GEC C.S.H.B. 740 75(R)    BILL ANALYSIS


BUSINESS & INDUSTRY
C.S.H.B. 740
By: Solomons
4-10-97
Committee Report (Substituted)



BACKGROUND
 
Credit is the life-blood of the construction industry.  Owners must have a
ready source of credit in order to fund construction projects and to
purchase improved property.  Equally important is the credit that must be
extended by contractors, subcontractors, and suppliers during the course
of construction.  Very few contractors and subcontractors have the working
capital to finance ongoing construction projects.   Currently, when a
supplier furnishes materials on a construction project, the supplier
extends credit -- often on a 30 day account.  The supplier is paid for the
materials furnished on the project when the contractor is paid by the
owner or the owner's lender. When purchases from a supplier are made by a
subcontractor, the money has to filter down two or more levels before the
supplier is paid.  The same is true for the payment of subcontractors for
the labor they furnish to a project.  Accordingly, a subcontractor or
supplier may not get paid for 45 to 60 days after the labor or materials
have been furnished to the project. 

Since the days of the Republic of Texas, those who furnish labor and
materials have been given lien rights on the property being improved to
secure the credit they extend on the project.  To protect owners and
others in the construction chain, the Legislature has imposed significant
notice and filing requirements as a prerequisite for these liens.
Claimants often complain that these laws are too complicated and that the
steps for perfecting a lien claim are too difficult.  On the other hand,
property owners often complain that their property can be subject to the
lien claim of a subcontractor or supplier with which the owner never
directly contracted.  While there are steps a property owner can take to
avoid or significantly minimize the risk of having a mechanic's lien claim
perfected against the property, many property owners, particularly
homeowners who are having homes built on their own lots, are not aware of
their legal rights and are not familiar with construction customs and
practices.  In such a case, when the contractor defaults, the consequences
can be disastrous for the homeowner.  Not only is the homeowner faced with
having to hire a contractor to finish and, in some cases, to redo the
work, but the homeowner may also have to deal with the mechanic's lien
claims of the subcontractors and suppliers the contractor failed to pay. 

In the last several years, a number of homeowners have brought these
problems to the Legislature's attention.  In 1994, following the 74th
Regular Session, the Committee on Business and Industry was charged with
studying lien laws and construction contracts.  During its Interim Study,
the Committee took extensive testimony from consumers as well as all
segments of the construction industry.  While the issues are complex and
not all problems can be fixed, the Committee concluded that there were
some changes that could be made in current law which would give owners,
particularly individual homeowners, added protection without unduly
prejudicing the other segments of the construction industry.  C.S.H.B. 740
reflects the work of the Committee and interested construction industry
representatives to address those problems. 


PURPOSE

The intent of this bill is to provide the appropriate protections for
homeowners and other owners of real property while protecting the rights
of contractors, subcontractors, and suppliers and maintaining a viable
construction industry in Texas. 


 RULEMAKING AUTHORITY

It is the committee's opinion that this bill does not expressly grant any
additional rulemaking authority to a state officer, department, agency or
institution. 

SECTION BY SECTION ANALYSIS

SECTION (1) Amends Section 41.001(b), Property Code.
 The Section number relating to the special procedures for perfecting a
lien on homestead is changed because Sec. 53.059 has been moved to Sec.
53.254. 

SECTION (2) Amends Section 53.001, Property Code.
 Three definitions are added to Sec. 53.001.  These definitions are
necessary in order to determine which types of projects will be subject to
the amended lien perfection procedures, consumer disclosures, and other
statutory changes in the new Subchapter K of Chapter 53. Essentially, with
these definitions, it is the intent of this legislation to give individual
homeowners added protection when they contract to construct or repair
their homes or dwellings. 

 New subsection (8) defines "residence" to mean a one to four unit house
or residential structure which is used for residential purposes and is
owned by one or more adult persons and is actually used or intended to be
used as a dwelling by one or more of those owners. With regard to
multi-unit structures, this definition is intended to cover the situation
where an individual uses or intends to use one of the units as that
individual's dwelling and intends to lease or rent the remaining units.
This definition is intended to encompass a family homestead as well as
second homes or vacation homes which the individual uses or intends to use
as that individual's dwelling.  Accordingly, the definition would include
the situation where an adult person or a husband and wife are residing in
a homestead but are building another home with the intent that they will
move into the second home when it is completed.  Lenders, title companies,
contractors, and other interested parties often have difficulty
determining which property is homestead in such situations.  This
definition removes that uncertainty for purposes of this Chapter.  On the
other hand, the definition does not include a situation where an
individual is building a residential structure for investment purposes
such as resale or as a rent house for a third party. For multi-unit
structures, if all of the units are intended for lease or resale, the
structure is not a residence for the purposes of this Chapter.   

 New subsection (9) defines "residential construction contract" to mean a
contract between an owner and a contractor to construct or repair a
residence. 

 New subsection (10) defines "residential construction project" as a
project for the construction or repair of a new or existing residence,
pursuant to a residential construction contract. 

 The remaining subsections are renumbered accordingly.

SECTION (3) Amends Section 53.003(a), Property Code.
 The general provisions and requirements set forth in Sec. 53.003 relating
to notices under this Chapter are made applicable to new Subchapter K and
the notices set forth therein. 

