A BILL TO BE ENTITLED
|
|
AN ACT
|
|
|
relating to energy savings performance contracts. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 302.001(4), Local Government Code, is |
|
amended to read as follows: |
|
(4) "Energy savings performance contract" means a |
|
contract with a provider for energy or water conservation or usage |
|
measures in which the estimated energy savings, utility cost |
|
savings, increase in billable revenues, or increase in meter |
|
accuracy resulting from the measures is subject to guarantee to |
|
offset the cost of the energy or water conservation or usage |
|
measures over a specified period. The term does not include the |
|
design or new construction of a water supply project, water plant, |
|
wastewater plant, water and wastewater distribution or conveyance |
|
facility, or drainage project. The term includes a contract |
|
related to the pilot program described by Subdivision (9-a) and a |
|
contract for the installation or implementation of the following in |
|
new or existing facilities, including all causally connected work: |
|
(A) insulation of a building structure and |
|
systems within the building; |
|
(B) storm windows or doors, caulking or weather |
|
stripping, multiglazed windows or doors, heat-absorbing or |
|
heat-reflective glazed and coated window or door systems, or other |
|
window or door system modifications that reduce energy consumption; |
|
(C) automatic energy control systems, including |
|
computer software and technical data licenses; |
|
(D) heating, ventilating, or air-conditioning |
|
system modifications or replacements that reduce energy or water |
|
consumption; |
|
(E) lighting fixtures that increase energy |
|
efficiency; |
|
(F) energy recovery systems; |
|
(G) electric systems improvements; |
|
(H) water-conserving fixtures, appliances, and |
|
equipment or the substitution of non-water-using fixtures, |
|
appliances, and equipment; |
|
(I) water-conserving landscape irrigation |
|
equipment; |
|
(J) landscaping measures that reduce watering |
|
demands and capture and hold applied water and rainfall, including: |
|
(i) landscape contouring, including the use |
|
of berms, swales, and terraces; and |
|
(ii) the use of soil amendments that |
|
increase the water-holding capacity of the soil, including compost; |
|
(K) rainwater harvesting equipment and equipment |
|
to make use of water collected as part of a storm-water system |
|
installed for water quality control; |
|
(L) equipment for recycling or reuse of water |
|
originating on the premises or from other sources, including |
|
treated municipal effluent; |
|
(M) equipment needed to capture water from |
|
nonconventional, alternate sources, including air-conditioning |
|
condensate or graywater, for nonpotable uses; |
|
(N) metering or related equipment or systems that |
|
improve the accuracy of billable-revenue-generation systems; |
|
(O) alternative fuel programs resulting in |
|
energy cost savings and reduced emissions for local government |
|
vehicles, including fleet vehicles; |
|
(P) programs resulting in utility cost savings; |
|
or |
|
(Q) other energy or water conservation-related |
|
improvements or equipment, including improvements or equipment |
|
relating to renewable energy or nonconventional water sources or |
|
water reuse. |
|
SECTION 2. Section 302.005, Local Government Code, is |
|
amended by adding Subsections (d) and (e) to read as follows: |
|
(d) The scope of an energy savings performance contract may |
|
not be modified under this section by change order, contract |
|
addendum, or other method: |
|
(1) to perform work that is not related to, connected |
|
with, or otherwise ancillary to the measures identified in the |
|
original scope of an energy savings performance contract; or |
|
(2) in a way that increases the price of the original |
|
awarded contract by more than 25 percent of the original contract |
|
value. |
|
(e) Subsection (d) applies only to the design or |
|
construction of a water supply project, water plant, wastewater |
|
plant, water and wastewater distribution or conveyance facility, or |
|
drainage project. |
|
SECTION 3. Chapter 302, Local Government Code, is amended |
|
by adding Section 302.008 to read as follows: |
|
Sec. 302.008. ENFORCEMENT. (a) A contract entered into or |
|
an arrangement made in violation of this chapter is voidable as |
|
against public policy. |
|
(b) This chapter may be enforced through an action for |
|
declaratory or injunctive relief filed not later than the 10th day |
|
after the date the contract is awarded. |
|
SECTION 4. The changes in law made by this Act do not apply |
|
to an energy savings performance contract entered into before the |
|
effective date of this Act, and the former law governing the |
|
contract is continued in effect for that purpose. |
|
SECTION 5. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2021. |
|
|
|
* * * * * |