By Solomons                                      H.B. No. 740

      75R2416 PAM-D                           

                                A BILL TO BE ENTITLED

 1-1                                   AN ACT

 1-2     relating to mechanics', contractors', and materialmen's liens;

 1-3     providing penalties.

 1-4           BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

 1-5           SECTION 1.  Section 28.002, Property Code, is amended to read

 1-6     as follows:

 1-7           Sec. 28.002.  Prompt Pay Required.  (a)  If an owner receives

 1-8     a written payment request from a contractor for an amount that is

 1-9     allowed to the contractor for properly performed work or suitably

1-10     stored materials, the owner shall pay the amount to the contractor,

1-11     less any statutory offsets, not later than the 45th day after the

1-12     date the owner receives the request.

1-13           (b)  If a [A] contractor receives a written payment request

1-14     from a subcontractor for an amount that is allowed to the

1-15     subcontractor for properly performed work or suitably stored

1-16     materials, the contractor [who receives a payment under Subsection

1-17     (a) or otherwise from an owner in connection with a contract to

1-18     improve real property] shall pay the amount to the subcontractor,

1-19     less any statutory offsets, [each of its subcontractors the portion

1-20     of the owner's payment, including interest, if any, that is

1-21     attributable to work performed or materials suitably stored by that

1-22     subcontractor if payment for stored materials is provided for in

1-23     the contract, to the extent of that subcontractor's interest in the

1-24     owner's payment.  The payment required by this subsection must be

 2-1     made] not later than the 45th [seventh] day after the date the

 2-2     contractor receives the subcontractor's request [owner's payment].

 2-3           (c)  If a [A] subcontractor who contracts with a secondary

 2-4     subcontractor receives a written payment request from the secondary

 2-5     subcontractor for an amount that is allowed to the secondary

 2-6     subcontractor for properly performed work or suitably stored

 2-7     materials, the initial subcontractor [who receives a payment under

 2-8     Subsection (b) or otherwise from a contractor in connection with a

 2-9     contract to improve real property] shall pay the amount to the

2-10     secondary subcontractor, less any statutory offsets, [each of its

2-11     subcontractors the portion of the payment, including interest, if

2-12     any, that is attributable to work performed or materials suitably

2-13     stored by that subcontractor if payment for stored materials is

2-14     provided for in the contract, to the extent of that subcontractor's

2-15     interest in the payment.  The payment required by this subsection

2-16     must be made] not later than the 45th [seventh] day after the date

2-17     the initial subcontractor receives the secondary subcontractor's

2-18     request [contractor's payment].

2-19           (d)  A contractor who violates Subsection (b) is liable to

2-20     the subcontractor for one and one-half times the amount of the

2-21     contract price for the subcontractor's labor and materials, plus

2-22     reasonable attorney's fees and court costs incurred by the

2-23     subcontractor in an effort to collect payment.  A subcontractor who

2-24     violates Subsection (c) is liable to the secondary subcontractor

2-25     for one and one-half times the amount of the contract price for the

2-26     secondary subcontractor's labor and materials, plus reasonable

2-27     attorney's fees and court costs incurred by the secondary

 3-1     subcontractor in an effort to collect payment.

 3-2           (e)  A provision in a contract between a contractor and a

 3-3     subcontractor that requires the contractor to pay the subcontractor

 3-4     only if the contractor is paid is unenforceable.  A provision in a

 3-5     contract between a subcontractor and a secondary subcontractor that

 3-6     requires the initial subcontractor to pay the secondary

 3-7     subcontractor only if the initial contractor is paid is

 3-8     unenforceable.

 3-9           SECTION 2.  Chapter 28, Property Code, is amended by adding

3-10     Section 28.0021 to read as follows:

3-11           Sec. 28.0021.  RELEASE REQUIRED.  When a debt owed to a

3-12     subcontractor for labor or materials is paid or otherwise

3-13     satisfied, the subcontractor shall, not later than the 10th day

3-14     after the date the debt is satisfied, execute and deliver to the

3-15     person who satisfies the debt a written release of the indebtedness

3-16     to the extent of the indebtedness paid.

3-17           SECTION 3.  Section 28.006(b), Property Code, is amended to

3-18     read as follows:

3-19           (b)  A written contract between an owner and a contractor for

3-20     improvements to or construction of a single-family residence may

3-21     provide that the payment required under Section 28.002(a) be made

3-22     not later than a date that occurs before the 61st day after the

3-23     date the owner receives the payment request.  An [Notwithstanding

3-24     Section 28.004(b), an] unpaid amount under contract subject to this

3-25     subsection that allows payment later than the date otherwise

3-26     required under Section 28.002(a) bears interest at the rate of 1

3-27     1/2  percent each month.

 4-1           SECTION 4.  Section 28.007(b), Property Code, is amended to

 4-2     read as follows:

 4-3           (b)  Nothing in this statute shall be interpreted to change

 4-4     the rights and obligations set forth in Chapter 53 or 62, Property

 4-5     Code.

 4-6           SECTION 5.  The title to Chapter 53, Property Code, is

 4-7     amended to read as follows:

 4-8         CHAPTER 53.  MECHANIC'S, CONTRACTOR'S OR MATERIALMAN'S LIEN

 4-9                  ON COMMERCIAL AND CERTAIN OTHER PROPERTY

4-10           SECTION 6.  Subchapter A, Chapter 53, Property Code, is

4-11     amended by adding Section 53.0011 to read as follows:

4-12           Sec. 53.0011.  APPLICABILITY.  This chapter applies only to

4-13     real property that is not covered by Chapter 62.

