|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
|
relating to mechanic's, contractor's, or materialman's liens. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 3503.051(3), Insurance Code, is amended |
|
to read as follows: |
|
(3) "Notice of claim" means a written notification by |
|
a claimant who makes a claim for payment from the surety company. |
|
The term does not include a routine statutory notice required by |
|
Section 53.056 or [53.056(b),] 53.057, [53.058, 53.252(b), or |
|
53.253,] Property Code, or Section 2253.047, Government Code. |
|
SECTION 2. Section 53.001, Property Code, is amended by |
|
amending Subdivisions (2), (3), (4), (8), (11), (13), and (14) and |
|
adding Subdivision (7-a) to read as follows: |
|
(2) "Improvement" includes: |
|
(A) a house, building, structure, parking |
|
structure, physical appurtenance, pool, utility, railroad, well, |
|
storage facility, abutting sidewalks and streets, [and] utilities |
|
in or on those sidewalks and streets, land reclaimed from overflow, |
|
and other fixtures or modifications to real property; |
|
(B) clearing, grubbing, draining, or fencing of |
|
land; |
|
(C) machinery or apparatuses used for raising |
|
water or for supplying or storing water for stock, domestic use, or |
|
irrigation [wells, cisterns, tanks, reservoirs, or artificial |
|
lakes or pools made for supplying or storing water]; |
|
(D) work described by Section 53.021(4) [pumps, |
|
siphons, and windmills or other machinery or apparatuses used for |
|
raising water for stock, domestic use, or irrigation]; and |
|
(E) a design, drawing, plan, plat, survey, or |
|
specification provided by a licensed architect, engineer, or |
|
surveyor [planting orchard trees, grubbing out orchards and |
|
replacing trees, and pruning of orchard trees]. |
|
(3) "Labor" means: |
|
(A) labor used in the direct performance |
|
[prosecution] of the work; or |
|
(B) a professional service used in the direct |
|
preparation for the work of a design, drawing, plan, plat, survey, |
|
or specification. |
|
(4) "Material" means all or part of: |
|
(A) the material, machinery, fixtures, or tools: |
|
(i) incorporated into the work; |
|
(ii) used [, consumed] in the direct |
|
performance [prosecution] of the work; |
|
(iii) specially fabricated for an |
|
improvement; [,] or |
|
(iv) ordered and delivered for |
|
incorporation or use [consumption]; |
|
(B) rent at a reasonable rate and actual running |
|
repairs at a reasonable cost for construction equipment used or |
|
reasonably required and delivered for use in the direct performance |
|
[prosecution] of the work at the site of the construction or repair; |
|
or |
|
(C) power, water, fuel, and lubricants consumed |
|
or ordered and delivered for consumption in the direct performance |
|
[prosecution] of the work. |
|
(7-a) "Purported original contractor" means an |
|
original contractor who can effectively control the owner or is |
|
effectively controlled by the owner through common ownership of |
|
voting stock or ownership interests, interlocking directorships, |
|
common management, or otherwise, or who was engaged by the owner for |
|
the construction or repair of improvements without a good faith |
|
intention of the parties that the purported original contractor was |
|
to perform under the contract. For purposes of this subdivision, |
|
the term "owner" does not include a person who has or claims a |
|
security interest only. |
|
(8) "Residence" means the real property and |
|
improvements for a single-family house, duplex, triplex, or |
|
quadruplex or a unit in a multiunit structure used for residential |
|
purposes in which title to the individual units is transferred to |
|
the owners under a condominium or cooperative system that is: |
|
(A) owned by one or more adult persons; and |
|
(B) used or intended to be used as a dwelling by |
|
one of the owners. |
|
(11) "Retainage" means an amount representing part of |
|
a contract payment that is not required to be paid to the claimant |
|
within the month following the month in which labor is performed, |
|
material is furnished, or specially fabricated material is |
|
delivered. [The term does not include retainage under Subchapter |
|
E.] |
|
(13) "Subcontractor" means a person who labors or has |
|
furnished labor or materials to fulfill an obligation to an |
|
original contractor or to a subcontractor of any tier to perform all |
|
or part of the work required by an original contract. |
|
(14) "Work" means any part of construction or repair |
|
of an improvement performed under an original contract. |
|
SECTION 3. Section 53.003, Property Code, is amended by |
|
amending Subsections (b) and (c) and adding Subsection (e) to read |
|
as follows: |
|
(b) Except as provided by Subsection (c) or (d), any [Any] |
|
notice or other written communication required by this chapter must |
|
[may] be delivered: |
|
(1) in person to the party entitled to the notice or to |
|
that party's agent; |
|
(2) by certified mail; or |
|
(3) by any other form of traceable, private delivery |
|
or mailing service that can confirm proof of receipt[, regardless |
|
of the manner prescribed by law]. |
|
(c) If notice is sent by [registered or] certified mail, |
|
deposit or mailing of the notice in the United States mail in the |
|
form required constitutes compliance with the notice requirement. |
|
This subsection does not apply if the law requires receipt of the |
|
notice by the person to whom it is directed. |
|
(e) In computing the period of days in which to provide a |
|
notice or to take any action required under this chapter, if the |
|
last day of the period is a Saturday, Sunday, or legal holiday, the |
|
period is extended to include the next day that is not a Saturday, |
|
Sunday, or legal holiday. |
|
SECTION 4. Section 53.021, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.021. PERSONS ENTITLED TO LIEN. [(a)] A person has |
|
a lien if[: |
|
[(1)] the person, under a contract with the owner or |
|
the owner's agent, trustee, receiver, contractor, or |
|
subcontractor: |
|
(1) labors[, specially fabricates material,] or |
|
furnishes labor or materials for construction or repair of an |
|
improvement; [in this state of: |
|
