A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the reliability of the ERCOT power grid. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. The heading to Section 39.159, Utilities Code, |
|
as added by Chapter 426 (S.B. 3), Acts of the 87th Legislature, |
|
Regular Session, 2021, is amended to read as follows: |
|
Sec. 39.159. POWER REGION RELIABILITY AND DISPATCHABLE |
|
GENERATION. |
|
SECTION 2. Section 39.159, Utilities Code, as added by |
|
Chapter 426 (S.B. 3), Acts of the 87th Legislature, Regular |
|
Session, 2021, is amended by amending Subsection (b) and adding |
|
Subsections (b-1) and (d) to read as follows: |
|
(b) The commission shall ensure that the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region: |
|
(1) establishes requirements to meet the reliability |
|
needs of the power region; |
|
(2) periodically, but at least annually, determines |
|
the quantity and characteristics of ancillary or reliability |
|
services necessary to ensure appropriate reliability during |
|
extreme heat and extreme cold weather conditions and during times |
|
of low non-dispatchable power production in the power region; |
|
(3) procures ancillary or reliability services on a |
|
competitive basis to ensure appropriate reliability during extreme |
|
heat and extreme cold weather conditions and during times of low |
|
non-dispatchable power production in the power region; |
|
(4) develops appropriate qualification and |
|
performance requirements for providing services under Subdivision |
|
(3), including appropriate penalties for failure to provide the |
|
services; [and] |
|
(5) sizes the services procured under Subdivision (3) |
|
to prevent prolonged rotating outages due to net load variability |
|
in high demand and low supply scenarios; and |
|
(6) allocates the cost of providing ancillary services |
|
and reliability services procured under this section on an annual |
|
basis among dispatchable generation facilities, non-dispatchable |
|
generation facilities, and load serving entities in proportion to |
|
their contribution to net load variability over the highest 100 |
|
hours of net load in the preceding year as follows: |
|
(A) for dispatchable generation facilities, the |
|
difference between the mean of the highest quartile forced outage |
|
rate for the facility and the mean forced outage rate of all |
|
dispatchable generation facilities in the ERCOT power region; |
|
(B) for non-dispatchable generation facilities, |
|
the difference between the mean of the lowest quartile generation |
|
for each non-dispatchable generation facility, divided by the |
|
installed capacity of that facility, and the mean generation of all |
|
non-dispatchable generation facilities in the ERCOT power region, |
|
divided by the total installed capacity of all non-dispatchable |
|
generation facilities in the ERCOT power region; and |
|
(C) for load serving entities, the difference |
|
between the mean of the highest quartile of each entity's metered |
|
load and the mean of each entity's metered load. |
|
(b-1) Subsection (b)(6) applies only to a generation |
|
facility or load serving entity that has participated in the ERCOT |
|
market for at least one year. |
|
(d) The commission shall require the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region to develop an ancillary services program that requires load |
|
serving entities to purchase dispatchable reliability reserve |
|
services on a day-ahead basis to account for market uncertainty. |
|
The program must provide payments only to generation resources that |
|
are not providing other ancillary services. The commission must |
|
require the independent organization to: |
|
(1) determine the quantity of services necessary based |
|
on historical variations in generation availability for each season |
|
based on a targeted reliability standard or goal, including |
|
renewable intermittency and forced outage rates; and |
|
(2) develop criteria for resource participation that |
|
require a resource to: |
|
(A) have a runtime of at least four hours; |
|
(B) be available not less than two hours after |
|
being called on for deployment; and |
|
(C) have the dispatchable flexibility to address |
|
inter-hour operational challenges. |
|
SECTION 3. Subchapter D, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.1591 to read as follows: |
|
Sec. 39.1591. REPORT ON DISPATCHABLE AND NON-DISPATCHABLE |
|
GENERATION FACILITIES. The commission shall file an annual report |
|
with the legislature that: |
|
(1) includes: |
|
(A) the estimated annual costs required to be |
|
incurred under this subchapter by non-dispatchable generators to |
|
guarantee that a firm amount of electric energy will be provided for |
|
the ERCOT power grid; and |
|
(B) the cumulative annual transmission costs |
|
that have been incurred in the ERCOT market to facilitate the |
|
transmission of non-dispatchable electricity to load; |
|
(2) documents the status of the implementation of this |
|
subchapter, including whether the rules and protocols adopted to |
|
implement this subchapter have materially improved the |
|
reliability, resilience, and transparency of the electricity |
|
market; and |
|
(3) includes recommendations for any additional |
|
legislative measures needed to empower the commission to implement |
|
market reforms to ensure that market signals are adequate to |
|
preserve existing dispatchable generation and incentivize the |
|
construction of new dispatchable generation sufficient to maintain |
|
reliability standards for at least five years after the date of the |
|
report. |
|
SECTION 4. (a) Not later than September 1, 2024, the |
|
Public Utility Commission of Texas shall implement the changes in |
|
law made by this Act to Section 39.159(b), Utilities Code, as added |
|
by Chapter 426 (S.B. 3), Acts of the 87th Legislature, Regular |
|
Session, 2021. |
|
(b) Not later than December 1, 2024, the Public Utility |
|
Commission of Texas shall implement the changes in law made by this |
|
Act in Section 39.159(d), Utilities Code, as added by this Act. |
|
(c) The Public Utility Commission of Texas shall prepare the |
|
portion of the first report required by Section 39.1591(1), |
|
Utilities Code, as added by this Act, not later than December 1, |
|
2023. |
|
(d) The Public Utility Commission of Texas shall prepare the |
|
portions of the first report required by Sections 39.1591(2) and |
|
(3), Utilities Code, as added by this Act, not later than December |
|
1, 2024. |
|
SECTION 5. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2023. |