A BILL TO BE ENTITLED
|
|
|
AN ACT
|
| |
|
|
relating to the compensation of a distributed renewable generation |
|
|
owner in certain areas outside of ERCOT. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. Section 39.554, Utilities Code, is amended by |
|
|
amending Subsection (f) and adding Subsection (i) to read as |
|
|
follows: |
|
|
(f) Unless the commission approves an alternative method |
|
|
for compensating a distributed renewable generation owner for |
|
|
electricity generated by distributed renewable generation or a |
|
|
qualifying facility, for [For] a distributed renewable generation |
|
|
owner that chooses interconnection through a single meter under |
|
|
Subsection (e): |
|
|
(1) the amount of electricity the owner generates |
|
|
through distributed renewable generation or a qualifying facility |
|
|
for a given billing period offsets the owner's consumption for that |
|
|
billing period; and |
|
|
(2) any electricity the owner generates through |
|
|
distributed renewable generation or a qualifying facility that |
|
|
exceeds the owner's consumption for a given billing period shall be |
|
|
credited to the owner under Subsection (g). |
|
|
(i) Before approving an alternative method for compensating |
|
|
a distributed renewable generation owner for electricity generated |
|
|
by distributed renewable generation or a qualifying facility, the |
|
|
commission shall require the electric utility to conduct and submit |
|
|
to the commission a comprehensive cost-benefit analysis using |
|
|
established best practices to justify the rates of compensation and |
|
|
any associated fees. The commission must consider the |
|
|
comprehensive cost-benefit analysis before approving alternative |
|
|
rates for compensating distributed renewable generation owners or |
|
|
the continuation of net metering, including any rates or fees that |
|
|
apply only to distributed renewable generation owners and reflect |
|
|
the value provided by the distributed renewable generation or |
|
|
qualifying facility. |
|
|
SECTION 2. This Act takes effect September 1, 2026. |
|
|
|
|
|
* * * * * |