88R28177 JXC-D
 
  By: Johnson, et al. S.B. No. 1929
 
  (Dean)
 
  Substitute the following for S.B. No. 1929:  No.
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the registration of virtual currency mining facilities
  in the ERCOT power region that demand a large load of interruptible
  power.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter H, Chapter 39, Utilities Code, is
  amended by adding Section 39.360 to read as follows:
         Sec. 39.360.  LARGE FLEXIBLE LOAD REGISTRATION.  (a)  In this
  section:
               (1)  "Virtual currency" has the meaning assigned by
  Section 12.001, Business & Commerce Code.
               (2)  "Virtual currency mining facility" means a
  facility that uses electronic equipment to add virtual currency
  transactions to a distributed ledger.
         (b)  The commission by rule shall require a person operating
  a virtual currency mining facility who enters into an agreement for
  retail electric service in the ERCOT power region to register the
  facility receiving service as a large flexible load under this
  section if:
               (1)  the person anticipates that the facility will
  require a total load of more than 75 megawatts before the second
  anniversary of the date the agreement begins; and
               (2)  the facility load is interruptible.
         (c)  The rules must require a person described by Subsection
  (b) to:
               (1)  register the large flexible load with the
  commission not later than one business day after the date the
  agreement begins; and
               (2)  provide the commission with:
                     (A)  the location of the facility; and
                     (B)  the anticipated demand from the facility for
  the five-year period beginning on the date of the registration.
         (d)  The commission by rule shall:
               (1)  adopt criteria for determining whether a load is
  interruptible for the purposes of this section based on whether it
  is possible for the facility operator to choose to interrupt the
  load; and
               (2)  establish a method to ensure compliance with this
  section.
         (e)  The commission may share with an independent
  organization certified under Section 39.151 registration
  information received under this section.
         SECTION 2.  This Act takes effect September 1, 2023.