A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the recovery of fuel and purchased power costs by |
|
electric utilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 36.203, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 36.203. FUEL AND PURCHASED POWER COST RECOVERY; |
|
ADJUSTMENT OF FUEL FACTOR. (a) Section 36.201 does not prohibit |
|
the commission from reviewing and providing for adjustments of an |
|
electric [a] utility's fuel factor. |
|
(b) The commission by rule shall implement procedures that |
|
provide for the timely adjustment of an electric [a] utility's fuel |
|
factor[, with or without a hearing]. The rules [procedures] must |
|
require that[: |
|
[(1)] the findings required by Section 36.058 |
|
regarding fuel transactions with affiliated interests be [are] made |
|
in a fuel reconciliation proceeding or in a rate case filed under |
|
Subchapter C or D. The rules must ensure that: |
|
(1) the utility collects as contemporaneously as |
|
reasonably possible the electric fuel and purchased power costs |
|
that the utility incurs and that the commission determines are |
|
eligible; |
|
(2) the total of the utility's eligible electric fuel |
|
and purchased power costs, including any under-collected or |
|
over-collected amounts to be recovered through an interim fuel |
|
adjustment, is allocated among customer classes based on actual |
|
historical calendar month usage; |
|
(3) any material balance of amounts under-collected or |
|
over-collected for eligible electric fuel and purchased power costs |
|
is collected from or refunded to customers through an interim fuel |
|
adjustment: |
|
(A) not later than the 90th day after the date the |
|
balance is accrued; or |
|
(B) if the adjustment would result in a total |
|
bill increase of 10 percent or more compared to the total bill in |
|
the month before implementation, not later than a date ordered by |
|
the commission which must be after the 90th day after the date the |
|
balance is accrued; and |
|
(4)[; and |
|
[(2)] an affected party will receive notice and have |
|
the opportunity to request a hearing before the commission. |
|
(c) Notwithstanding Subsection (b)(3), on a finding that an |
|
electric utility has an under-collected balance that is the result |
|
of extraordinary electric fuel and purchased power costs that are |
|
unlikely to continue, the commission may approve an interim fuel |
|
adjustment that would defer recovery to take place over a period |
|
longer than 90 days [The commission may adjust a utility's fuel |
|
factor without a hearing if the commission determines that a |
|
hearing is not necessary. If the commission holds a hearing, the |
|
commission may consider at the hearing any evidence that is |
|
appropriate and in the public interest]. |
|
(d) The commission is not required to hold a hearing on the |
|
adjustment of an electric utility's fuel factor under this section. |
|
If the commission holds a hearing, the commission may consider at |
|
the hearing any evidence that is appropriate and in the public |
|
interest [The commission shall render a timely decision approving, |
|
disapproving, or modifying the adjustment to the utility's fuel |
|
factor]. |
|
(e) A customer of the electric utility, a municipality with |
|
original jurisdiction over the utility, or the office may protest a |
|
fuel factor or interim fuel adjustment proposed under this section. |
|
The prudence of costs may not be considered in a fuel factor or |
|
interim fuel adjustment proceeding and may only be considered in a |
|
fuel reconciliation proceeding under Subsection (h) or another |
|
appropriate proceeding [The commission by rule shall provide for |
|
the reconciliation of a utility's fuel costs on a timely basis]. |
|
(f) The sole issue that may be considered on a protest of a |
|
fuel factor under Subsection (e) is whether the factor reasonably |
|
reflects costs the electric utility will incur so that the utility |
|
will not substantially under-collect or over-collect the utility's |
|
reasonably stated fuel and purchased power costs on an ongoing |
|
basis. The commission may adjust the utility's fuel factor based on |
|
its determination on that issue. |
|
(g) The commission shall hold a hearing on a protest of an |
|
interim fuel adjustment under Subsection (e) if the adjustment |
|
would result in a total bill increase of 10 percent or more as |
|
described by Subsection (b)(3) or if the adjustment results from |
|
extraordinary electric fuel and purchased power costs as described |
|
by Subsection (c). In response to a protest of an interim fuel |
|
adjustment, if the commission finds that the electric utility is in |
|
a state of material under-collection or over-collection of the |
|
utility's reasonably stated eligible fuel and purchased power costs |
|
and is projected to remain in that state on an ongoing basis, the |
|
commission shall order the utility to establish or modify an |
|
interim fuel adjustment to address the under-collection or |
|
over-collection in a manner consistent with this section. |
|
(h) An electric utility shall apply to reconcile the |
|
utility's electric fuel and purchased power costs at least once |
|
every two years. The application must be made not later than the |
|
180th day after the last day of the period to be reconciled. The |
|
commission may by rule establish the calendar year timing of the |
|
reconciliation period for each electric utility subject to this |
|
section to facilitate efficient work by the commission. To the |
|
extent a reconciliation results in a change to the electric |
|
utility's under-collected or over-collected fuel balance, that |
|
change may be incorporated into an interim fuel adjustment as |
|
directed by the commission. |
|
(i) A proceeding under this section is not a rate case under |
|
Subchapter C. |
|
SECTION 2. The first time an electric utility applies to |
|
reconcile the utility's fuel costs and purchased power costs under |
|
Section 36.203(h), Utilities Code, as added by this Act, after the |
|
Public Utility Commission of Texas adopts the rules required to |
|
implement that subsection, the electric utility shall include in |
|
the application any period that has not been addressed in a previous |
|
reconciliation proceeding. |
|
SECTION 3. This Act takes effect September 1, 2023. |