4-14           SECTION 7.  Section 53.021(a), Property Code, is amended to

4-15     read as follows:

4-16           (a)  A person has a lien if:

4-17                 (1)  the person labors, specially fabricates material,

4-18     or furnishes labor or materials for construction or repair in this

4-19     state of:

4-20                       (A)  a [house,] building[,] or improvement;

4-21                       (B)  a levee or embankment to be erected for the

4-22     reclamation of overflow land along a river or creek; or

4-23                       (C)  a railroad; and

4-24                 (2)  the person labors, specially fabricates the

4-25     material, or furnishes the labor or materials under or by virtue of

4-26     a contract with the owner or the owner's agent, trustee, receiver,

4-27     contractor, or subcontractor.

 5-1           SECTION 8.  Sections 53.022(a), (c), and (d), Property Code,

 5-2     are amended to read as follows:

 5-3           (a)  The lien extends to the [house,] building, fixtures, or

 5-4     improvements, the land reclaimed from overflow, or the railroad and

 5-5     all of its properties, and to each lot of land necessarily

 5-6     connected or reclaimed.

 5-7           (c)  A lien against land in a city, town, or village extends

 5-8     to each lot on which the [house,] building[,] or improvement is

 5-9     situated or on which the labor was performed.

5-10           (d)  A lien against land not in a city, town, or village

5-11     extends to not more than 50 acres on which the [house,] building[,]

5-12     or improvement is situated or on which the labor was performed.

5-13           SECTION 9.  Section 53.026(a), Property Code, is amended to

5-14     read as follows:

5-15           (a)  A person who labors, specially fabricates materials, or

5-16     furnishes labor or materials under a direct contractual

5-17     relationship with another person is considered to be in direct

5-18     contractual relationship with the owner and has a lien as an

5-19     original contractor, if:

5-20                 (1)  the owner contracted with the other person for the

5-21     construction or repair of a [house,] building[,] or improvements

5-22     and the owner can effectively control that person through ownership

5-23     of voting stock, interlocking directorships, or otherwise; or

5-24                 (2)  the owner contracted with the other person for the

5-25     construction or repair of a [house,] building[,] or improvements

5-26     and the contract was made without good faith intention of the

5-27     parties that the other person was to perform the contract.

 6-1           SECTION 10.  Section 53.085, Property Code, is amended to

 6-2     read as follows:

 6-3           Sec. 53.085.  Affidavit Required.  (a)  Any person who

 6-4     furnishes labor or materials for the construction of improvements

 6-5     on real property shall, [if requested and] as a condition of

 6-6     payment for such labor or materials, provide to the receiving

 6-7     [requesting] party, or its agent, an affidavit stating that such

 6-8     person has paid each of his subcontractors, laborers, or

 6-9     materialmen in full for all labor and materials provided to him for

6-10     the construction.  In the event, however, that the person has not

6-11     paid each of his subcontractors, laborers, or materialmen in full,

6-12     the person shall state in the affidavit the amount owed and the

6-13     name and, if known, the address and telephone number of each

6-14     subcontractor, laborer, or materialman to whom such payment is

6-15     owed.

6-16           (b)  The seller of any real property shall, [upon request by

6-17     the purchaser or its agent] prior to closing of the purchase of

6-18     such real property, provide to such purchaser or its agent, a

6-19     written affidavit stating that the seller has paid each of his

6-20     contractors, laborers, or materialmen in full for all labor and

6-21     materials provided to the seller for any construction of

6-22     improvements on the real property and that the seller is not

6-23     indebted to any person, firm, or corporation by reason of any such

6-24     construction.  In the event that the seller has not paid each of

6-25     his contractors, laborers, or materialmen in full, the seller shall

6-26     state in the affidavit the amount owed and the name and, if known,

6-27     the address and telephone number of each contractor, laborer, or

 7-1     materialman to whom such payment is owed.

 7-2           (c)  The affidavit required by this section must, at a

 7-3     minimum, read substantially similar to the following:

 7-4                       (AWAITING FORM TO BE INSERTED)

 7-5           (d)  A person, including a seller, commits an offense if the

 7-6     person intentionally, knowingly, or recklessly makes a false or

 7-7     misleading statement in an affidavit under this section.  An

 7-8     offense under this section is a [Class A] misdemeanor.  A person

 7-9     adjudged guilty of an offense under this section shall be punished

7-10     by a fine not to exceed $4,000 and confinement in jail for a term

7-11     not to exceed one year.  A person may not receive community

7-12     supervision for the offense.

7-13           SECTION 11.  Section 53.105(a), Property Code, is amended to

7-14     read as follows:

7-15           (a)  If the owner fails or refuses to comply with this

7-16     subchapter, the claimants complying with this chapter have a lien,

7-17     at least to the extent of the amount that should have been retained

7-18     from the original contract under which they are claiming, against

7-19     the [house,] building, structure, fixture, or improvement and all

7-20     of its properties and against the lot or lots of land necessarily

7-21     connected.

7-22           SECTION 12.  Section 53.123(a), Property Code, is amended to

7-23     read as follows:

7-24           (a)  Except as provided by this section, a mechanic's lien

7-25     attaches to the [house,] building, improvements, or railroad

7-26     property in preference to any prior lien, encumbrance, or mortgage

 8-1     on the land on which it is located, and the person enforcing the

 8-2     lien may have the [house,] building, improvement, or any piece of

 8-3     the railroad property sold separately.

 8-4           SECTION 13.  Section 53.155, Property Code, is amended to

 8-5     read as follows:

 8-6           Sec. 53.155.  Transfer of Property Sold.  If the [house,]

 8-7     building, improvement, or any piece of railroad property is sold

 8-8     separately, the officer making the sale shall place the purchaser

 8-9     in possession.  The purchaser is entitled to a reasonable time

8-10     after the date of purchase within which to remove the purchased

8-11     property.