[(A) a house, building, or improvement; |
|
[(B) a levee or embankment to be erected for the |
|
reclamation of overflow land along a river or creek; or |
|
[(C) a railroad; and] |
|
(2) [the person labors, specially fabricates the |
|
material, or furnishes the labor or materials under or by virtue of |
|
a contract with the owner or the owner's agent, trustee, receiver, |
|
contractor, or subcontractor. |
|
[(b) A person who] specially fabricates material, [has a |
|
lien] even if the material is not delivered; |
|
(3) is a licensed [. |
|
[(c) An] architect, engineer, or surveyor providing |
|
services to prepare a design, drawing, [who prepares a] plan, [or] |
|
plat, survey, or specification; |
|
(4) [under or by virtue of a written contract with the |
|
owner or the owner's agent, trustee, or receiver in connection with |
|
the actual or proposed design, construction, or repair of |
|
improvements on real property or the location of the boundaries of |
|
real property has a lien on the property. |
|
[(d) A person who] provides labor, plant material, or other |
|
supplies for the installation of landscaping for an [a house, |
|
building, or] improvement, including the construction of a |
|
retention pond, retaining wall, berm, irrigation system, fountain, |
|
or other similar installation; or |
|
(5) [, under or by virtue of a written contract with |
|
the owner or the owner's agent, contractor, subcontractor, trustee, |
|
or receiver has a lien on the property. |
|
[(e) A person who] performs labor as part of, or [who] |
|
furnishes labor or materials for, the demolition of an improvement |
|
[a structure] on real property [under or by virtue of a written |
|
contract with the owner of the property or the owner's agent, |
|
trustee, receiver, contractor, or subcontractor has a lien on the |
|
property]. |
|
SECTION 5. Sections 53.022(a), (c), and (d), Property Code, |
|
are amended to read as follows: |
|
(a) The lien extends to the [house, building, fixtures, or] |
|
improvements [, the land reclaimed from overflow, or the railroad |
|
and all of its properties,] and to each lot of land necessarily |
|
connected [or reclaimed]. |
|
(c) A lien against land in a city, town, or village extends |
|
to each lot on which the [house, building, or] improvement is |
|
situated or on which the labor was performed. |
|
(d) A lien against land not in a city, town, or village |
|
extends to not more than 50 acres on which the [house, building, or] |
|
improvement is situated or on which the labor was performed. |
|
SECTION 6. Section 53.023, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.023. PAYMENT SECURED BY LIEN. The lien secures |
|
payment for: |
|
(1) the labor done or material furnished for the |
|
construction, [or] repair, design, survey, or demolition; or |
|
(2) the specially fabricated material, even if the |
|
material has not been delivered or incorporated into the |
|
construction or repair, less its fair salvage value[; or |
|
[(3) the preparation of a plan or plat by an architect, |
|
engineer, or surveyor in accordance with Section 53.021(c)]. |
|
SECTION 7. Section 53.026(a), Property Code, is amended to |
|
read as follows: |
|
(a) A person who labors[, specially fabricates materials,] |
|
or furnishes labor or materials under a direct contractual |
|
relationship with a purported original contractor [another person] |
|
is considered to be [in direct contractual relationship with the |
|
owner and has a lien as] an original contractor for purposes of |
|
perfecting a mechanic's lien [, if: |
|
[(1) the owner contracted with the other person for |
|
the construction or repair of a house, building, or improvements |
|
and the owner can effectively control that person through ownership |
|
of voting stock, interlocking directorships, or otherwise; |
|
[(2) the owner contracted with the other person for |
|
the construction or repair of a house, building, or improvements |
|
and that other person can effectively control the owner through |
|
ownership of voting stock, interlocking directorships, or |
|
otherwise; or |
|
[(3) the owner contracted with the other person for |
|
the construction or repair of a house, building, or improvements |
|
and the contract was made without good faith intention of the |
|
parties that the other person was to perform the contract]. |
|
SECTION 8. Section 53.052, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.052. FILING OF AFFIDAVIT. (a) An original |
|
contractor claiming the lien must file an affidavit with the county |
|
clerk: |
|
(1) for projects other than residential construction |
|
projects, not later than the 15th day of the fourth month after the |
|
month in which the original contractor's work was completed, |
|
terminated, or abandoned; or |
|
(2) for residential construction projects, not later |
|
than the 15th day of the third month after the month in which the |
|
original contractor's work was completed, terminated, or |
|
abandoned. |
|
(b) Except as provided by Subsection (c) or (d) [(b)], a |
|
claimant other than an original contractor [the person] claiming |
|
the lien must file an affidavit with the county clerk [of the county |
|
in which the property is located or into which the railroad extends] |
|
not later than the 15th day of the fourth [calendar] month after the |
|
later of: |
|
(1) the month the claimant last provided labor or |
|
materials; or |
|
(2) the month the claimant would normally have been |
|
required to deliver the last of specially fabricated materials that |
|
have not been actually delivered [day on which the indebtedness |
|
accrues]. |
|
(c) [(b)] A claimant other than an original contractor |
|
[person] claiming a lien arising from a residential construction |
|
project must file an affidavit with the county clerk [of the county |
|
in which the property is located] not later than the 15th day of the |
|
third [calendar] month after the later of: |
|
(1) the month the claimant last provided labor or |
|
materials; or |
|
(2) the month the claimant would normally have been |
|
required to deliver the last of specially fabricated materials that |
|
have not been actually delivered. |
|
(d) A claimant other than an original contractor claiming a |
|
