               AN ACT
             | 
         
         
            | 
                
			 | 
            relating to water losses reported by certain municipally owned  | 
         
         
            | 
                
			 | 
            utilities to the Texas Water Development Board; authorizing  | 
         
         
            | 
                
			 | 
            administrative penalties. | 
         
         
            | 
                
			 | 
                   BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | 
         
         
            | 
                
			 | 
                   SECTION 1.  Subchapter B, Chapter 16, Water Code, is amended  | 
         
         
            | 
                
			 | 
            by adding Section 16.0122 to read as follows: | 
         
         
            | 
                
			 | 
                   Sec. 16.0122.  WATER AUDIT VALIDATION BY CERTAIN MUNICIPALLY  | 
         
         
            | 
                
			 | 
            OWNED UTILITIES.  (a) In this section, "municipally owned utility"  | 
         
         
            | 
                
			 | 
            has the meaning assigned by Section 13.002. | 
         
         
            | 
                
			 | 
                   (b)  This section applies only to a municipally owned utility  | 
         
         
            | 
                
			 | 
            that provides potable water through more than 150,000 service  | 
         
         
            | 
                
			 | 
            connections. | 
         
         
            | 
                
			 | 
                   (c)  A municipally owned utility that has filed an annual  | 
         
         
            | 
                
			 | 
            water audit under Section 16.0121 shall: | 
         
         
            | 
                
			 | 
                         (1)  not later than the 180th day after the date the  | 
         
         
            | 
                
			 | 
            audit was filed, complete a validation of the audit to ensure the  | 
         
         
            | 
                
			 | 
            utility accurately assessed potential inaccuracies in data used in  | 
         
         
            | 
                
			 | 
            the audit; and | 
         
         
            | 
                
			 | 
                         (2)  not later than the first anniversary of the date  | 
         
         
            | 
                
			 | 
            the audit was filed, develop and submit to the board a water loss  | 
         
         
            | 
                
			 | 
            mitigation plan. | 
         
         
            | 
                
			 | 
                   (d)  Not later than December 31, 2030, and every 10 years  | 
         
         
            | 
                
			 | 
            thereafter, a municipally owned utility that has filed an annual  | 
         
         
            | 
                
			 | 
            water audit under Section 16.0121 shall: | 
         
         
            | 
                
			 | 
                         (1)  complete a more detailed validation of the  | 
         
         
            | 
                
			 | 
            utility's most current water audit to: | 
         
         
            | 
                
			 | 
                               (A)  determine whether the implementation of  | 
         
         
            | 
                
			 | 
            water leakage reduction strategies is appropriate; and | 
         
         
            | 
                
			 | 
                               (B)  investigate the accuracy of the utility's  | 
         
         
            | 
                
			 | 
            billing data; and  | 
         
         
            | 
                
			 | 
                         (2)  update the water loss mitigation plan developed by  | 
         
         
            | 
                
			 | 
            the utility under Subsection (c)(2) accordingly. | 
         
         
            | 
                
			 | 
                   (e)  Each validation required under Subsection (c)(1) must  | 
         
         
            | 
                
			 | 
            be performed by a person who has completed water audit validation  | 
         
         
            | 
                
			 | 
            training and is certified to conduct the validation.  The  | 
         
         
            | 
                
			 | 
            validation: | 
         
         
            | 
                
			 | 
                         (1)  must follow board validation guidelines; and | 
         
         
            | 
                
			 | 
                         (2)  may not be conducted by a board staff member or the  | 
         
         
            | 
                
			 | 
            person who submitted the water audit. | 
         
         
            | 
                
			 | 
                   (f)  Each water loss mitigation plan developed under  | 
         
         
            | 
                
			 | 
            Subsection (c)(2), as updated under Subsection (d)(2), if  | 
         
         
            | 
                
			 | 
            applicable, must be incorporated into the utility's most recent  | 
         
         
            | 
                
			 | 
            water conservation plan required under Section 13.146 not later  | 
         
         
            | 
                
			 | 
            than the first anniversary of the date the mitigation plan is  | 
         
         
            | 
                
			 | 
            completed.  As part of the utility's annual water conservation  | 
         
         
            | 
                
			 | 
            report under Section 16.402(b), the utility shall report the  | 
         
         
            | 
                
			 | 
            utility's progress in implementing the mitigation plan.  The  | 
         
         
            | 
                
			 | 
            mitigation plan must include: | 
         
         
            | 
                
			 | 
                         (1)  one-year, three-year, five-year, and ten-year  | 
         
         
            | 
                
			 | 
            goals for water loss mitigation; | 
         
         
            | 
                
			 | 
                         (2)  descriptions of water loss mitigation projects or  | 
         
