A BILL TO BE ENTITLED
|
|
AN ACT
|
|
|
relating to the cost of interconnecting certain electric generation |
|
facilities with the ERCOT transmission system. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 35.004, Utilities Code, is amended by |
|
amending Subsection (d) and adding Subsections (d-1), (d-2), and |
|
(d-3) to read as follows: |
|
(d) The commission shall price wholesale transmission |
|
services within ERCOT based on the postage stamp method of pricing |
|
under which a transmission-owning utility's rate is based on the |
|
ERCOT utilities' combined annual costs of transmission, other than |
|
costs described by Subsections (d-2) and (d-3), divided by the |
|
total demand placed on the combined transmission systems of all |
|
such transmission-owning utilities within a power region. An |
|
electric utility subject to the freeze period imposed by Section |
|
39.052 may treat transmission costs in excess of transmission |
|
revenues during the freeze period as an expense for purposes of |
|
determining annual costs in the annual report filed under Section |
|
39.257. Notwithstanding Section 36.201, the commission may approve |
|
wholesale rates that may be periodically adjusted to ensure timely |
|
recovery of transmission investment. Notwithstanding Section |
|
36.054(a), if the commission determines that conditions warrant the |
|
action, the commission may authorize the inclusion of construction |
|
work in progress in the rate base for transmission investment |
|
required by the commission under Section 39.203(e). |
|
(d-1) The commission by rule shall establish a reasonable |
|
allowance to be applied on a per megawatt basis for costs incurred |
|
to interconnect generation resources directly with the ERCOT |
|
transmission system at transmission voltage, including costs of |
|
utility interconnection facilities. The allowance must: |
|
(1) take into account: |
|
(A) average historical dispatchable generation |
|
interconnection costs; and |
|
(B) the reliability impact to the grid of the |
|
interconnecting resource and whether the interconnecting resource |
|
increases reliability or volatility in managing the grid; and |
|
(2) be designed to lower costs to consumers and |
|
encourage owners of generation resources to locate the resources |
|
closer to load. |
|
(d-2) Costs in excess of the allowance provided by |
|
Subsection (d-1) incurred to interconnect generation resources |
|
with the ERCOT transmission system, including costs of utility |
|
interconnection facilities, must be directly assigned to and |
|
collected from the generation resource interconnecting through the |
|
facilities. |
|
(d-3) Not later than September 1 of every fifth year after |
|
2023, the commission shall review and may adjust the allowance |
|
provided by Subsection (d-1) to account for inflation or supply |
|
chain issues. |
|
SECTION 2. This Act takes effect September 1, 2023. |
|
|
|
* * * * * |