lien for retainage must file an affidavit with the county clerk not |
|
later than the 15th day of the third month after the month in which |
|
the original contract under which the claimant performed was |
|
completed, terminated, or abandoned. |
|
(e) An affidavit under this chapter must be filed in the |
|
county where the improvements are located [day on which the |
|
indebtedness accrues]. |
|
[(c)] The county clerk shall record the affidavit in records |
|
kept for that purpose and shall index and cross-index the affidavit |
|
in the names of the claimant, the original contractor, and the |
|
owner. Failure of the county clerk to properly record or index a |
|
filed affidavit does not invalidate the lien. |
|
SECTION 9. Section 53.055(a), Property Code, is amended to |
|
read as follows: |
|
(a) A person who files an affidavit must send a copy of the |
|
affidavit [by registered or certified mail] to the owner or reputed |
|
owner at the owner's last known business or residence address not |
|
later than the fifth day after the date the affidavit is filed with |
|
the county clerk. |
|
SECTION 10. The heading to Section 53.056, Property Code, |
|
is amended to read as follows: |
|
Sec. 53.056. DERIVATIVE CLAIMANT: NOTICE TO OWNER AND [OR] |
|
ORIGINAL CONTRACTOR. |
|
SECTION 11. Section 53.056, Property Code, is amended by |
|
amending Subsection (a) and adding Subsections (a-1), (a-2), (a-3), |
|
and (a-4) to read as follows: |
|
(a) Except as provided by Section 53.057 [Subchapter K], a |
|
claimant other than an original contractor must give the notice |
|
prescribed by Subsections (a-1) and (a-2) [this section] for the |
|
lien to be valid. |
|
(a-1) For all unpaid labor or materials provided, the |
|
claimant must send a notice of claim for unpaid labor or materials |
|
to the owner or reputed owner and the original contractor. The |
|
notice must be sent: |
|
(1) for projects other than residential construction |
|
projects, not later than the 15th day of the third month after the |
|
month during which: |
|
(A) the labor or materials were provided; or |
|
(B) the undelivered specially fabricated |
|
materials would normally have been delivered; or |
|
(2) for residential construction projects, not later |
|
than the 15th day of the second month after the month during which: |
|
(A) the labor or materials were provided; or |
|
(B) the undelivered specially fabricated |
|
materials would normally have been delivered. |
|
(a-2) The notice must be in substantially the following |
|
form: |
|
"NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS |
|
"WARNING: This notice is provided to preserve lien rights. |
|
"Owner's property may be subject to a lien if sufficient funds are |
|
not withheld from future payments to the original contractor to |
|
cover this debt. |
|
"Date:_______________ |
|
"Project description and/or address: _______________ |
|
"Claimant's name: _______________ |
|
"Type of labor or materials provided: _______________ |
|
"Original contractor's name: _______________ |
|
"Party with whom claimant contracted if different from |
|
original contractor: _______________ |
|
"Claim amount: _______________ |
|
"_______________ (Claimant's contact person) |
|
"_______________ (Claimant's address)" |
|
(a-3) The notice may include an invoice or billing |
|
statement. |
|
(a-4) A claimant may give to the original contractor a |
|
written notice of an unpaid labor or materials invoice that is past |
|
due. A notice under this subsection is not required for a lien to be |
|
valid. |
|
SECTION 12. The heading to Section 53.057, Property Code, |
|
is amended to read as follows: |
|
Sec. 53.057. DERIVATIVE CLAIMANT: NOTICE OF CLAIM FOR |
|
UNPAID [CONTRACTUAL] RETAINAGE [CLAIM]. |
|
SECTION 13. Section 53.057, Property Code, is amended by |
|
amending Subsections (a) and (f) and adding Subsections (a-1), |
|
(a-2), and (a-3) to read as follows: |
|
(a) To the extent that a claim for unpaid retainage is not |
|
included wholly or partly in a notice provided under Section |
|
53.056, a claimant other than an original contractor whose contract |
|
provides for retainage must [A claimant may] give notice under this |
|
section for a lien for unpaid retainage to be valid [instead of or |
|
in addition to notice under Section 53.056 or 53.252 if the claimant |
|
is to labor, furnish labor or materials, or specially fabricate |
|
materials, or has labored, furnished labor or materials, or |
|
specially fabricated materials, under an agreement with an original |
|
contractor or a subcontractor providing for retainage]. |
|
(a-1) The claimant must send the notice of claim for unpaid |
|
retainage to the owner or reputed owner and the original contractor |
|
not later than the earlier of: |
|
(1) the 30th day after the date the claimant's contract |
|
is completed, terminated, or abandoned; or |
|
(2) the 30th day after the date the original contract |
|
is terminated or abandoned. |
|
(a-2) The notice must be in substantially the following |
|
form: |
|
"NOTICE OF CLAIM FOR UNPAID RETAINAGE |
|
"WARNING: This notice is provided to preserve lien rights. |
|
"Owner's property may be subject to a lien if sufficient funds are |
|
not withheld from future payments to the original contractor to |
|
cover this debt. |
|
"Date:________________ |
|
"Project description and/or address: ________________ |
|
"Claimant's name: ________________ |
|
"Type of labor or materials provided: ________________ |
|
"Original contractor's name: ________________ |
|
"Party with whom claimant contracted if different from |
|
original contractor: ________________ |
|
"Total retainage unpaid: ________________ |
|
"________________ (Claimant's contact person) |
|
"________________ (Claimant's address)" |
|
(a-3) The notice may include an invoice or billing |
|
statement. |
|
(f) A claimant has a lien on, and the owner is personally |
|
liable to the claimant for, the reserved [retained] funds under |
|
Subchapter E if the claimant: |
|
(1) gives notice in accordance with this section and: |
|
(A) complies with Subchapter E; or |
|
(B) files an affidavit claiming a lien not later |
|
than [the earliest of: |
|
[(i)] the date required for filing an |
|
affidavit under the applicable provision of Section 53.052[; |
