A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to cost recovery for costs arising from the |
|
interconnection of certain electric generation facilities with the |
|
ERCOT transmission system. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 35.004, Utilities Code, is amended by |
|
amending Subsection (d) and adding Subsection (d-1) to read as |
|
follows: |
|
(d) The commission shall price wholesale transmission |
|
services within ERCOT based on the postage stamp method of pricing |
|
under which a transmission-owning utility's rate is based on the |
|
ERCOT utilities' combined annual costs of transmission, other than |
|
costs described in Subsection (d-1), divided by the total demand |
|
placed on the combined transmission systems of all such |
|
transmission-owning utilities within a power region. An electric |
|
utility subject to the freeze period imposed by Section 39.052 may |
|
treat transmission costs in excess of transmission revenues during |
|
the freeze period as an expense for purposes of determining annual |
|
costs in the annual report filed under Section 39.257. |
|
Notwithstanding Section 36.201, the commission may approve |
|
wholesale rates that may be periodically adjusted to ensure timely |
|
recovery of transmission investment. Notwithstanding Section |
|
36.054(a), if the commission determines that conditions warrant the |
|
action, the commission may authorize the inclusion of construction |
|
work in progress in the rate base for transmission investment |
|
required by the commission under Section 39.203(e). |
|
(d-1) Capital costs incurred to interconnect with the ERCOT |
|
transmission system generation resources and electric energy |
|
storage resources described by Section 35.152(a), including costs |
|
of utility interconnection facilities and all necessary system |
|
upgrades, must be directly assigned by the ERCOT independent system |
|
operator to the generation resource or electric energy storage |
|
resource receiving interconnection service through the facilities. |
|
SECTION 2. This Act takes effect September 1, 2021. |