A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the generation of electricity in this state. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter A, Chapter 35, Utilities Code, is |
|
amended by adding Section 35.0021 to read as follows: |
|
Sec. 35.0021. MAINTENANCE OF GENERATION ASSETS; CAPACITY |
|
FORECAST REPORTS. The commission by rule shall require each |
|
provider of generation in the ERCOT power region to: |
|
(1) submit to the commission annual maintenance plans |
|
showing how the provider will maintain generation assets; |
|
(2) periodically inspect and maintain generation |
|
assets to ensure that the assets can withstand extreme weather |
|
conditions; and |
|
(3) report to the independent organization certified |
|
under Section 39.151 for the ERCOT power region annual forecasts of |
|
the provider's generation capacity for a five-year period beginning |
|
with the year following the year in which the forecast is submitted. |
|
SECTION 2. Section 39.351, Utilities Code, is amended by |
|
adding Subsection (d) to read as follows: |
|
(d) The commission shall require a person registered under |
|
this section who operates a natural gas generation facility to |
|
maintain at the site of the facility an amount of natural gas as a |
|
reserve that will allow the facility to provide generation for at |
|
least 48 hours that equals at least 10 percent of the net dependable |
|
capability of the facility in the event of a natural gas shortage. |
|
In this subsection, "net dependable capability" means the maximum |
|
load in megawatts, net of station use, which a generating unit or |
|
generating station can carry under specified conditions for a given |
|
period of time, without exceeding approved limits of temperature |
|
and stress. |
|
SECTION 3. Not later than September 1, 2022, the Public |
|
Utility Commission of Texas shall submit a report to the |
|
legislature on the potential costs and benefits of establishing an |
|
emergency strategic electric energy reserve in this state. The |
|
report must evaluate the feasibility of establishing a state |
|
natural gas reserve and of constructing state-owned power plants. |
|
SECTION 4. This Act takes effect September 1, 2021. |