|
[(ii) the 40th day after the date stated in |
|
an affidavit of completion as the date of completion of the work |
|
under the original contract, if the owner sent the claimant notice |
|
of an affidavit of completion in the time and manner required; |
|
[(iii) the 40th day after the date of |
|
termination or abandonment of the original contract, if the owner |
|
sent the claimant a notice of such termination or abandonment in the |
|
time and manner required; or |
|
[(iv) the 30th day after the date the owner |
|
sent to the claimant to the claimant's address provided in the |
|
notice for contractual retainage, as required under Subsection (c), |
|
a written notice of demand for the claimant to file the affidavit |
|
claiming a lien]; and |
|
(2) gives the notice of the filed affidavit as |
|
required by Section 53.055. |
|
SECTION 14. Sections 53.081(a) and (b), Property Code, are |
|
amended to read as follows: |
|
(a) If an owner receives notice under Section 53.056 or [,] |
|
53.057, [53.058, 53.252, or 53.253,] the owner may withhold from |
|
payments to the original contractor an amount necessary to pay the |
|
claim for which he receives notice. The withholding may be in |
|
addition to any reserved funds. |
|
(b) If notice is sent under [in a form that substantially |
|
complies with] Section 53.056 [or 53.252], the owner may withhold |
|
the funds immediately on receipt of the notice. |
|
SECTION 15. Section 53.082, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.082. TIME FOR WHICH FUNDS ARE WITHHELD. Unless |
|
[payment is made under Section 53.083 or] the claim is otherwise |
|
settled, discharged, indemnified against under Subchapter H or I, |
|
or determined to be invalid by a final judgment of a court, the |
|
owner shall retain the funds withheld until: |
|
(1) the time for filing the affidavit of mechanic's |
|
lien has passed; or |
|
(2) if a lien affidavit has been filed, [until] the |
|
lien claim has been satisfied or released. |
|
SECTION 16. Section 53.084, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.084. OWNER'S LIABILITY. (a) Except for the amount |
|
the owner fails to reserve [required to be retained] under |
|
Subchapter E, the owner is not liable for any amount paid to the |
|
original contractor before the owner is authorized to withhold |
|
funds under this subchapter. |
|
(b) If the owner has received a notice [the notices] |
|
required by Section 53.056 or 53.057 [Subchapter C or K], if the |
|
lien has been secured, and if the claim has been reduced to final |
|
judgment, the owner is liable and the owner's property is subject to |
|
a claim for any money paid to the original contractor after the |
|
owner was authorized to withhold funds under this subchapter. The |
|
owner is liable for that amount in addition to any amount for which |
|
the owner [he] is liable under Subchapter E. |
|
SECTION 17. The heading to Subchapter E, Chapter 53, |
|
Property Code, is amended to read as follows: |
|
SUBCHAPTER E. FUNDS RESERVED [REQUIRED RETAINAGE] FOR BENEFIT OF |
|
LIEN CLAIMANTS |
|
SECTION 18. Sections 53.101, 53.102, 53.103, 53.104, and |
|
53.105, Property Code, are amended to read as follows: |
|
Sec. 53.101. FUNDS REQUIRED TO BE RESERVED [RETAINAGE]. |
|
(a) During the progress of work under an original contract for |
|
which a mechanic's lien may be claimed and for 30 days after the |
|
work under the contract is completed, the owner shall reserve |
|
[retain]: |
|
(1) 10 percent of the contract price of the work to the |
|
owner; or |
|
(2) 10 percent of the value of the work, measured by |
|
the proportion that the work done bears to the work to be done, |
|
using the contract price or, if there is no contract price, using |
|
the reasonable value of the completed work. |
|
(b) In this section, "owner" includes the owner's agent, |
|
trustee, or receiver. |
|
Sec. 53.102. PAYMENT SECURED BY RESERVED FUNDS [RETAINAGE]. |
|
The reserved [retained] funds secure the payment of artisans and |
|
mechanics who perform labor or service and the payment of other |
|
persons who furnish material, material and labor, or specially |
|
fabricated material for any contractor, subcontractor, agent, or |
|
receiver in the performance of the work. |
|
Sec. 53.103. LIEN ON RESERVED [RETAINED] FUNDS. A claimant |
|
has a lien on the reserved [retained] funds if the claimant: |
|
(1) sends the notices required by this chapter in the |
|
time and manner required; and |
|
(2) except as allowed by Section 53.057(f), files an |
|
affidavit claiming a lien not later than the 30th day after the |
|
earliest of the date: |
|
(A) the work is completed; |
|
(B) the original contract is terminated; or |
|
(C) the original contractor abandons performance |
|
under the original contract. |
|
Sec. 53.104. PREFERENCES. (a) Individual artisans and |
|
mechanics are entitled to a preference to the reserved [retained] |
|
funds and shall share proportionately to the extent of their claims |
|
for wages and fringe benefits earned. |
|
(b) After payment of artisans and mechanics who are entitled |
|
to a preference under Subsection (a), other participating claimants |
|
share proportionately in the balance of the reserved [retained] |
|
funds. |
|
Sec. 53.105. OWNER'S LIABILITY FOR FAILURE TO RESERVE FUNDS |
|
[RETAIN]. (a) If the owner fails or refuses to comply with this |
|
subchapter, the claimants complying with Subchapter C or this |
|
subchapter have a lien, at least to the extent of the amount that |
|
should have been reserved [retained] from the original contract |
|
under which they are claiming, against the improvements [house, |
|
building, structure, fixture, or improvement] and all of its |
|
properties and against the lot or lots of land necessarily |
|
connected. |
|
(b) The claimants share the lien proportionately in |
|
accordance with the preference provided by Section 53.104. |
|
SECTION 19. Sections 53.106(a), (b), and (d), Property |
|
Code, are amended to read as follows: |
|
(a) An owner may file with the county clerk of the county in |
|
which the property is located an affidavit of completion. The |
|
affidavit must contain: |
|
(1) the name and address of the owner; |
|
(2) the name and address of the original contractor; |