8-12           SECTION 14.  Subtitle B, Title 5, Property Code, is amended

8-13     by adding Chapter 62 to read as follows:

8-14        CHAPTER 62.  MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN

8-15                           ON RESIDENTIAL PROPERTY

8-16                      SUBCHAPTER A.  GENERAL PROVISIONS

8-17           Sec. 62.001.  DEFINITIONS.  In this chapter:

8-18                 (1)  "Contract price" means the cost to the owner for

8-19     any part of construction or repair performed under an original

8-20     contract.

8-21                 (2)  "Improvement" includes:

8-22                       (A)  abutting sidewalks and streets and utilities

8-23     in or on those sidewalks and streets;

8-24                       (B)  clearing, grubbing, draining, or fencing of

8-25     land;

8-26                       (C)  wells, cisterns, tanks, reservoirs, or

8-27     artificial lakes or pools made for supplying or storing water;

 9-1                       (D)  pumps, siphons, and windmills or other

 9-2     machinery or apparatuses used for raising water for stock, domestic

 9-3     use, or irrigation; and

 9-4                       (E)  planting orchard trees, grubbing out

 9-5     orchards and replacing trees, and pruning of orchard trees.

 9-6                 (3)  "Labor" means labor used in the direct prosecution

 9-7     of the work.

 9-8                 (4)  "Material" means all or part of:

 9-9                       (A)  the material, machinery, fixtures, or tools

9-10     incorporated into the work, consumed in the direct prosecution of

9-11     the work, or ordered and delivered for incorporation or

9-12     consumption;

9-13                       (B)  rent at a reasonable rate and actual running

9-14     repairs at a reasonable cost for construction equipment used or

9-15     reasonably required and delivered for use in the direct prosecution

9-16     of the work at the site of the construction or repair; or

9-17                       (C)  power, water, fuel, and lubricants consumed

9-18     or ordered and delivered for consumption in the direct prosecution

9-19     of the work.

9-20                 (5)  "Mechanic's lien" means the lien provided by this

9-21     chapter.

9-22                 (6)  "Original contract" means an agreement to which an

9-23     owner is a party either directly or by implication of law.

9-24                 (7)  "Original contractor" means a person contracting

9-25     with an owner either directly or through the owner's agent.

9-26                 (8)  "Specially fabricated material" means material

9-27     fabricated for use as a component of the construction or repair so

 10-1    as to be reasonably unsuitable for use elsewhere.

 10-2                (9)  "Subcontractor" means a person who has furnished

 10-3    labor or materials to fulfill an obligation to an original

 10-4    contractor or to a subcontractor to perform all or part of the work

 10-5    required by an original contract.

 10-6                (10)  "Work" means any part of construction or repair

 10-7    performed under an original contract.

 10-8          Sec. 62.002.  APPLICABILITY.  This chapter applies only to

 10-9    real property:

10-10                (1)  on which exists or for which a contract is

10-11    executed to construct a structure that consists of not more than

10-12    four units intended as the principal place of residence for a

10-13    person or family; or

10-14                (2)  that is a homestead as provided by Chapter 41.

10-15          Sec. 62.003.  MORE THAN ONE ORIGINAL CONTRACTOR.  On any work

10-16    there may be more than one original contractor for purposes of this

10-17    chapter.

10-18              (Sections 62.004-62.020 reserved for expansion

10-19        SUBCHAPTER B.  REQUIRED DOCUMENTATION AND RESPONSIBILITIES

10-20                                OF PARTIES

10-21          Sec. 62.021.  DISCLOSURE STATEMENT REQUIRED FOR HOMESTEAD

10-22    PROPERTY.  (a)  If the property on which improvements are to be

10-23    constructed or repairs are to be made is homestead property, the

10-24    original contractor shall execute and deliver to the owner before

10-25    the work commences a disclosure statement described by this

10-26    section.

10-27          (b)  The statement must disclose:

 11-1                (1)  the cost of the work to be performed;

 11-2                (2)  the contract price for the work if a sum certain

 11-3    is agreed to by the parties;

 11-4                (3)  the percentage rate charged above the cost of the

 11-5    work and the estimated final cost to the purchaser if the contract

 11-6    provides for a price based on the cost of the work plus a certain

 11-7    percentage; and

 11-8                (4)  the estimated date of completion of the work.

 11-9          (c)  The original contractor shall attach to the disclosure

11-10    statement a list that identifies by name, address, and telephone

11-11    number each subcontractor and supplier the contractor intends to

11-12    use in the work to be performed.  The contractor shall provide the

11-13    owner with an updated list of subcontractors and suppliers not

11-14    later than the 15th day after the date a subcontractor or supplier

11-15    is added or deleted.

11-16          (d)  The statement must contain the following notice

11-17    conspicuously printed, stamped, or typed in a size equal to

11-18    10-point boldface or the computer equivalent, at the top of each

11-19    page of the list of subcontractors and suppliers:

11-20    NOTICE:  THIS LIST OF SUBCONTRACTORS AND SUPPLIERS MAY NOT BE A

11-21    FINAL LISTING.  THE CONTRACTOR IS REQUIRED BY LAW TO SUPPLY UPDATED

11-22    INFORMATION, AS THE INFORMATION BECOMES AVAILABLE, FOR EACH

11-23    SUBCONTRACTOR OR SUPPLIER USED IN THE WORK PERFORMED ON YOUR

11-24    RESIDENCE.  UPON PAYMENT TO EACH SUBCONTRACTOR OR SUPPLIER, YOU ARE

11-25    ENTITLED TO RECEIVE A WAIVER OF LIEN.