         
            | 
                
			 | 
            programs designed to meet those goals; | 
         
         
            | 
                
			 | 
                         (3)  estimated financial savings from the  | 
         
         
            | 
                
			 | 
            implementation of the projects or programs under Subdivision (2); | 
         
         
            | 
                
			 | 
                         (4)  estimated water savings from the implementation of  | 
         
         
            | 
                
			 | 
            the projects or programs under Subdivision (2); and | 
         
         
            | 
                
			 | 
                         (5)  cost estimates for implementing each project or  | 
         
         
            | 
                
			 | 
            program under Subdivision (2). | 
         
         
            | 
                
			 | 
                   (g)  If the utility must complete a validation under  | 
         
         
            | 
                
			 | 
            Subsection (d)(1), the utility shall update the water loss  | 
         
         
            | 
                
			 | 
            mitigation plan developed by the utility under Subsection (c)(2) to  | 
         
         
            | 
                
			 | 
            revise the utility's one-year, three-year, five-year, and ten-year  | 
         
         
            | 
                
			 | 
            goals. | 
         
         
            | 
                
			 | 
                   (h)  Each validation required under Subsection (d)(1) must  | 
         
         
            | 
                
			 | 
            be performed by a person who is experienced in performing required  | 
         
         
            | 
                
			 | 
            validation activities.  The validation: | 
         
         
            | 
                
			 | 
                         (1)  must be based on the recommendations from the  | 
         
         
            | 
                
			 | 
            utility's validation performed under Subsection (c)(1); | 
         
         
            | 
                
			 | 
                         (2)  must be completed in consultation with the person  | 
         
         
            | 
                
			 | 
            who completed the validation under Subsection (c)(1); | 
         
         
            | 
                
			 | 
                         (3)  must be conducted in accordance with industry  | 
         
         
            | 
                
			 | 
            standards; and | 
         
         
            | 
                
			 | 
                         (4)  may not be conducted by a board staff member or the  | 
         
         
            | 
                
			 | 
            person who submitted the water audit. | 
         
         
            | 
                
			 | 
                   (i)  The commission shall assess against a municipally owned  | 
         
         
            | 
                
			 | 
            utility an administrative penalty of $25,000 if the utility fails  | 
         
         
            | 
                
			 | 
            to develop and submit to the board a water loss mitigation plan  | 
         
         
            | 
                
			 | 
            required by Subsection (c)(2). | 
         
         
            | 
                
			 | 
                   SECTION 2.  This Act takes effect immediately if it receives  | 
         
         
            | 
                
			 | 
            a vote of two-thirds of all the members elected to each house, as  | 
         
         
            | 
                
			 | 
            provided by Section 39, Article III, Texas Constitution.  If this  | 
         
         
            | 
                
			 | 
            Act does not receive the vote necessary for immediate effect, this  | 
         
         
            | 
                
			 | 
            Act takes effect September 1, 2025. | 
         
         
            |   | 
         
         
            |   | 
         
         
            |   | 
            ______________________________ | 
            ______________________________ | 
         
         
            |   | 
               President of the Senate | 
            Speaker of the House      | 
         
         
            |   | 
         
         
            |   | 
         
         
            | 
                		
			 | 
                   I certify that H.B. No. 29 was passed by the House on April  | 
         
         
            | 
                		
			 | 
            25, 2025, by the following vote:  Yeas 138, Nays 0, 2 present, not  | 
         
         
            | 
                		
			 | 
            voting; and that the House concurred in Senate amendments to H.B.  | 
         
         
            | 
                		
			 | 
            No. 29 on May 19, 2025, by the following vote:  Yeas 129, Nays 0, 1  | 
         
         
            | 
                		
			 | 
            present, not voting. | 
         
         
            | 
                		
			 | 
             | 
         
         
            | 
                		
			 | 
            ______________________________ | 
         
         
            | 
                		
			 | 
            Chief Clerk of the House    | 
         
         
            |   | 
         
         
            | 
                		
			 | 
                   I certify that H.B. No. 29 was passed by the Senate, with  | 
         
         
            | 
                		
			 | 
            amendments, on May 8, 2025, by the following vote:  Yeas 31, Nays 0. | 
         
         
            | 
                		
			 | 
             | 
         
         
            | 
                		
			 | 
            ______________________________ | 
         
         
            | 
                		
			 | 
            Secretary of the Senate    | 
         
         
            | 
                		
			 | 
            APPROVED: __________________ | 
         
         
            | 
                		
			 | 
                            Date        | 
         
         
            | 
                		
			 | 
              | 
         
         
            | 
                		
			 | 
                     __________________ | 
         
         
            | 
                		
			 | 
                          Governor        |