|
(3) a description, legally sufficient for |
|
identification, of the real property on which the improvements are |
|
located; |
|
(4) a description of the improvements furnished under |
|
the original contract; |
|
(5) a statement that the improvements under the |
|
original contract have been completed and the date of completion; |
|
and |
|
(6) a conspicuous statement that a claimant may not |
|
have a lien on retained funds unless the claimant files an affidavit |
|
claiming a lien in the time and manner required by this chapter [not |
|
later than the 40th day after the date the work under the original |
|
contract is completed]. |
|
(b) A copy of the affidavit must be sent [by certified or |
|
registered mail] to the original contractor [not later than the |
|
date the affidavit is filed] and to each claimant who sends a notice |
|
[of lien liability] to the owner under Section 53.056 or [,] 53.057 |
|
[, 53.058, 53.252, or 53.253] not later than the third day after the |
|
date the affidavit is filed or the 10th day after the date the owner |
|
receives the notice of lien liability, whichever is later. |
|
(d) An [Except as provided by this subsection, an] affidavit |
|
filed under this section [on or before the 10th day after the date |
|
of completion of the improvements] is prima facie evidence of the |
|
date the work under the original contract is completed for purposes |
|
of this chapter [subchapter and Section 53.057]. If the affidavit |
|
is filed after the 10th day after the date of completion, the date |
|
of completion for purposes of this subchapter [and Section 53.057] |
|
is the date the affidavit is filed. This subsection does not apply |
|
to a person to whom the affidavit was not sent as required by this |
|
section. |
|
SECTION 20. Sections 53.107(a) and (b), Property Code, are |
|
amended to read as follows: |
|
(a) Not later than the 10th day after the date an original |
|
contract is terminated or the original contractor abandons |
|
performance under the original contract, the owner shall give |
|
notice to each subcontractor who, before the date of termination or |
|
abandonment, has: |
|
(1) given notice to the owner as provided by Section |
|
53.056 or [,] 53.057 [, or 53.058]; or |
|
(2) sent to the owner [by certified or registered |
|
mail] a written request for notice of termination or abandonment. |
|
(b) The notice must contain: |
|
(1) the name and address of the owner; |
|
(2) the name and address of the original contractor; |
|
(3) a description, legally sufficient for |
|
identification, of the real property on which the improvements are |
|
located; |
|
(4) a general description of the improvements agreed |
|
to be furnished under the original contract; |
|
(5) a statement that the original contract has been |
|
terminated or that performance under the contract has been |
|
abandoned; |
|
(6) the date of the termination or abandonment; and |
|
(7) a conspicuous statement that a claimant may not |
|
have a lien on the retained funds unless the claimant files an |
|
affidavit claiming a lien in the time and manner required by this |
|
chapter [not later than the 40th day after the date of the |
|
termination or abandonment]. |
|
SECTION 21. Section 53.155, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.155. TRANSFER OF PROPERTY SOLD. If the [house, |
|
building,] improvement [, or any piece of railroad property] is |
|
sold separately from the land, the officer making the sale shall |
|
provide [place] the purchaser [in possession. The purchaser is |
|
entitled to] a reasonable time after the date of purchase within |
|
which to remove and take possession of the purchased improvement |
|
[property]. |
|
SECTION 22. Section 53.157, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.157. DISCHARGE OF LIEN. An [A mechanic's lien or] |
|
affidavit claiming a mechanic's lien filed under Section 53.052 may |
|
be discharged of record by: |
|
(1) recording a lien release signed by the claimant |
|
under Section 53.152; |
|
(2) failing to institute suit to foreclose the lien in |
|
the county in which the improvement [property] is located within |
|
the period prescribed by Section 53.158, 53.175, or 53.208; |
|
(3) recording the original or certified copy of a |
|
final judgment or decree of a court of competent jurisdiction |
|
providing for the discharge; |
|
(4) filing the bond and notice in compliance with |
|
Subchapter H; |
|
(5) filing the bond in compliance with Subchapter I; |
|
or |
|
(6) recording a certified copy of the order removing |
|
the lien under Section 53.160, provided [and a certificate from the |
|
clerk of the court that states] that no bond or deposit as described |
|
by Section 53.161 was filed by the claimant within 30 days after the |
|
date the order was entered. |
|
SECTION 23. Section 53.158, Property Code, is amended by |
|
amending Subsection (a) and adding Subsections (a-1) and (a-2) to |
|
read as follows: |
|
(a) Except as provided by Subsection (a-2) [(b)], suit must |
|
be brought to foreclose the lien not later than the first |
|
anniversary of [within two years after] the last day a claimant may |
|
file the lien affidavit under Section 53.052 [or within one year |
|
after completion, termination, or abandonment of the work under the |
|
original contract under which the lien is claimed, whichever is |
|
later]. |
|
(a-1) Notwithstanding Section 16.069, Civil Practice and |
|
Remedies Code, or any other law, if suit is pursued solely to |
|
discharge a lien because limitations have expired on bringing a |
|
lien foreclosure suit, the lien claimant's rights to pursue a suit |
|
to foreclose a lien are not revived. |
|
(a-2) The limitations period established under Subsection |
|
(a) may be extended to not later than the second anniversary of the |
|
date the claimant filed the lien affidavit under Section 53.052 if, |
|
before the expiration of the limitations period established under |
|
Subsection (a), the claimant enters into a written agreement with |
|
the then-current record owner of the property to extend the |
|
limitations period. The agreement must be recorded with the clerk |
|
of the same county where the lien was recorded and is considered to |
|