11-26          Sec. 62.022.  PROVISIONS RELATED TO CLOSING OF LOAN FOR

11-27    CONSTRUCTION OF IMPROVEMENTS.  (a)  If the owner is obtaining

 12-1    third-party financing for the construction of improvements, the

 12-2    lender shall deliver to the owner all documentation relating to the

 12-3    closing of the loan not less than 24 hours before the time of the

 12-4    closing.  This provision may not be waived by the owner.  If the

 12-5    lender fails to comply with this section, the owner may contest the

 12-6    validity of any document delivered in violation of this section.

 12-7          (b)  If an owner obtains interim financing during the

 12-8    construction of the improvement, the lender shall verify that the

 12-9    owner has filed a notice of completion as provided by Sections

12-10    62.083 and 62.084 before the lender may fund the permanent loan.

12-11          Sec. 62.023.  PAYMENT MONITORING REQUIRED.  (a)  The original

12-12    contractor shall provide to the owner, if the construction of the

12-13    improvements is owner-financed, or to the lender, if the

12-14    construction of the improvements is financed by a third party, a

12-15    periodic statement of funds disbursed.

12-16          (b)  If the construction of the improvements is financed by a

12-17    third party, the lender shall provide to the owner a periodic

12-18    statement of funds disbursed.

12-19          (c)  The disbursement statements required by this section

12-20    must be provided at least once a month during the construction

12-21    period.

12-22          (d)  A person commits an offense if the person intentionally,

12-23    knowingly, or recklessly provides false or misleading information

12-24    in a disbursement statement required under this section.  An

12-25    offense under this section is a misdemeanor.  A person adjudged

12-26    guilty of an offense under this section shall be punished by a fine

12-27    not to exceed $4,000 and confinement in jail for a term not to

 13-1    exceed one year.  A person may not receive community supervision

 13-2    for the offense.

 13-3          Sec. 62.024.  FINAL BILLS PAID AFFIDAVIT REQUIRED.  (a)  As a

 13-4    condition of final payment under the original contract, the

 13-5    original contractor shall, at the time the final payment is

 13-6    tendered, execute and deliver to the owner, or the owner's agent,

 13-7    an affidavit stating that the original contractor has paid each

 13-8    person in full for all labor and materials used in the construction

 13-9    of improvements on the real property.  If the original contractor

13-10    has not paid each person in full, the original contractor shall

13-11    state in the affidavit the amount owed and the name and, if known,

13-12    the address and telephone number of each person to whom a payment

13-13    is owed.

13-14          (b)  The seller of any real property shall, at the closing of

13-15    the purchase of the real property, execute and deliver to the

13-16    purchaser, or the purchaser's agent, an affidavit stating that the

13-17    seller has paid each person in full for all labor and materials

13-18    used in the construction of improvements on the real property and

13-19    that the seller is not indebted to any person by reason of any

13-20    construction.  In the event that the seller has not paid each

13-21    person in full, the seller shall state in the affidavit the amount

13-22    owed and the name and, if known, the address and telephone number

13-23    of each person to whom a payment is owed.

13-24          (c)  A person commits an offense if the person intentionally,

13-25    knowingly, or recklessly makes a false or misleading statement in

13-26    an affidavit under this section.  An offense under this section is

13-27    a misdemeanor.  A person adjudged guilty of an offense under this

 14-1    section shall be punished by a fine not to exceed $4,000 and

 14-2    confinement in jail for a term not to exceed one year.  A person

 14-3    may not receive community supervision for the offense.

 14-4          (d)  The affidavit required by this section must, at a

 14-5    minimum, read substantially similar to the following:

 14-6                      (AWAITING FORM TO BE INSERTED)

 14-7              (Sections 62.025-62.050 reserved for expansion

 14-8         SUBCHAPTER C.  PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY

 14-9          Sec. 62.051.  PERSONS ENTITLED TO LIEN.  (a)  A person has a

14-10    lien if:

14-11                (1)  the person labors, specially fabricates material,

14-12    or furnishes labor or materials for construction or repair in this

14-13    state of a house, building, or improvement; and

14-14                (2)  the person labors, specially fabricates the

14-15    material, or furnishes the labor or materials under or by virtue of

14-16    a contract with the owner or the owner's agent, trustee, receiver,

14-17    contractor, or subcontractor.

14-18          (b)  A person who specially fabricates material has a lien

14-19    even if the material is not delivered.

14-20          (c)  An architect, engineer, or surveyor who prepares a plan

14-21    or plat under or by virtue of a written contract with the owner or

14-22    the owner's agent, trustee, or receiver in connection with the

14-23    actual or proposed design, construction, or repair of improvements

14-24    on real property or the location of the boundaries of real property

14-25    has a lien on the property.

14-26          Sec. 62.052.  PROPERTY TO WHICH LIEN EXTENDS.  (a)  The lien

 15-1    extends to the house, building, fixtures, or improvements and to

 15-2    each lot of land necessarily connected or reclaimed.

 15-3          (b)  The lien does not extend to abutting sidewalks, streets,

 15-4    and utilities that are public property.

 15-5          (c)  A lien against land in a city, town, or village extends

 15-6    to each lot on which the house, building, or improvement is

 15-7    situated or on which the labor was performed.

 15-8          (d)  A lien against land not in a city, town, or village

 15-9    extends to not more than 50 acres on which the house, building, or

15-10    improvement is situated or on which the labor was performed.

15-11          Sec. 62.053.  PAYMENT SECURED BY LIEN.  The lien secures

15-12    payment for:

15-13                (1)  the labor done or material furnished to the land

15-14    for the construction or repair;

15-15                (2)  the specially fabricated material, even if the

15-16    material has not been delivered or incorporated into the

15-17    construction or repair, less its fair salvage value; or

15-18                (3)  the preparation of a plan or plat by an architect,

15-19    engineer, or surveyor in accordance with Section 62.051(c).

