         SECTION 1.  Sections 53.001(2) and (4), Property Code, are
  amended to read as follows:
               (2)  "Improvement" includes:
                     (A)  a house, building, structure, parking
  structure, physical appurtenance, pool, utility, railroad, well,
  storage facility, abutting sidewalks and streets, utilities in or
  on those sidewalks and streets, land reclaimed from overflow, and
  other fixtures or modifications to real property;
                     (B)  clearing, grubbing, draining, or fencing of
  land;
                     (C)  machinery or apparatuses used for raising
  water or for supplying or storing water for stock, domestic use, or
  irrigation;
                     (D)  work described by Section 53.021(4) or (6);
  and
                     (E)  a design, drawing, plan, plat, survey, or
  specification provided by a licensed architect, engineer, or
  surveyor.
               (4)  "Material" means all or part of:
                     (A)  the material, machinery, fixtures, or tools:
                           (i)  incorporated into the work;
                           (ii)  used in the direct performance of the
  work;
                           (iii)  specially fabricated for an
  improvement; or
                           (iv)  ordered and delivered for
  incorporation or use;
                     (B)  rent at a reasonable rate and actual running
  repairs at a reasonable cost for construction equipment used or
  reasonably required and delivered for use in the direct performance
  of the work at the site of the construction or repair; or
                     (C)  power, water, fuel, [and] lubricants, and
  cleaning supplies consumed or ordered and delivered for consumption
  in the direct performance of the work.
         SECTION 2.  Section 53.021, Property Code, is amended to
  read as follows:
         Sec. 53.021.  PERSONS ENTITLED TO LIEN. A person has a lien
  if the person, under a contract with the owner or the owner's agent,
  trustee, receiver, contractor, or subcontractor:
               (1)  labors or furnishes labor or materials for
  construction or repair of an improvement;
               (2)  specially fabricates material, even if the
  material is not delivered;
               (3)  is a licensed architect, engineer, or surveyor
  providing services to prepare a design, drawing, plan, plat,
  survey, or specification;
               (4)  provides labor, plant material, or other supplies
  for the installation of landscaping for an improvement, including
  the construction of a retention pond, retaining wall, berm,
  irrigation system, fountain, or other similar installation; [or]
               (5)  performs labor as part of, or furnishes labor or
  materials for, the demolition of an improvement on real property;
  or
               (6)  provides labor or other supplies for the interior
  cleaning of a home or office.
         SECTION 3.  Section 53.023, Property Code, is amended to
  read as follows:
         Sec. 53.023.  PAYMENT SECURED BY LIEN.  The lien secures
  payment for:
               (1)  the labor done or material furnished for the
  construction, repair, design, survey, [or] demolition, or
  cleaning; or
               (2)  the specially fabricated material, even if the
  material has not been delivered or incorporated into the
  construction or repair, less its fair salvage value.
         SECTION 4.  Section 53.124(e), Property Code, is amended to
  read as follows:
         (e)  The time of inception of a lien that is created under
  Section 53.021(3), (4), (5), or (6) [53.021(c), (d), or (e)] is the
  date of recording of an affidavit of lien under Section 53.052.  The
  priority of a lien claimed by a person entitled to a lien under
  Section 53.021(3), (4), (5), or (6) [53.021(c), (d), or (e)] with
  respect to other mechanic's liens is determined by the date of
  recording.  A lien created under Section 53.021(3), (4), (5), or (6)
  [53.021(c), (d), or (e)] is not valid or enforceable against a
  grantee or purchaser who acquires an interest in the real property
  before the time of inception of the lien.
         SECTION 5.  The changes in law made by this Act apply only to
  an original contract entered into on or after the effective date of
  this Act.  An original contract entered into before the effective
  date of this Act is governed by the law as it existed immediately
  before the effective date of this Act, and that law is continued in
  effect for that purpose.
         SECTION 6.  This Act takes effect September 1, 2025.