SECTION (4)Amends Section 53.026(a), Property Code, by adding a new
subsection (a)(2) and renumbering 53.026 (a) accordingly.  
 Sec. 53.026 was known before the codification of the mechanic's lien
statutes into the Property Code as the"Sham Contractor Statute" because it
was intended, in part, to allow claimants to treat a property owner and
contractor as a single entity for determining how to perfect a lien claim
when the owner owned and/or controlled the contractor.  This is important
because owners and contractors do sometimes set up sham or even
legitimate, wholly owned subsidiaries or affiliates to act as either the
property owner or contractor.  The problem with the current statute is
that it only deals with the situation in which the owner actually owns and
controls the contractor.  In that situation, the owner and contractor are
deemed to be the same  party for purposes of determining the types of
notices a claimant must furnish or steps a claimant must take in order to
perfect a valid lien or bond claim.  These amendments simply provide that,
when the contractor owns and controls the owner (the reverse situation),
they will be deemed the same entity for purposes of Chapter 53.  In other
words a claimant who contracts with the contractor in that situation will
be deemed to have contracted with the owner. 

SECTION (5) Amends Section 53.052, Property Code.
 The time requirements for filing the mechanic's lien affidavit are
changed.  For liens arising from a residential construction project, the
lien affidavit must be filed no later than the 15th day of the third
calendar month after the date the indebtedness accrues.  This amendment
shortens the time for filing a lien affidavit for a lien arising from a
residential construction project by one month.  For all other projects,
the time for filing the lien affidavit does not change. 

SECTION (6) Amends Sections 53.054(a) and (b), Property Code.
 The requirements for the content of the mechanic's lien affidavit are
changed.  These changes will apply to all lien claims, not just to those
arising from a residential construction project.  Changed or new
requirements are: 

 a.the claimant must disclose the last known addresses of the owner or
reputed owner, original contractor, and person with whom the claimant
contracted; 

 b. the claimant must state its physical and, if different, mailing
address; 

 c.in connection with the general statement of the kind of work or
materials furnished to the project by the claimant, any claimant other
than an original contractor must state the month or months in which the
work was performed or the materials were delivered; 

 d.for a claimant other than an original contractor, the claimant must
identify the date on which each notice of claim was sent to the owner and
original contractor and must state the method the notice was sent (such as
by hand delivery or certified mail). 

 These new requirements are designed to give owners and other interested
parties more information from the face of the lien affidavit about the
nature and validity of the claimant's lien. For the most part, this
information is readily available to claimants and should not be overly
burdensome.  It should be noted that the addresses of the third parties
need only be the "last known addresses."  Further, in the event that a
claimant may inadvertently omit some information, it may not necessarily
invalidate the lien claim because Sec. 53.054 continues to require that
the claimant need only substantially comply with requirements for the
content of the affidavit. 

SECTION (7) Amends Sec. 53.055(a), Property Code.
 Under current law, the claimant must send a copy of the lien affidavit to
the owner and original contractor no later than the 10th business day
after the date the lien is filed of record or, if earlier, on the date the
statute requires the lien affidavit to be filed.  Claimants will now be
required to send a copy of the lien affidavit to the owner and original
contractor no later than one business day after the lien affidavit is
filed.  This simplifies the procedure and gives owners and contractors
information on a more timely basis. 

SECTION (8) Amends Sec. 53.056(a), Property Code.
 New notice requirements are imposed on claims arising from residential
construction projects by the new Subchapter K.  Sec. 53.056 is amended to
provide that the notice to owner and original contractor for residential
construction projects will be governed by Subchapter K. 

SECTION (9) Amends Sec. 53.057(a), Property Code.
 New notice requirements are imposed on claims arising from residential
construction projects by the new Subchapter K.   Sec. 53.057 is amended to
provide that the notices for  residential construction projects will be
governed by Subchapter K.  There will be no notice of contractual retain
age agreement for residential construction projects.  This notice has been
eliminated on these types of projects to simplify the procedures for
owners, contractors, and claimants.  Because the time periods for typical
residential construction do not extend over many months, it is anticipated
that most claimants who have contractual retain age agreements can simply
comply with the other notice requirements with little difficulty. 

SECTION (10) Amends Sec. 53.058(a), Property Code.
 New notice requirements are imposed on claims arising from residential
construction projects by the new Subchapter K.  Sec. 53.058 is amended to
provide that the notice for specially fabricated items for residential
construction projects will be governed by Subchapter K. 
 
SECTION (11) Amends Sections 53.081 (a), (b), and (c), Property Code.
 Section 53.081 authorizes the owner to withhold funds upon receipt of
special "fund-trapping" notices from claimants.  Failing to withhold the
amount of the claimant's claim from future payments to the contractor is
one of the two ways an owner may become liable for the claim of a
derivative claimant (a claimant with whom the owner does not have a direct
contract).  The new notice provisions in Subchapter K are added to Sec.
53.081 so that an owner will be authorized to withhold funds upon receipt. 

SECTION (12) Amends Section 53.084(b), Property Code.
 The provision imposing liability on the owner for failing to withhold the
payments to the contractor in the amount stated in a claimant's notice of
claim is amended to include the notices required by the new Subchapter K. 

SECTION (13) Amends Section 53.085, Property Code.
 Currently, Sec. 53.085 requires persons seeking payment for labor or
materials furnished on a construction project to furnish an affidavit as a
condition to payment in which the person seeking payment states that all
bills have been paid.  In the event that there are bills that have not
been paid, the affiant is required to disclose the amount of each unpaid
bill and the name of the person to whom it is owed.  A similar affidavit
must be given by a seller of property on which improvements were
constructed.   

