89R26827 SCR-F
 
  By: Guillen H.B. No. 3712
 
  Substitute the following for H.B. No. 3712:
 
  By:  Button C.S.H.B. No. 3712
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to funds reserved or retained for certain construction
  materials.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 2252.032, Government Code, is amended by
  amending Subsection (e) and adding Subsection (e-1) to read as
  follows:
         (e)  A governmental entity may not withhold retainage:
               (1)  after completion of the work required to be
  performed under the contract by the prime contractor, including
  during the warranty period; [or]
               (2)  for the purpose of requiring the prime contractor,
  after completion of the work required to be performed under the
  contract, to perform work on manufactured goods or systems that
  were:
                     (A)  specified by the designer of record; and
                     (B)  properly installed by the contractor; or
               (3)  for specially fabricated material that:
                     (A)  has been delivered by a subcontractor and
  accepted by the governmental entity and the prime contractor at the
  site or off-site; and
                     (B)  is covered by a manufacturer's warranty:
                           (i)  under a contract with the governmental
  entity; or 
                           (ii)  assigned to the governmental entity by
  the prime contractor.
         (e-1)  Subsection (e)(3) does not apply to funds for the
  value of the installation of the specially fabricated material by a
  subcontractor. 
         SECTION 2.  Section 53.101, Property Code, is amended by
  amending Subsection (a) and adding Subsections (a-1) and (a-2) to
  read as follows:
         (a)  Except as provided by Subsection (a-1), during [During]
  the progress of work under an original contract for which a
  mechanic's lien may be claimed and for 30 days after the work under
  the contract is completed, the owner shall reserve:
               (1)  10 percent of the contract price of the work to the
  owner; or
               (2)  10 percent of the value of the work, measured by
  the proportion that the work done bears to the work to be done,
  using the contract price or, if there is no contract price, using
  the reasonable value of the completed work.
         (a-1)  An owner is not required to reserve under this section
  and may not retain under a contract funds for specially fabricated
  material that:
               (1)  has been delivered by a subcontractor and accepted
  by the owner or a contractor or subcontractor at the site or
  off-site; and
               (2)  is covered by a manufacturer's warranty under a
  contract with the owner or a contractor or subcontractor.
         (a-2)  Subsection (a-1) does not apply to funds for the value
  of the installation of specially fabricated material by a
  subcontractor.
         SECTION 3.  The changes in law made by this Act apply only to
  an original contract that is entered into on or after the effective
  date of this Act. An original contract entered into before the
  effective date of this Act is governed by the law as it existed
  immediately before the effective date of this Act, and the former
  law is continued in effect for that purpose.
         SECTION 4.  This Act takes effect September 1, 2025.