be notice of the extension to any subsequent purchaser. |
|
SECTION 24. Sections 53.160(b) and (c), Property Code, are |
|
amended to read as follows: |
|
(b) The grounds for objecting to the validity or |
|
enforceability of the claim or lien for purposes of the motion are |
|
limited to the following: |
|
(1) notice of claim was not timely furnished to the |
|
owner or original contractor as required by Section 53.056 or [,] |
|
53.057 [, 53.058, 53.252, or 53.253]; |
|
(2) an affidavit claiming a lien failed to comply with |
|
Section 53.054 or was not filed as required by Section 53.052; |
|
(3) notice of the filed affidavit was not furnished to |
|
the owner or original contractor as required by Section 53.055; |
|
(4) the deadlines for perfecting a lien claim for |
|
retainage under this chapter have expired and the owner complied |
|
with the requirements of Section 53.101 and paid the retainage and |
|
all other funds owed to the original contractor before: |
|
(A) the claimant perfected the lien claim; and |
|
(B) the owner received a notice of the claim as |
|
required by this chapter; |
|
(5) all funds subject to the notice of a claim to the |
|
owner and a notice regarding the retainage have been deposited in |
|
the registry of the court and the owner has no additional liability |
|
to the claimant; |
|
(6) when the lien affidavit was filed on homestead |
|
property: |
|
(A) no contract was executed or filed as required |
|
by Section 53.254; |
|
(B) the affidavit claiming a lien failed to |
|
contain the notice as required by Section 53.254; or |
|
(C) the notice of the claim failed to include the |
|
statement required by Section 53.254; and |
|
(7) the claimant executed a valid and enforceable |
|
waiver or release of the claim or lien claimed in the affidavit. |
|
(c) The claimant is not required to file a response. The |
|
claimant and any other party that has appeared in the proceeding |
|
must be notified by at least 30 [21] days before the date of the |
|
hearing on the motion. A motion may not be heard before the 30th |
|
[21st] day after the date the claimant answers or appears in the |
|
proceeding. The claimant must be allowed expedited discovery |
|
regarding information relevant to the issues listed under |
|
Subsection (b). |
|
SECTION 25. Section 53.173(c), Property Code, is amended to |
|
read as follows: |
|
(c) The notice must be served on each obligee by mailing a |
|
copy of the notice and the bond to the obligee by certified [United |
|
States] mail[, return receipt requested,] addressed to the claimant |
|
at the address stated in the lien affidavit for the obligee. |
|
SECTION 26. Section 53.205(a), Property Code, is amended to |
|
read as follows: |
|
(a) The bond protects all persons with a claim that is: |
|
(1) perfected in the manner prescribed for fixing a |
|
lien under Subchapter C [or, if the claim relates to a residential |
|
construction project, under Subchapter K]; or |
|
(2) perfected in the manner prescribed by Section |
|
53.206. |
|
SECTION 27. Section 53.206, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.206. PERFECTION OF CLAIM. (a) Except as provided |
|
by Subsection (b), to [To] perfect a claim against a bond in a |
|
manner other than that prescribed by Subchapter C [or K] for fixing |
|
a lien, a person must [: |
|
[(1)] give notice under Sections 53.056 and 53.057, as |
|
applicable, to the original contractor and surety on the bond [all |
|
applicable notices under the appropriate subchapter; and |
|
[(2) give to the surety on the bond, instead of the |
|
owner, all notices under the appropriate subchapter required to be |
|
given to the owner]. |
|
(b) To perfect a claim for retainage under this section, a |
|
claimant [person] is not required to[: |
|
[(1)] give notice to the surety under Section 53.057 |
|
if [, unless] the claimant has a direct contractual relationship |
|
with the original contractor [and the agreed retainage is in excess |
|
of 10 percent of the contract; |
|
[(2) give notice to the surety under Section 53.058(b) |
|
or, if the claim relates to a residential construction project, |
|
under Section 53.253(c); or |
|
[(3) file any affidavit with the county clerk]. |
|
(c) A claimant that provides the notices described by this |
|
section is not required to file an affidavit claiming a mechanic's |
|
lien to perfect a claim under the bond [For the claim to be valid, a |
|
person must give notice in the time and manner required by this |
|
section, but the content of the notices need only provide fair |
|
notice of the amount and the nature of the claim asserted]. |
|
(d) A person satisfies the requirements of this section |
|
relating to providing notice to the surety if the person mails the |
|
notice by certified [or registered] mail to the surety: |
|
(1) at the address stated on the bond or on an |
|
attachment to the bond; |
|
(2) at the address on file with the Texas Department of |
|
Insurance; or |
|
(3) at any other address allowed by law. |
|
SECTION 28. Section 53.207(a), Property Code, is amended to |
|
read as follows: |
|
(a) If the owner receives any of the notices or a lien is |
|
fixed under this chapter [Subchapter C or K], the owner shall mail |
|
to the surety on the bond a copy of all notices received. |
|
SECTION 29. Section 53.208(a), Property Code, is amended to |
|
read as follows: |
|
(a) A claimant may sue the principal and surety on the bond |
|
either jointly or severally, if the [his] claim remains unpaid for |
|
60 days after the claimant perfects the claim. |
|
SECTION 30. Section 53.232, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.232. TO WHOM NOTICE GIVEN; MANNER. The lien |
|
claimant must send written notice of his claim by [registered or] |
|
certified mail to: |
|
(1) the officials of the state, county, town, or |
|
municipality whose duty it is to pay the contractor; and |
|
(2) the contractor at the contractor's last known |
|
business or residence address. |
|
SECTION 31. Section 53.238, Property Code, is amended to |
|
read as follows: |
|
Sec. 53.238. NOTICE OF BOND. The official with whom the |
|
bond is filed shall send an exact copy of the bond by [registered |
|
mail or] certified mail, return receipt requested, to all |
|