15-20          Sec. 62.054.  LIMITATION ON SUBCONTRACTOR'S LIEN.  The amount

15-21    of a lien claimed by a subcontractor may not exceed:

15-22                (1)  an amount equal to the proportion of the total

15-23    subcontract price that the sum of the labor performed, materials

15-24    furnished, materials specially fabricated, reasonable overhead

15-25    costs incurred, and proportionate profit margin bears to the total

15-26    subcontract price; minus

15-27                (2)  the sum of previous payments received by the

 16-1    claimant on the subcontract.

 16-2          Sec. 62.055.  SHAM CONTRACT.  (a)  A person who labors,

 16-3    specially fabricates materials, or furnishes labor or materials

 16-4    under a direct contractual relationship with another person is

 16-5    considered to be in direct contractual relationship with the owner

 16-6    and has a lien as an original contractor, if:

 16-7                (1)  the owner contracted with the other person for the

 16-8    construction or repair of a house, building, or improvement and the

 16-9    owner can effectively control that person through ownership of

16-10    voting stock, interlocking directorships, or otherwise; or

16-11                (2)  the owner contracted with the other person for the

16-12    construction or repair of a house, building, or improvement and the

16-13    contract was made without good faith intention of the parties that

16-14    the other person was to perform the contract.

16-15          (b)  In this section, "owner" does not include a person who

16-16    has or claims a security interest only.

16-17              (Sections 62.056-62.080 reserved for expansion

16-18               SUBCHAPTER D.  PROCEDURE FOR PERFECTING LIEN

16-19          Sec. 62.081.  NECESSARY PROCEDURES.  To perfect the lien, a

16-20    person must comply with this subchapter.

16-21          Sec. 62.082.  FILING OF APPLICATION.  (a)  A person claiming

16-22    a lien in an amount of $5,000 or less must file an application for

16-23    lien in the justice court in the precinct in which the property is

16-24    located not later than the 60th day after the date of completion.

16-25          (b)  A person claiming a lien in an amount of more than

16-26    $5,000 must file an application for lien with the county clerk of

16-27    the county in which the property is located not later than the 60th

 17-1    day after the date of completion.

 17-2          (c)  The clerk of the court or the person fulfilling the

 17-3    duties of the clerk of the court shall record the application in

 17-4    records kept for that purpose and shall index and cross-index the

 17-5    application in the names of the lien claimant, the original

 17-6    contractor, and the owner.

 17-7          Sec. 62.083.  DATE OF COMPLETION.  (a)  For purposes of

 17-8    Section 62.082, the date of completion is the first day after the

 17-9    date that the owner, original contractor, or subcontractor:

17-10                (1)  publishes a notice of completion stating that the

17-11    improvement has been completed or has been abandoned; and

17-12                (2)  files with the county clerk of the county in which

17-13    the property is located:

17-14                      (A)  an affidavit verifying the publication of

17-15    the notice of completion; and

17-16                      (B)  a copy of the notice of completion.

17-17          (b)  The notice of completion must be published once in a

17-18    newspaper of general circulation in the county in which the

17-19    property is located.

17-20          (c)  The original contractor for the improvement may publish

17-21    the notice and file the affidavit only if:

17-22                (1)  the contractor has requested in writing that the

17-23    owner publish the notice and file the affidavit; and

17-24                (2)  the owner has failed to publish the notice and

17-25    file the affidavit within five days after the date the owner

17-26    received the written request.

17-27          (d)  A subcontractor for the improvement may publish the

 18-1    notice and file the affidavit only if:

 18-2                (1)  the subcontractor has requested in writing that

 18-3    the original contractor publish the notice and file the affidavit

 18-4    or request the owner to publish the notice and file the affidavit;

 18-5    and

 18-6                (2)  the original contractor has failed to publish the

 18-7    notice and file the affidavit or request the owner to publish the

 18-8    notice and file the affidavit within five days after the date the

 18-9    contractor received the written request.

18-10          (e)  If a notice of completion is not published and filed

18-11    before the first anniversary of the date on which the improvement

18-12    is actually completed or abandoned, the date of completion for the

18-13    improvement is considered to be the first anniversary of the date

18-14    on which the improvement was completed or abandoned.

18-15          Sec. 62.084.  NOTICE OF COMPLETION.  (a)  The notice of

18-16    completion must contain:

18-17                (1)  the name and address of the owner;

18-18                (2)  the name and address of the original contractor;

18-19                (3)  a description, legally sufficient for

18-20    identification, of the real property on which the improvements are

18-21    located;

18-22                (4)  a description of the improvements furnished under

18-23    the contract; and

18-24                (5)  a statement that the improvements under the

18-25    original contract have been completed.

18-26          (b)  The notice of completion is effective only if the

18-27    improvement has been substantially completed or the improvement has

 19-1    been abandoned before the notice is published.

 19-2          (c)  The notice of completion is not an admission by the

 19-3    owner or the original contractor that the improvement has been

 19-4    satisfactorily completed.

 19-5          (d)  The county clerk shall record the notice of completion

 19-6    in records kept for that purpose.  Failure of the county clerk to

 19-7    properly record the notice does not invalidate the notice.

 19-8          Sec. 62.085.  CONTENTS OF APPLICATION.  (a)  The application

 19-9    must be signed by the person claiming the lien or by another person

19-10    on the claimant's behalf and must contain substantially:

19-11                (1)  a sworn statement of the claim, including the

19-12    amount;

19-13                (2)  the name of the owner or reputed owner;

19-14                (3)  the name of any person with an interest in the

19-15    property;

19-16                (4)  a general statement of the kind of work done and

19-17    materials furnished by the claimant;

19-18                (5)  the name of the person by whom the claimant was

19-19    employed or to whom the claimant furnished the materials or labor;

19-20                (6)  the name of the original contractor;

19-21                (7)  a description, legally sufficient for

19-22    identification, of the property sought to be charged with the lien;

19-23    and

19-24                (8)  the claimant's business address.