 Various non-substantive changes were made in the wording of Sec. 53.085.
Additionally, Sec. 53.085 (a) will include the requirement that the
affiant state the address and telephone number, if known, of each of the
persons to whom unpaid bills are owed. 

 When the affidavit includes a waiver or release of the affiant's lien
rights and payment is not made in current funds, Sec. 53.085(c)(1) will
authorize the affiant to condition its waiver or release on receipt of
actual payment.  Under Sec. 53.085(c)(3) the affidavit may also include a
contractual obligation of the affiant to indemnify the person paying the
money for any loss or expense resulting from false or incorrect
information in the affidavit.  Under Sec. 53.085 (e) the person signing
the affidavit will be personally liable for any such false or incorrect
information. 

 Because these affidavits are sometimes provided during the course of
construction, Sec. 53.085 (c) (2) provides that the affidavit may include
a warranty or representation that the affiant will use the funds to pay
all current obligations.  This recognizes the reality of current
construction practices in which contractors use the proceeds of the
progress payment to pay those bills which were incurred since the date of
the last payment.  In those situations, it is fair to require the
contractor receiving payment to make an express representation that the
money will be used for paying those current obligations. 

 Sec. 53.085(d) provides that a person convicted of violating this Section
shall be punished by a fine not to exceed $4,000 or confinement in jail
for a term not to exceed one year, or both.  A person will not be allowed
to receive community supervision for the offense. 

SECTION (14) Amends Sections 53.106(b), (c), and (d), Property Code.
 Sec. 53.106, which deals with the Affidavit of Completion, is amended to
conform to the amendments to Chapter 53 made in this bill, including the
new notice provisions in Subchapter  K. 

SECTION (15) Amends Sec. 53.157, Property Code.
 Subsection (4) is amended to conform to the new requirements in
Subchapter H for releasing a lien by filing and recording a surety bond.
Subsection (6) is added which provides for the discharge of a lien when an
owner records a certified copy of the order removing a lien and the
certificate of the clerk stating that no bond or security has been filed
pursuant to the Summary Motion to Remove Invalid or Unenforceable Lien
provisions in Sections 53.160 through 53.162. 

SECTION (16) Amends Sec. 53.158, Property Code.
 The limitations period for bringing suit to foreclose a lien arising from
a residential construction project has been shortened to the first
anniversary of the date the lien affidavit is filed.  If a lien affidavit
is filed on March 15 of a given year, any suit to foreclose the lien must
be filed on or before March 15 of the next year.  This limitations period
does not apply to a suit on the underlying claim.  Further, the one year
limitations period in Subsection (b) only applies to liens arising from
residential construction projects. 


SECTION (17)Amends Chapter G, Property Code, by adding Sections 53.160,
53.161, and 53.162. 
 One of the problems the Committee found in its hearings was that owners
needed a relatively inexpensive and efficient means of clearing title to
their property when disputed liens have been filed.  Even a lien claim
which appears invalid on its face may cause a cloud on an owner's title
which could result in the owner being unable to sell the property or to
use it as collateral for a loan.  This problem can be quite critical when
a contractor defaults and multiple claimants file lien claims.
Frequently, those claims are not valid or the claimants otherwise fail to
properly perfect their liens.  While an owner can bond around those liens,
there should be an alternative method to clear title without unduly
prejudicing the rights of legitimate claimants.   

 C.S.H.B. 740 creates a new procedure to allow owners who are in
litigation with lien claimants to file an expedited motion which is very
similar to a Motion for Summary Judgment permitted under the Texas Rules
of Civil Procedure.  However, unlike most pre-trial orders, the court's
order can be used to remove the liens and clear title to the owner's
property before a full trial on the merits is conducted and before a
lengthy appeal is exhausted.  Lien claimants whose liens are ordered
removed are not denied due process because they are given a full hearing
on the issues of the validity of the lien and are provided with a means of
staying the order by posting a reasonable bond or similar security. 

 Under Section 53.160, whenever a lien claimant has filed suit to enforce
and foreclose a lien or an owner has filed suit to declare a claim or lien
invalid or unenforceable, the owner may file a motion with the court to
remove the claim or lien.  The motion must be verified and must state the
legal and factual basis for objecting to the lien or the underlying claim. 

 Sec. 53.160 (b) sets forth the only grounds on which the owner can object
and have the lien removed pursuant to this special procedure.  The 7
grounds generally relate to defects in the manner in which notice is given
or the lien is perfected, whether the claimant previously released or
waived the lien or claim, and whether the claimant actually trapped funds
or properly perfected a claim against the statutory retain age.  

 For the most part, the grounds for removal relate to issues or facts that
should be relatively clear or easily discernable.  Consequently, under
subsection (c) the motion can be heard on 21 days notice so long as the
claimant has appeared in the proceeding for at least 21 days. The claimant
does not need to file a formal response to the motion.  At the hearing, if
one of the grounds stated in the motion was that the claimant failed to
furnish the notice of claim or the lien affidavit to the owner or the
original contractor as required by Chapter 53, the burden will be on the
claimant to prove that the notices and lien affidavit were properly sent
or furnished.  The owner will have the burden of proof on all other
grounds.  Sec. 53.160 (d). 