claimants. |
|
SECTION 32. The heading to Section 53.254, Property Code, |
|
is amended to read as follows: |
|
Sec. 53.254. CONTRACTUAL REQUIREMENTS FOR LIEN ON |
|
HOMESTEAD. |
|
SECTION 33. Section 53.254(g), Property Code, is amended to |
|
read as follows: |
|
(g) For the lien on a homestead to be valid, the notice |
|
required to be given to the owner under Subchapter C [Section |
|
53.252] must include or have attached the following statement: |
|
"If a subcontractor or supplier who furnishes materials or |
|
performs labor for construction of improvements on your property is |
|
not paid, your property may be subject to a lien for the unpaid |
|
amount if: |
|
(1) after receiving notice of the unpaid claim from |
|
the claimant, you fail to withhold payment to your contractor that |
|
is sufficient to cover the unpaid claim until the dispute is |
|
resolved; or |
|
(2) during construction and for 30 days after |
|
completion of your contractor's work [construction], you fail to |
|
reserve [retain] 10 percent of the contract price or 10 percent of |
|
the value of the work performed by your contractor. |
|
"If you have complied with the law regarding the reservation |
|
of 10 percent of the contract price or value of work [retainage] and |
|
you have withheld payment to the contractor sufficient to cover any |
|
written notice of claim and have paid that amount, if any, to the |
|
claimant, any lien claim filed on your property by a subcontractor |
|
or supplier, other than a person who contracted directly with you, |
|
will not be a valid lien on your property. In addition, except for |
|
the required 10 percent reservation [retainage], you are not liable |
|
to a subcontractor or supplier for any amount paid to your |
|
contractor before you received written notice of the claim." |
|
SECTION 34. Section 53.255(b), Property Code, is amended to |
|
read as follows: |
|
(b) The disclosure statement must read substantially |
|
similar to the following: |
|
"KNOW YOUR RIGHTS AND RESPONSIBILITIES UNDER THE LAW. You |
|
are about to enter into a transaction to build a new home or remodel |
|
existing residential property. Texas law requires your contractor |
|
to provide you with this brief overview of some of your rights, |
|
responsibilities, and risks in this transaction. |
|
"CONVEYANCE TO CONTRACTOR NOT REQUIRED. Your contractor may |
|
not require you to convey your real property to your contractor as a |
|
condition to the agreement for the construction of improvements on |
|
your property. |
|
"KNOW YOUR CONTRACTOR. Before you enter into your agreement |
|
for the construction of improvements to your real property, make |
|
sure that you have investigated your contractor. Obtain and verify |
|
references from other people who have used the contractor for the |
|
type and size of construction project on your property. |
|
"GET IT IN WRITING. Make sure that you have a written |
|
agreement with your contractor that includes: (1) a description of |
|
the work the contractor is to perform; (2) the required or |
|
estimated time for completion of the work; (3) the cost of the work |
|
or how the cost will be determined; and (4) the procedure and |
|
method of payment, including provisions for statutory reservation |
|
of funds [retainage] and conditions for final payment. If your |
|
contractor made a promise, warranty, or representation to you |
|
concerning the work the contractor is to perform, make sure that |
|
promise, warranty, or representation is specified in the written |
|
agreement. An oral promise that is not included in the written |
|
agreement may not be enforceable under Texas law. |
|
"READ BEFORE YOU SIGN. Do not sign any document before you |
|
have read and understood it. NEVER SIGN A DOCUMENT THAT INCLUDES AN |
|
UNTRUE STATEMENT. Take your time in reviewing documents. If you |
|
borrow money from a lender to pay for the improvements, you are |
|
entitled to have the loan closing documents furnished to you for |
|
review at least one business day before the closing. Do not waive |
|
this requirement unless a bona fide emergency or another good cause |
|
exists, and make sure you understand the documents before you sign |
|
them. If you fail to comply with the terms of the documents, you |
|
could lose your property. You are entitled to have your own |
|
attorney review any documents. If you have any question about the |
|
meaning of a document, consult an attorney. |
|
"GET A LIST OF SUBCONTRACTORS AND SUPPLIERS. Before |
|
construction commences, your contractor is required to provide you |
|
with a list of the subcontractors and suppliers the contractor |
|
intends to use on your project. Your contractor is required to |
|
supply updated information on any subcontractors and suppliers |
|
added after the list is provided. Your contractor is not required |
|
to supply this information if you sign a written waiver of your |
|
rights to receive this information. |
|
"MONITOR THE WORK. Lenders and governmental authorities may |
|
inspect the work in progress from time to time for their own |
|
purposes. These inspections are not intended as quality control |
|
inspections. Quality control is a matter for you and your |
|
contractor. To ensure that your home is being constructed in |
|
accordance with your wishes and specifications, you should inspect |
|
the work yourself or have your own independent inspector review the |
|
work in progress. |
|
"MONITOR PAYMENTS. If you use a lender, your lender is |
|
required to provide you with a periodic statement showing the money |
|
disbursed by the lender from the proceeds of your loan. Each time |
|
your contractor requests payment from you or your lender for work |
|
performed, your contractor is also required to furnish you with a |
|
disbursement statement that lists the name and address of each |
|
subcontractor or supplier that the contractor intends to pay from |
|
the requested funds. Review these statements and make sure that the |
|
money is being properly disbursed. |
|
"CLAIMS BY SUBCONTRACTORS AND SUPPLIERS. Under Texas law, if |
|
a subcontractor or supplier who furnishes labor or materials for |
|
the construction of improvements on your property is not paid, you |
|