19-25          (b)  The claimant may attach to the application a copy of any

19-26    applicable written agreement or contract.

19-27          (c)  The application is not required to set forth individual

 20-1    items of work done or material furnished or specially fabricated.

 20-2    The application may use any abbreviations or symbols customary in

 20-3    the trade.

 20-4          Sec. 62.086.  SERVICE OF NOTICE OF FILED APPLICATION.  (a)  A

 20-5    copy of the application for lien shall be served in the manner

 20-6    prescribed by law for the service of summons on:

 20-7                (1)  the owner of the property;

 20-8                (2)  each person who contracted for the improvements to

 20-9    the property; and

20-10                (3)  any person with a recorded interest in the

20-11    property.

20-12          (b)  If a person entitled to notice cannot be served, notice

20-13    may be given to that person by posting notice on the improvement.

20-14          (c)  The application is returnable not less than three or

20-15    more than 10 days after service.

20-16          Sec. 62.087.  MEDIATION.  (a)  If an application for lien is

20-17    filed for an amount of $5,000 or less, the court may require the

20-18    parties to mediate the dispute.

20-19          (b)  If the application for lien is filed for an amount of

20-20    more than $5,000, the court shall require the parties to mediate

20-21    the dispute before proceeding under this subchapter.

20-22          Sec. 62.088.  HEARING.  (a)  After the application is

20-23    returned, the court shall set a hearing date to determine whether

20-24    probable cause exists to permit the lien to attach to the property.

20-25          (b)  Any person who is required to receive notice is

20-26    permitted to offer testimony and documentary evidence on the issue

20-27    of whether probable cause exists to permit the lien to attach to

 21-1    the property.

 21-2          (c)  If a person who contracted for the improvement from

 21-3    which the requested lien arises claims a set-off against the

 21-4    claimant or if any person who is required to receive notice

 21-5    disputes the amount of the requested lien, the court shall receive

 21-6    all evidence offered by that person.

 21-7          Sec. 62.089.  ORDER DIRECTING LIEN TO ATTACH.  (a)  The court

 21-8    shall enter an order directing the lien to attach only if the court

 21-9    determines that there is probable cause that the claim for the lien

21-10    is valid.

21-11          (b)  An order issued under this section is valid only if the

21-12    application and notice were served on and the opportunity to appear

21-13    was provided to:

21-14                (1)  the party contracting for the improvement;

21-15                (2)  the original contractor; and

21-16                (3)  the owner of the property.

21-17          (c)  The court may not issue an order directing the lien to

21-18    attach to an owner's property if the owner presents evidence in the

21-19    form of disbursement statements provided under Section 62.023 and

21-20    the affidavit required under Section 62.024 that represents to the

21-21    owner that the lien claimant was paid.

21-22          (d)  The order shall be filed with the county clerk in the

21-23    county in which the property is located.

21-24          Sec. 62.090.  HOMESTEAD.  (a)  To fix a lien on a homestead,

21-25    the person who is to furnish material or perform labor and the

21-26    owner must execute a written contract setting forth the terms of

21-27    the agreement.

 22-1          (b)  The contract must be executed before the material is

 22-2    furnished or the labor is performed.

 22-3          (c)  If the owner is married, the contract must be signed by

 22-4    both spouses.

 22-5          (d)  The contract must be filed with the county clerk of the

 22-6    county in which the homestead is located, who shall record it in

 22-7    records kept for that purpose.

 22-8          (e)  If the contract is made and recorded by an original

 22-9    contractor, the contract inures to the benefit of all persons who

22-10    labor or furnish material for the original contractor.

22-11          (f)  An application for lien filed under this subchapter that

22-12    relates to a homestead must contain the following notice

22-13    conspicuously printed, stamped, or typed in a size equal to at

22-14    least 10-point boldface or computer equivalent, at the top of the

22-15    page:

22-16          "NOTICE:  THIS IS NOT A LIEN.  THIS IS ONLY AN APPLICATION

22-17          FOR A LIEN."

22-18          (g)  For the lien on a homestead to be valid, the notice

22-19    required to be given to the owner under Section 62.086 must include

22-20    or have attached the following statement:

22-21          "If a subcontractor or supplier who furnishes materials or

22-22    performs labor for construction of improvements on your property is

22-23    not paid, your property may be subject to a lien for the unpaid

22-24    amount if after receiving notice of the application for lien, you

22-25    fail to withhold any remaining payment to your contractor that is

22-26    sufficient to cover the unpaid claim until the dispute is

22-27    resolved."

 23-1              (Sections 62.091-62.110 reserved for expansion

 23-2          SUBCHAPTER E.  FUNDS WITHHELD BY OWNER FOLLOWING ORDER

 23-3          Sec. 62.111.  AUTHORITY TO WITHHOLD FUNDS FOR BENEFIT OF

 23-4    CLAIMANTS.  (a)  The owner may withhold from payments to the

 23-5    original contractor an amount necessary to pay the claim for which

 23-6    a lien is ordered under Subchapter D.

 23-7          (b)  The owner may withhold the funds immediately on receipt

 23-8    of notice of the order.

 23-9          Sec. 62.112.  TIME FOR WHICH FUNDS ARE WITHHELD.  Unless the

23-10    claim is settled, discharged, indemnified against under Subchapter

23-11    H or I, or determined to be invalid by a final judgment of a court,

23-12    the owner shall retain the funds withheld until the lien claim has

23-13    been satisfied or released.