 Any admissible evidence offered at the hearing may be used in the trial
of the case;  however, the court's order, itself, will not be admissible
in the subsequent trial in determining the validity and enforceability of
the claim or lien.  Sec. 53.160 (f).  Given the nature of the issues, it
is anticipated that the evidence will consist primarily of affidavits and
documents.  However, when a factual issue is in dispute, the court
presumably would listen to the testimony of witnesses as in any contested
hearing or trial.  

 Following the hearing, the court is directed under subsection (e) to
promptly determine whether the movant is entitled to have the lien
removed.  If the court determines that the movant is entitled to have the
lien or liens removed, the court shall enter an order removing the lien
claimed in the lien affidavit.  If the court determines that the movant is
not entitled to removal of the lien, the court shall deny the motion.
Because the proceeding is only directed to the validity or enforceability
of the lien, it will not resolve all of the issues relating to the owner
or contractor's underlying liability for the claim.  In fact, it will not
be a final judgment as to the validity of the lien.  Consequently, the
order will be interlocutory and there will be no appeal until there has
been a trial on the merits and a final judgment is entered resolving of
all the outstanding issues in the case.  

 Under Sec. 53.161, if the court enters an order removing the lien, the
court is also required to set the amount of the bond or other security
which the claimant may provide in order to stay the removal.  The amount
of the bond or security must be the amount which the court determines to
be a reasonable estimate of the costs and attorney's fees which the owner
will incur in the ongoing litigation.  However, in no event shall the
amount of the bond or other security be set at an amount greater than the
lien claim itself.  If the court should fail to set the amount of the bond
in the order of removal, the bond amount shall be the amount of the lien
claim.   

 Under subsection (c) the bond must be conditioned upon the claimant's
payment of any final judgment rendered against the claimant with regard to
attorney's fees and costs to the movant under Sec. 53.156.  Therefore, if
the movant recovers no damages but is awarded $5,000 in attorney's fees in
a final judgment in the case, the claimant's surety will be liable for
$5,000 in the event the claimant fails or refuses to pay the attorney's
fees.  On the other hand, if the movant is not awarded any attorney's fees
or costs in the final judgment, the claimant's surety will have no
liability under the bond. 

 Under subsection (d) the claimant may provide alternative security in
lieu of a bond.  The security may include cash, a negotiable obligation of
the federal government or a negotiable obligation of a federally insured
financial institution. 

 Under subsection (b), if the claimant does timely and properly file the
bond or authorized security, the court must stay the removal order. 

 The primary purpose of this proceeding is to allow an owner to clear
title to its property when an invalid lien claim has been asserted.
Because the order removing the lien is interlocutory and not appealable,
such a pretrial order would normally not be effective to remove the cloud
on the owner's title.  However, under these procedures, the order may be
effective to remove the lien with regard to third party creditors and
purchasers under certain circumstances. Under subsection (f), if the
claimant fails to provide the bond or security with the clerk of the court
in which the litigation is pending within 30 days (or as otherwise ordered
by the court), the owner can obtain a certified copy of the order and a
certificate from the clerk that no bond or security has been filed and
record those two instruments in the Real Property Records of the County in
which the property is located.  When that is done, the lien is removed and
extinguished as to any creditor or subsequent purchaser for valuable
consideration.  This would remove the cloud which the lien imposed on the
owner's title -- at least as to subsequent creditors and purchasers who
pay valuable consideration for the property. 

 Because the order removing the lien is not a final judgment, the
litigation between the parties will likely continue.  In the event that
the claimant is unable or otherwise fails to furnish the bond or security
in a timely fashion but nonetheless obtains a final judgment which
establishes the validity of the lien, the claimant may file a certified
copy of the judgment with the county clerk in the county in which the real
property is located and the lien affidavit was filed.  When the judgment
is filed, the lien is revived and the claimant is entitled to foreclosure
of the lien.  However, the lien is not revived as to creditors or
purchasers for value who obtained their interest in the property after the
lien was removed but before the final judgment reviving the lien was filed
with the county clerk.   

 This new summary proceeding is not limited to lien claims arising from
residential construction projects.  Also, this does not prevent an owner
or other interested party in litigation to seek and obtain a summary
judgment under appropriate court rules which would, of course, be a final
judgment if granted.  With a traditional summary judgment, however, the
claimant would have the right to appeal and supersede the judgment under
applicable rules of procedure.  Therefore, an owner may not be able to
remove the cloud on its title by filing a traditional motion for summary
judgment. 

SECTION (18) Amends Section 53.171, Property Code by adding a new
subsection (c). 
 Sec. 53.171 authorizes an owner or other interested party to file a bond
to release a lien claim on the owner's property.  This is another
mechanism for an owner to clear a cloud on its title created by one or
more disputed lien claims.  One of the problems the Committee found with
this procedure is the difficulty owners or interested parties have in
complying with the requirement for service of the bond on the disputed
lien claimant.  Often the lien claims that are disputed fail to fully
identify the lien claimant or claimants dodge service for any number of
reasons.  C.S.H.B. 740 addresses this problem by changing the requirements
concerning the lien release bond.  Instead of having to serve the claimant
with a copy of the bond, the county clerk will only have to mail a copy by
certified mail.  (See Sections 19 and 20 below). 