may become liable and your property may be subject to a lien for the |
|
unpaid amount, even if you have not contracted directly with the |
|
subcontractor or supplier. To avoid liability, you should take the |
|
following actions: |
|
(1) If you receive a written notice from a |
|
subcontractor or supplier, you should withhold payment from your |
|
contractor for the amount of the claim stated in the notice until |
|
the dispute between your contractor and the subcontractor or |
|
supplier is resolved. If your lender is disbursing money directly |
|
to your contractor, you should immediately provide a copy of the |
|
notice to your lender and instruct the lender to withhold payment in |
|
the amount of the claim stated in the notice. If you continue to pay |
|
the contractor after receiving the written notice without |
|
withholding the amount of the claim, you may be liable and your |
|
property may be subject to a lien for the amount you failed to |
|
withhold. |
|
(2) During construction and for 30 days after final |
|
completion, termination, or abandonment of the contract by the |
|
contractor, you should reserve [withhold] or cause your lender to |
|
reserve [withhold] 10 percent of the amount of payments made for the |
|
work performed by your contractor. [This is sometimes referred to |
|
as 'statutory retainage.'] If you choose not to reserve [withhold] |
|
the 10 percent for at least 30 days after final completion, |
|
termination, or abandonment of the contract by the contractor and |
|
if a valid claim is timely made by a claimant and your contractor |
|
fails to pay the claim, you may be personally liable and your |
|
property may be subject to a lien up to the amount that you failed to |
|
reserve [withhold]. |
|
"If a claim is not paid within a certain time period, the |
|
claimant is required to file a mechanic's lien affidavit in the real |
|
property records in the county where the property is located. A |
|
mechanic's lien affidavit is not a lien on your property, but the |
|
filing of the affidavit could result in a court imposing a lien on |
|
your property if the claimant is successful in litigation to |
|
enforce the lien claim. |
|
"SOME CLAIMS MAY NOT BE VALID. When you receive a written |
|
notice of a claim or when a mechanic's lien affidavit is filed on |
|
your property, you should know your legal rights and |
|
responsibilities regarding the claim. Not all claims are valid. A |
|
notice of a claim by a subcontractor or supplier is required to be |
|
sent, and the mechanic's lien affidavit is required to be filed, |
|
within strict time periods. The notice and the affidavit must |
|
contain certain information. All claimants may not fully comply |
|
with the legal requirements to collect on a claim. If you have paid |
|
the contractor in full before receiving a notice of a claim and have |
|
withheld the 10 percent of the contract price or value of work |
|
[fully complied with the law regarding statutory retainage], you |
|
may not be liable for that claim. Accordingly, you should consult |
|
your attorney when you receive a written notice of a claim to |
|
determine the true extent of your liability or potential liability |
|
for that claim. |
|
"OBTAIN A LIEN RELEASE AND A BILLS-PAID AFFIDAVIT. When you |
|
receive a notice of claim, do not release withheld funds without |
|
obtaining a signed and notarized release of lien and claim from the |
|
claimant. You can also reduce the risk of having a claim filed by a |
|
subcontractor or supplier by requiring as a condition of each |
|
payment made by you or your lender that your contractor furnish you |
|
with an affidavit stating that all bills have been paid. Under |
|
Texas law, on final completion of the work and before final payment, |
|
the contractor is required to furnish you with an affidavit stating |
|
that all bills have been paid. If the contractor discloses any |
|
unpaid bill in the affidavit, you should withhold payment in the |
|
amount of the unpaid bill until you receive a waiver of lien or |
|
release from that subcontractor or supplier. |
|
"OBTAIN TITLE INSURANCE PROTECTION. You may be able to obtain |
|
a title insurance policy to insure that the title to your property |
|
and the existing improvements on your property are free from liens |
|
claimed by subcontractors and suppliers. If your policy is issued |
|
before the improvements are completed and covers the value of the |
|
improvements to be completed, you should obtain, on the completion |
|
of the improvements and as a condition of your final payment, |
|
a 'completion of improvements' policy endorsement. This |
|
endorsement will protect your property from liens claimed by |
|
subcontractors and suppliers that may arise from the date the |
|
original title policy is issued to the date of the endorsement." |
|
SECTION 35. Section 53.281(b), Property Code, is amended to |
|
read as follows: |
|
(b) A waiver and release is effective to release the owner, |
|
the owner's property, the contractor, and the surety on a payment |
|
bond from claims and liens only if: |
|
(1) the waiver and release substantially complies with |
|
one of the forms prescribed by Section 53.284; |
|
(2) the waiver and release is signed by the claimant or |
|
the claimant's authorized agent [and notarized]; and |
|
(3) in the case of a conditional release, evidence of |
|
payment to the claimant exists. |
|
SECTION 36. The following provisions of the Property Code |
|
are repealed: |
|
(1) Section 53.003(a); |
|
(2) Section 53.026(b); |
|
(3) Section 53.053; |
|
(4) Sections 53.056(b), (c), (d), (e), and (f); |
|
(5) Sections 53.057(b), (b-1), (c), (d), (e), and (g); |
|
(6) Section 53.058; |
|
(7) Section 53.081(d); |
|
(8) Section 53.083; |
|
(9) Section 53.158(b); and |
|
(10) Sections 53.252 and 53.253. |
|
SECTION 37. The changes in law made by this Act apply only |
|
to an original contract entered into on or after the effective date |
|
of this Act. An original contract entered into before the effective |
|
date of this Act is governed by the law as it existed immediately |
|
before the effective date of this Act, and that law is continued in |
|
effect for that purpose. |
|
SECTION 38. This Act takes effect January 1, 2022. |
|
|
|
* * * * * |