23-14          Sec. 62.113.  PAYMENT TO CLAIMANT ON DEMAND.  (a)  The

23-15    claimant may make written demand for payment of the claim to an

23-16    owner authorized to withhold funds under this subchapter.  The

23-17    demand must give notice to the owner that all or part of the claim

23-18    is past due according to the agreement between the parties.

23-19          (b)  The claimant must send a copy of the demand to the

23-20    original contractor.  The original contractor may give the owner

23-21    written notice that the contractor intends to dispute the claim.

23-22    The original contractor must give the notice not later than the

23-23    30th day after the date the contractor receives the copy of the

23-24    demand.  If the original contractor does not give the owner timely

23-25    notice, the contractor is considered to have assented to the demand

23-26    and the owner shall pay the claim.

23-27          (c)  The claimant's demand may accompany the original notice

 24-1    of a past-due claim and may be stamped or written in legible form

 24-2    on the face of the notice.

 24-3          Sec. 62.114.  OWNER'S LIABILITY.  (a)  The owner is not

 24-4    liable for any amount paid to the original contractor before the

 24-5    owner is authorized to withhold funds under this subchapter.

 24-6          (b)  The owner is liable and the owner's property is subject

 24-7    to a claim for any money paid to the original contractor after the

 24-8    owner was authorized to withhold funds under this subchapter.

 24-9              (Sections 62.115-62.140 reserved for expansion

24-10                 SUBCHAPTER F.  PRIORITIES AND PREFERENCES

24-11          Sec. 62.141.  PREFERENCE OVER OTHER CREDITORS.  All

24-12    subcontractors, laborers, and materialmen who have a mechanic's

24-13    lien have preference over other creditors of the original

24-14    contractor.

24-15          Sec. 62.142.  EQUALITY OF MECHANIC'S LIENS.  (a)  Perfected

24-16    mechanic's liens are on equal footing without reference to the date

24-17    of the order directing the lien.

24-18          (b)  If the proceeds of a foreclosure sale of property are

24-19    insufficient to discharge all mechanic's liens against the

24-20    property, the proceeds shall be paid pro rata on the perfected

24-21    mechanic's liens on which suit is brought.

24-22          (c)  This chapter does not affect the contract between the

24-23    owner and the original contractor as to the amount, manner, or time

24-24    of payment of the contract price.

24-25          Sec. 62.143.  PRIORITY OF MECHANIC'S LIEN OVER OTHER LIENS.

24-26    (a)  Except as provided by this section, a mechanic's lien attaches

24-27    to the house, building, or improvement in preference to any prior

 25-1    lien, encumbrance, or mortgage on the land on which it is located,

 25-2    and the person enforcing the lien may have the house, building, or

 25-3    improvement sold separately.

 25-4          (b)  The  mechanic's lien does not affect any lien,

 25-5    encumbrance, or mortgage on the land or improvement at the time of

 25-6    the inception of the mechanic's lien, and the holder of the lien,

 25-7    encumbrance, or mortgage need not be made a party to a suit to

 25-8    foreclose the mechanic's lien.

 25-9          Sec. 62.144.  INCEPTION OF MECHANIC'S LIEN.  (a)  For

25-10    purposes of Section 62.143, the time of inception of a mechanic's

25-11    lien is the commencement of construction of improvements or

25-12    delivery of materials to the land on which the improvements are to

25-13    be located and on which the materials are to be used.

25-14          (b)  The construction or materials under Subsection (a) must

25-15    be visible from inspection of the land on which the improvements

25-16    are being made.

25-17          (c)  An owner and original contractor may jointly file an

25-18    affidavit of commencement with the county clerk of the county in

25-19    which the land is located not later than the 30th day after the

25-20    date of actual commencement of construction of the improvements or

25-21    delivery of materials to the land.  The affidavit must contain:

25-22                (1)  the name and address of the owner;

25-23                (2)  the name and address of each original contractor

25-24    that is known at the time to the owner and that is furnishing

25-25    labor, service, or materials for the construction of the

25-26    improvements;

25-27                (3)  a description, legally sufficient for

 26-1    identification, of the property being improved;

 26-2                (4)  the date the work actually commenced; and

 26-3                (5)  a general description of the improvement.

 26-4          (d)  An affidavit filed in compliance with this section is

 26-5    prima facie evidence of the date of the commencement of the

 26-6    improvement described in the affidavit.  The time of inception of a

 26-7    mechanic's lien arising from work described in an affidavit of

 26-8    commencement is the date of commencement of the work stated in the

 26-9    affidavit.

26-10              (Sections 62.145-62.170 reserved for expansion

26-11          SUBCHAPTER G.  RELEASE AND FORECLOSURE; ACTION ON CLAIM

26-12          Sec. 62.171.  ENFORCEMENT OF REMEDIES AGAINST MONEY DUE

26-13    ORIGINAL CONTRACTOR OR SUBCONTRACTOR.  (a)  A creditor of an

26-14    original contractor may not collect, enforce a security interest

26-15    against, garnish, or levy execution on the money due the original

26-16    contractor or the contractor's surety from the owner, and a

26-17    creditor of a subcontractor may not collect, enforce a security

26-18    interest against, garnish, or levy execution on the money due the

26-19    subcontractor, to the prejudice of the subcontractors, mechanics,

26-20    laborers, materialmen, or their sureties.

26-21          (b)  A surety issuing a payment bond or performance bond in

26-22    connection with the improvements has a priority claim over other

26-23    creditors of its principal to contract funds to the extent of any

26-24    loss it suffers or incurs.  That priority does not excuse the

26-25    surety from paying any obligations that it may have under its

26-26    payment bonds.