 The new subsection (c) to Sec. 53.171 makes it clear to title companies
and third parties relying on the bond to release the lien that the lien is
released against the property when the bond is filed with the county
clerk, the notice by the clerk is issued, and the bond and notice are
filed by the clerk.  Therefore, actual service on the claimant is no
longer a prerequisite for the lien being released by the bond. 

SECTION (19) Amends Section 53.172, Property Code.
 The procedures required in order for the bond under Sec. 53.171 to be
effective to release a disputed lien have been changed.  A copy of the
bond and notice issued by the county clerk no longer have to be served on
the lien claimant.  Under C.S.H.B. 740, the clerk issues a notice and the
clerk serves the notice and a copy of the bond on the claimant by mailing
it to the claimant by first class certified mail, return receipt
requested, at the address which the claimant discloses in its lien
affidavit.  That is one of the reasons that Sec. 53.054 has also been
amended to require the claimant to disclose its physical and mailing
address.  If the claimant fails to disclose its address, the clerk does
not have to mail the bond to the claimant.  Therefore, the failure to
disclose the address may not be a fatal defect in the lien affidavit for
the claimant, but it may result in the claimant not having notice of the
filing of the bond. 

 The bond releases the lien when the clerk files the notice to the
claimant and the bond. The clerk should retain any return receipt showing
actual receipt by the claimant; however, actual receipt is not necessary.
This should not work a hardship on a claimant because the claimant will
still have an alternative form of security for its claim, to wit: the
bond.  However, claimants may be subject to a shorter limitations period
and must act diligently in pursuing their claims. 

 It is the Committee's intent that, by making these procedures more
workable, owners will have viable, affordable alternatives in removing
disputed lien claims on their property without prejudicing legitimate
claimants. 

SECTION (20) Amends Sec. 53.174, Property Code.
 This amendment requires the clerk to file a certificate of mailing in the
real property records, along with the bond and a copy of the notice to the
claimant.  However, a party acquiring an interest in the property (a
purchaser or lender) or a party insuring title to the property (a title
company) may rely on the filing of the bond and notice with regard to the
release of the lien.  In other words, the clerk's failure to file a
certificate of mailing will still result in the lien being released.  
 
SECTION (21) Amends Sec. 53.175(b), Property Code.
 Sec. 53.175(b) is amended to make it clear that a suit against the lien
release bond must be filed in the same jurisdiction that a suit to enforce
the lien claim is filed.  In other words, it must be filed in the county
in which the property is located.  However, it may be filed in any court
having the appropriate monetary jurisdictional limits.  Accordingly, if
the bond is only $1,000, the suit may be filed in a court other than
District Court. 

SECTION (22) Amends Sec. 53.201(a), Property Code.
 Sec. 53.201 deals with the statutory payment bond that covers claims
which might arise on the entire project.  It is typically a bond that is
provided at the beginning of the project and is typically referred to as
the "payment bond."  It is different from the lien release bond provided
by Sections 53.171 - 53.175 (see above). 

 Under current law, the payment bond is required to be filed; however,
there is no requirement as to when the bond must be filed.  In fact, Sec.
53.208(d) expressly contemplates the situation in which the bond is
actually filed after a lien claim is perfected.  The bond is still
effective to remove any and all liens on the property. 

 C.S.H.B. 740 amends Sec. 53.201(a) to make it more clear that the owner
may furnish the bond at any time for the benefit of claimants.  In other
words, the bond need not be furnished before any work has commenced or any
claims have been asserted. 


SECTION (23) Amends Chapter 53, Property Code, by adding a new Subchapter
K relating to claims arising from residential construction projects. 
 A new Subchapter K entitled "Residential Construction Projects" is added
to Chapter 53 of the Property Code.  This new Subchapter deals with
contracts and claims arising on residential construction projects as
defined in Sec. 53.001. 

 Sec. 53.251 provides that Subchapter K applies only to residential
construction projects. (See analysis of Section 2 above for a discussion
of the meaning and scope of a residential construction project.) 

 To perfect a valid lien on property, the lien claimant must furnish
written notice to the owner and original contractor within strict time
periods.  Under current law (Sec. 53.056) a derivative claimant (a
claimant that does not have a direct contract with the owner) must give
written notice of the claim to the owner, with a copy to the original
contractor, no later than the 15th day of the 3rd month after each month
in which the unpaid work or materials were furnished.  In other words, for
unpaid work in January, the claimant must send the notice letter by April
15.  If the claimant had performed work in December for which payment is
sought and the claimant waited until April 15 to send the notice of claim
letter, the claimant would not have perfected a valid claim for the value
of the work performed in December.  When a claimant does not have a direct
contractual relationship with the original contractor, the claimant has to
also send a notice letter to the original contractor by the 15th day of
the 2nd month after each month in which the unpaid work or materials were
furnished.  Therefore, for work performed in January, the letter to the
original contractor must be sent by the 15th of March. 

 In order to simplify the procedures and to provide owners with more
timely information, the notice requirement on residential construction
projects under Sec. 53.252 has been reduced by one month (to the 15th day
of the 2nd month after each month in which the unpaid work was furnished).
This eliminates the need for a second letter to the original contractor
because the claimant must copy the original contractor with the notice
letter anyway. 

