S.B. No. 226
8-1 COMMITTEE AMENDMENT NO. 1
8-2 Amend S.B. 226 as follows:
8-3 On page 1, line 18 and 19 after "bidding" strike "or
8-4 competative sealed proposals" and substitute ".".
8-5 Bailey
8-6 COMMITTEE AMENDMENT NO. 2
8-7 Amend S.B. 226 as follows:
8-8 (1) On page 1, between lines 21 and 22, insert a letter (d)
8-9 to read as follows:
8-10 (d) Any construction or engineering contract that falls
8-11 under this chapter for competitive sealed bidding or competitive
8-12 sealed proposals shall not include a provision requiring a
8-13 contractor or an engineering firm to indemnify the municipality for
8-14 damages arising from negligence of the municipality.
8-15 Bailey