and an electric cooperative |
|
shall establish the rates, terms, and conditions for pole |
|
attachments by a written pole attachment contract executed by both |
|
parties. The rates, terms, and conditions for attachments by a |
|
broadband provider on an electric cooperative's poles must be just, |
|
reasonable, and nondiscriminatory. |
|
(b) In determining whether rates, terms, and conditions are |
|
just and reasonable, the following factors must be considered: |
|
(1) the interests of and benefits to the consumers and |
|
potential consumers of the electric cooperative's services; |
|
(2) the interests of and benefits to the subscribers |
|
and potential subscribers to broadband services offered through the |
|
pole attachments; |
|
(3) the interests of and benefits to third parties |
|
from the availability of broadband services offered through the |
|
pole attachments; |
|
(4) compliance with the specifications in the National |
|
Electrical Safety Code, applicable fire safety codes, and any |
|
building code or similar code of general applicability for the |
|
protection of public health, safety, or welfare applicable to the |
|
pole attachments; and |
|
(5) the maintenance and reliability of both electric |
|
distribution and broadband services. |
|
(c) A broadband provider and an electric cooperative shall |
|
negotiate a pole attachment contract and any amendment, |
|
modification, or renewal thereof in good faith. |
|
(d) A request to negotiate a new pole attachment contract or |
|
to amend, modify, or renew a contract pertaining to pole |
|
attachments by a broadband provider or an electric cooperative must |
|
be made in writing. |
|
Sec. 253.0502. CONTRACT NEGOTIATIONS AND MEDIATION. (a) |
|
If a broadband provider and an electric cooperative are unable to |
|
agree to a new pole attachment contract before the expiration date |
|
of an existing contract, the rates, terms, and conditions of the |
|
existing contract and the terms and conditions of the electric |
|
cooperative's application and permitting processes remain in |
|
force: |
|
(1) during the 90-day negotiation period described by |
|
Subsection (b) and during the period of any agreed extension; |
|
(2) during the 60-day mediation period described by |
|
Subsection (b) and during the period of any agreed extension; and |
|
(3) pending final disposition of any litigation |
|
commenced under Subsection (c). |
|
(b) If a broadband provider and an electric cooperative are |
|
unable to agree to a new pole attachment contract before the 91st |
|
day after the expiration date of an existing contract, and are |
|
unable to agree to an extension of the negotiation period for a |
|
certain number of days, the broadband provider and electric |
|
cooperative shall attempt to resolve any disagreement over the |
|
rates, terms, or conditions by submitting the contract negotiations |
|
to a mediation process. The mediation process may not extend later |
|
than the 60th day after the end of the initial 90-day negotiation |
|
period and any agreed extension of that period unless the broadband |
|
provider and electric cooperative agree to an extension of the |
|
mediation period for a certain number of days. The mediation |
|
process must be conducted in a county in which the electric |
|
cooperative has distribution poles. The broadband provider and |
|
electric cooperative must share equally the expenses for the |
|
mediator. |
|
(c) If the mediation process under Subsection (b) does not |
|
resolve the disagreement over the rates, terms, or conditions of a |
|
new pole attachment agreement, or if a dispute arises under the |
|
terms of an existing agreement or the requirements of this chapter, |
|
the broadband provider or electric cooperative may file suit in a |
|
district court to resolve the disagreement or dispute, including to |
|
enforce the terms of the agreement or of this chapter. |
|
SECTION 3. This Act takes effect September 1, 2021. |