 With regard to the notice requirement for specially fabricated materials
on residential construction projects, which is now contained in Sec.
53.253, no real substantive change has been made in the content or timing
of the notice.  C.S.H.B. 740 does make one significant change in the
notice requirements for residential construction projects by deleting the
requirement for a notice of contractual retain age agreement.  It is the
Committee's view that this notice letter is  very confusing and, given the
relatively short construction periods on typical residential construction,
it would not unduly prejudice claimants to require them to send their
notice letters and perfect their claims by sending a notice of claim under
Sec. 53.252 even when a contractual retain age agreement exists. 

 The former Sec. 53.059 relating to special notice and other requirements
for the perfection of a lien on homestead property has been moved to
subchapter K, Sec. 53.254.  There has been no significant substantive
change between former Sec. 53.059 and the new Sec. 53.254.   

 The most striking aspect of the consumers' testimony during the Interim
Study was the fact that, time and again, the consumers were not aware of
the rights and protections the law gave owners in connection with
construction defaults and mechanic's lien claims.  While very sympathetic
to the problems encountered by the consumers who testified during the
Interim Study, the Committee believed that many of those problems could
have been avoided or significantly minimized if the consumers had been
better informed and had exercised the rights and responsibilities already
provided by law.  Accordingly, one of the most important features of
C.S.H.B. 740 is to require those who contract with homeowners and those
who lend the money for that construction to provide information to
homeowners about their rights and responsibilities. 

 Sec. 53.255 requires an original contractor to furnish a disclosure
statement to the owner before a contract for the construction of
improvements to the owner's residence is executed. Because any supplier
who sells directly to an owner is technically considered an "original
contractor" even though the supplier is a large retailer and the consumer
has done nothing more than buy 50_ worth of nails, the disclosure
requirement will be limited to those original contractors that enter into
a residential construction contract.  This will address the particular
area where most of the problems occur -- when individual consumers enter
into contracts to construct or repair improvements on the consumer's
homestead. 

 The disclosure statement is written in plain English and provides a
general summary of the most significant rights and responsibilities an
owner has under Texas law with regard to a number of construction issues,
including selecting a contractor, entering into a contract, monitoring the
work of the contractor and the payments to the contractor, and avoiding
and dealing with claims made by subcontractors and suppliers.  It is the
intent of the Committee that contractors duplicate the statutory
disclosure notice and provide that to consumers.  The notice actually
given to consumers does not have to be exact but must read substantially
similar to the disclosure set forth in Sec. 53.255(b). 

 To further inform the consumer, Sec. 53.256 requires original contractors
under a residential construction contract to give the consumer a list of
the subcontractors and suppliers the contractor intends to use on the
project.  As that list changes, the contractor is obligated to update the
information. 

 Sec. 53.257 requires lenders or those persons who furnish financing for
the construction of improvements under a residential construction contract
to deliver to the owner a copy of all the closing documents no later than
one business day before the date of the closing.  This requirement can be
waived in the case of a bona fide emergency or other good cause.  However,
the lender must obtain the owner's written consent to waive this
protection.  To better ensure that the owner receives the disclosure
statement under Sec. 53.255(b), the lender is also required to provide the
statement to the owner with the closing documents.  Of course, a lender
may choose to provide the statement in advance of the closing to better
inform the consumer. 

 Under Sec. 53.258, an original contractor is also required to provide a
signed disbursement statement to the consumer during the course of
construction.  This statement must list the bills and expenses that the
contractor represents have been paid  by the contractor.  When coupled
with the list of subcontractors, an owner can verify whether the
contractor is paying the bills for work performed on the project.  If not,
the owner can take steps to avoid mechanic's lien claims and other
problems that arise when a contractor fails to pay its bills on a project. 

  If the owner finances the construction payments through a third party
lender and that lender advances the loan proceeds directly to the
contractor, the lender must provide the owner with a disbursement
statement which reflects the loan advances made to the contractor and any
other disbursements made by the lender.  The lender is also obligated to
obtain a disbursement statement from the contractor in connection with
every request for loan advances from the contractor.  The disclosure
statement must list the bills and expenses the contractor represents that
it has paid since the last loan advance and the bills and expenses it
represents that it will pay from the loan proceeds to be advanced.  The
lender is required to furnish this disclosure statement to the owner prior
to making the requested loan advance to the contractor.  The method of
furnishing the disclosure will be determined by the agreement between the
owner and the lender. 

 A person who intentionally, knowingly, or recklessly provides false or
misleading information to the consumer in connection with a disbursement
statement will be guilty of a misdemeanor and subject to a fine up to
$4,000 and/or confinement in jail up to one year.  The person may not
receive community supervision for the offense. 

 In connection with the disclosure and disbursement statements, there are
no specific remedies provided against the contractor or the lender who
fails to provide these statements because the Committee believes that
there are sufficient statutory causes of action available to consumers who
are injured as a result of the failure to comply with a statutory
disclosure requirement.   With regard to the disbursement statement the
lender receives from the contractor and furnishes to the owner, the lender
is not responsible for the accuracy of the information obtained from the
contractor.  Further, the failure to provide the disclosure or
disbursement statements will not invalidate the lien which arises under
Chapter 53.  This is very important because lenders and third parties,
particularly the secondary mortgage market, must be able to rely upon the
validity of the lien.  For homestead property, it is the lien of the
contractor which is assigned to the lender and which allows the lender to
obtain a lien on the property to secure the loan to the consumer for the
cost of the improvements.   

 Sec. 53.259 requires an original contractor on a residential construction
project to provide the owner with a final bills paid affidavit as a
condition to final payment.  A seller of residential property on which
improvements were constructed must provide the bills paid affidavit as a
condition of the sale.  A person who intentionally, knowingly, or
recklessly makes a false or misleading statement in the affidavit will be
guilty of a misdemeanor and subject to a fine up to $4,000 and/or
confinement in jail up to one year.  The person may not receive community
supervision for the offense. 

SECTION (24) Repeals Section 53.059, Property Code.
 Sec. 53.059 is repealed because it has been renumbered as Sec. 53.254 and
moved to the new Subchapter K relating to residential construction
projects.   

SECTION (25) Effective date.
 The effective date of the changes in the law will be September 1, 1997,
for all original contracts (that is, direct contracts between the property
owner and the contractor) which are entered into on or after September 1,
1997.  An original contract is entered into when the parties have become
legally and mutually bound by a valid offer and acceptance.  The date a
written contract is signed by both parties is often the date the contract
is entered into.  For original contracts entered into prior to September
1, 1997, the former law will remain in effect.   For claims arising from
subcontractors and suppliers who do not have a direct contract with the
owner, the effective date will depend upon the original contract under
which the claim arises.  In other words, a subcontractor must look to the
date of the original contract in determining whether the changes in the
law are effective. 

 This may be somewhat confusing to claimants; however, the alternative
would be chaos with different contracts and subcontracts being subject to
different laws on the same project.   


SECTION (26) Emergency Clause.
 COMPARISON OF ORIGINAL TO SUBSTITUTE 

SECTION 1.  The substitute deletes the proposed amendments to Section
28.002 of the Property Code relating to prompt pay.  This is the subject
of separate legislation.   

 Section 1 of the substitute renumbers the section relating to homestead
liens in Sec. 41.001 of the Property Code. 

SECTION 2.   The substitute deletes the proposed Sec. 28.0021 of the
Property Code relating to the release required in connection with the
prompt pay statute.  This is the subject of separate legislation.   

 Section 2 of the substitute defines "residence", "residential
construction contract", and "residential construction project."  These
terms are necessary in order to determine which claims and contracts are
subject to the new Subchapter K relating to residential construction.
With these definitions, the special procedures and disclosure mandated by
the new Subchapter K will relate to construction on property owned by
individuals who use or intend to use that property as a residence or
dwelling.  It will not include speculative or tract building where the
contractor or developer owns the property and sells the house after
construction has been completed.  It will also not include residential
structures an individual is building for resale or lease to a third party.
It will include homestead property as well as second homes or vacation
homes.  It will also cover the situation in which the consumer is living
in its homestead but is building a home which it intends to be homestead
when the improvements are completed. 

SECTION 3.   The substitute deletes the proposed amendments to Sections
28.006 of the Property Code relating to prompt pay.  This is the subject
of separate legislation.   

 Section 3 of the substitute inserts the reference to the new Subchapter K
in Section 53.003. 

SECTION 4.   The substitute deletes the proposed amendments to Sections
28.007 of the Property Code relating to prompt pay.  This is the subject
of separate legislation.   

 Section 4 of the substitute amends Sec. 53.026 which is commonly referred
to as the "sham contractor statute".  Currently, if an owner controls the
general contractor through ownership or otherwise, they are deemed to be a
single party of interest for purposes of determining the appropriate
notices and time periods.  The substitute provides that, if the contractor
controls the owner, they will also be deemed to be a single party of
interest.  This will assist subcontractors and suppliers who must file
lien or bond claims. 

SECTION 5.   The original HB 740 changes the name of Chapter 53 to conform
to its proposed addition of a new Chapter relating to residential
mechanic's lien laws.  

 Section 5 of the substitute deletes that proposed change because a new
Chapter is not created.  Instead, a new subchapter K is created for
residential construction contracts.  Section 5 of the substitute changes
the time for filing a mechanic's lien affidavit in connection with a lien
on a residential construction project.  It shortens the time for claimants
to file the affidavit by one month. 

SECTION 6.   The original bill created a new Sec. 53.0011 which
distinguished between claims under Chapter 53 and claims covered by the
new Chapter relating to residential construction. Because the new Chapter
is not created, this new Section was deleted.   

 Section 6 of the substitute makes several changes in the requirements for
the content of the lien affidavit.  Most are relatively minor (adding last
known addresses).  However, a claimant will have to state the month or
months in which the work was furnished and for which payment is sought.
Also, the claimant must provide a statement as to when the notices of
claim were sent and the method by which they were sent.  

 SECTION 7. The original bill's proposed amendment to Sec. 53.021 is
deleted because the new Chapter is not created.    

 Section 7 of the substitute changes the time period in which a claimant
must sent a copy of the lien affidavit to the owner.  Currently, a
claimant may have up to ten days to send an owner a copy of the affidavit.
Under the substitute, the claimant will have to send a copy of the
affidavit no later than one business day after the affidavit is filed or
record. 

SECTION 8.   The original bill's proposed amendment to Sec. 53.022 is
deleted because the new Chapter is not created.    

 Section 8 of the substitute inserts the reference to the new Subchapter K
in Section 53.056. 

SECTION 9.  The original bill's proposed amendment to Sec. 53.026 is
deleted because the new Chapter is not created.    

 Section 9 of the substitute inserts the reference to the new Subchapter K
in Section 53.057. 

SECTION 10.   The original bill's proposed amendment to Sec. 53.085 is
moved to Section 13 of the substitute (see below).    

 Section 10 of the substitute inserts the reference to the new Subchapter
K in Section 53.058. 


SECTION 11.   The original bill's proposed amendment to Sec. 53.105 is
deleted because the new Chapter is not created.    

 Section 11 of the substitute amends Sec. 53.081 to conform to the new
provisions in Subchapter K. 

SECTION 12.    The original bill's proposed amendment to Sec. 53.123 is
deleted because the new Chapter is not created.    

 Section 12  of the substitute inserts the reference to the new Subchapter
K in Section 53.084. 

SECTION 13.    The original bill's proposed amendment to Sec. 53.155 is
deleted because the new Chapter is not created.    

 Section 13 of the new bill amends Sec. 53.085 relating to the bills paid
affidavit.  The original bill had proposed several changes to the bills
paid affidavit provisions.  Many of those changes are carried forward in
the substitute; however, some additional changes are made.  In the
substitute, there is an express recognition that the affidavit may include
additional contractual provisions relating to a conditional waiver of
liens, a warranty or representation that bills will be paid, and an
indemnification for loss caused by inaccurate information.  The substitute
also deletes the reference to a statutory form which could actually
detract from the legal effect of the affidavit (could a person be
prosecuted for a false affidavit if it varied from the statutory form?).
Also the substitute expressly provides that the person signing the
affidavit is personally liable for false or incorrect information. 

SECTION 14.  The original bill created a new Chapter 62 which covered
claims arising from residential construction.  This new Chapter would
cover all forms of residential construction, including tract or
speculative homebuilding (i.e., where the developer actually builds the
improvements and sells a completed home to the consumer).  Tract or
speculative building makes up a large percentage of new home construction
in Texas and the consumer complaints in the Interim Study were not
directed to this segment of the industry.  Accordingly, this broader
Chapter 62 was deleted in the substitute. 

Instead of creating an entirely new Chapter in the Property Code separate
and apart from the current lien laws, a new Subchapter K in the lien laws
(Chapter 53) was created which mandates special notices and requirements
for lien claimants on consumer type residential construction.   

 Section 14 of the original bill required disclosures to be provided to
the owner by the contractor and lender.  It also imposed payment
monitoring requirements on the lender.  The substitute (in various
Sections of the bill) actually expands the disclosure requirements imposed
on both the contractor and lender.  The substitute eliminated the active
monitoring requirement imposed on lenders but does impose a requirement on
lenders of obtaining and furnishing a disbursement statement to the owner
before loan proceeds are advanced to the contractor. 

To assist owners in removing questionable lien claims from their property,
Section 14 of the original bill created a rather cumbersome procedure
which would have required claimants to file legal proceedings in order to
perfect lien claims.  It was felt that this might discourage invalid
claims; however, the substitute takes a different, more efficient
approach.  It amends the current statutes to make it easier to obtain a
bond to release or remove a disputed lien.  Most significantly, it creates
a summary proceeding in any litigation between the owner and the claimant
which allows the owner to obtain an expeditious hearing on the validity of
the disputed lien and gives the owner an opportunity to have an order
entered which would remove the lien and the cloud on the owner's property. 

 Section 14 reduced the time periods imposed on claimants for sending
notices and filing liens.  It also eliminated the statutory retain age
requirements on all residential type construction. The substitute also
reduces the time periods but those reduced time periods only apply to
residential projects in which the consumer owns the property and is having
the improvements built or repaired for its own, personal use.  At the
strong urging of the supply and subcontractor industries, statutory retain
age (which can benefit the owner as well) is not eliminated in the
substitute. 

 Section 14 of the substitute amends Sec. 53.106 relating to the Affidavit
of Completion. 

SECTION  15. The substitute deletes the proposed amendments to Section
162.001 of the Property Code relating to construction trust funds.  This
is the subject of separate legislation.  See discussion of Section 15 in
Bill Analysis above. 
 
SECTION 16.  The substitute deletes the proposed amendments to Section
162.003 of the Property Code relating to construction trust funds.  This
is the subject of separate legislation.  See discussion of Section 16 in
Bill Analysis above. 
 
SECTION 17.   The substitute deletes the proposed amendments to Section
162.005 of the Property Code relating to construction trust funds.  This
is the subject of separate legislation.  See discussion of Section 17 in
Bill Analysis above.  

SECTION 18.   The substitute deletes the proposed amendments to Subchapter
A of Chapter 162 of the Property Code relating to construction trust
funds.  This is the subject of separate legislation.    See discussion of
Section 18 in Bill Analysis above. 

SECTION 19.   The substitute deletes the proposed amendments to Section
162.032 of the Property Code relating to construction trust funds.  This
is the subject of separate legislation.  See discussion of Section 19 in
Bill Analysis above. 

SECTION 20.  This Section has been renumbered in the substitute as Section
24.    See discussion of Section 20 in Bill Analysis above. 

SECTION 21.  This Section has been renumbered in the substitute as Section
25.  The effective date has been changed in the substitute to provide that
the changes in the law will be effective as to all matters arising under
original contracts entered into on or after the effective date.    See
discussion of Section 21 in Bill Analysis above. 

SECTION 22.   This Section has been renumbered in the substitute as
Section 26.    See discussion of Section 22 in Bill Analysis above. 

SECTIONS 23 through 26.  These Sections are new in the substitute.  See
discussions above.