26-27          Sec. 62.172.  RELEASE OF CLAIM OR LIEN.  (a)  When a debt for

 27-1    labor or materials is satisfied or paid by collected funds, the

 27-2    person who furnished the labor or materials shall, not later than

 27-3    the 10th day after the date of receipt of a written request,

 27-4    furnish to the requesting person a release of the indebtedness and

 27-5    any lien claimed, to the extent of the indebtedness paid.  An

 27-6    owner, the original contractor, or any person making the payment

 27-7    may request the release.

 27-8          (b)  A release of lien must be in a form that would permit it

 27-9    to be filed of record.

27-10          Sec. 62.173.  DEFENSE OF ACTIONS.  If a court orders a lien

27-11    against the owner or the owner's property, the owner is entitled to

27-12    deduct the amount of the judgment and costs from any amount due the

27-13    original contractor.  If the owner has settled with the original

27-14    contractor in full, the owner is entitled to recover from the

27-15    original contractor any amount paid for which the original

27-16    contractor was originally liable.

27-17          Sec. 62.174.  FORECLOSURE.  A mechanic's lien may be

27-18    foreclosed only on judgment of a court foreclosing the lien and

27-19    ordering the sale of the property subject to the lien.

27-20          Sec. 62.175.  TRANSFER OF PROPERTY SOLD.  If the house,

27-21    building, or improvement is sold separately, the officer making the

27-22    sale shall place the purchaser in possession.  The purchaser is

27-23    entitled to a reasonable time after the date of purchase within

27-24    which to remove the purchased property.

27-25          Sec. 62.176.  COSTS AND ATTORNEY'S FEES.  In any proceeding

27-26    to foreclose a lien or to enforce a claim against a bond issued

27-27    under Subchapter H or I or in any proceeding to declare that any

 28-1    lien or claim is invalid or unenforceable in whole or in part, the

 28-2    court may award costs and reasonable attorney's fees as are

 28-3    equitable and just.

 28-4          Sec. 62.177.  DISCHARGE OF LIEN.  A mechanic's lien or

 28-5    application for lien filed under Section 62.082 may be discharged

 28-6    of record by:

 28-7                (1)  recording a lien release signed by the claimant

 28-8    under Section 62.172;

 28-9                (2)  failing to institute suit to foreclose the lien in

28-10    the county in which the property is located within the period

28-11    prescribed by Section 62.178, 62.205, or 62.238;

28-12                (3)  recording the original or certified copy of a

28-13    final judgment or decree of a court providing for the discharge;

28-14                (4)  filing the bond, notice, and return in compliance

28-15    with Subchapter H; or

28-16                (5)  filing the bond in compliance with Subchapter I.

28-17          Sec. 62.178.  PERIOD FOR BRINGING SUIT TO FORECLOSE LIEN.

28-18    Suit must be brought to foreclose the lien not later than the 90th

28-19    day after the date the order directing the lien to attach is

28-20    issued.

28-21          Sec. 62.179.  OBLIGATION TO FURNISH INFORMATION.  (a)  An

28-22    owner, on written request, shall furnish the following information

28-23    within a reasonable time, but not later than the 10th day after the

28-24    date the request is received, to any person furnishing labor or

28-25    materials for the project:

28-26                (1)  a description of the real property being improved

28-27    legally sufficient to identify it;

 29-1                (2)  whether there is a surety bond and if so, the name

 29-2    and last known address of the surety and a copy of the bond; and

 29-3                (3)  whether there are any prior recorded liens or

 29-4    security interests on the real property being improved and if so,

 29-5    the name and address of the person having the lien or security

 29-6    interest.

 29-7          (b)  An original contractor, on written request by a person

 29-8    who furnished work under the original contract, shall furnish to

 29-9    the person the following information within a reasonable time, but

29-10    not later than the 10th day after the date the request is received:

29-11                (1)  the name and last known address of the person to

29-12    whom the original contractor furnished labor or materials for the

29-13    construction project; and

29-14                (2)  whether the original contractor has furnished or

29-15    has been furnished a payment bond for any of the work on the

29-16    construction project and if so, the name and last known address of

29-17    the surety and a copy of the bond.

29-18          (c)  A subcontractor, on written request by an owner of the

29-19    property being improved, the original contractor, a surety on a

29-20    bond covering the original contract, or any person furnishing work

29-21    under the subcontract, shall furnish to the person the following

29-22    information within a reasonable time, but not later than the 10th

29-23    day after the date the request is received:

29-24                (1)  the name and last known address of each person

29-25    from whom the subcontractor purchased labor or materials for the

29-26    construction project, other than those materials that were

29-27    furnished to the project from the subcontractor's inventory;

 30-1                (2)  the name and last known address of each person to

 30-2    whom the subcontractor furnished labor or materials for the

 30-3    construction project; and

 30-4                (3)  whether the subcontractor has furnished or has

 30-5    been furnished a payment bond for any of the work on the

 30-6    construction project and if so, the name and last known address of

 30-7    the surety and a copy of the bond.

 30-8          (d)  Not later than the 30th day after the date a written

 30-9    request is received from the owner, the contractor under whom a

30-10    claim of lien or under whom a bond is made, or a surety on a bond

30-11    on which a claim is made, a claimant for a lien or under a bond

30-12    shall furnish to the requesting person a copy of any applicable

30-13    written agreement, purchase order, or contract and any billing,

30-14    statement, or payment request of the claimant reflecting the amount

30-15    claimed and the work performed by the claimant for which the claim

30-16    is made.  If requested, the claimant shall provide the estimated

30-17    amount due for each calendar month in which the claimant has

30-18    performed labor or furnished materials.

30-19          (e)  If a person from whom information is requested does not

30-20    have a direct contractual relationship on the project with the

30-21    person requesting the information, the person from whom information

30-22    is requested, other than a claimant requested to furnish

30-23    information under Subsection (d), may require payment of the actual

30-24    costs, not to exceed $25, in furnishing the requested information.

30-25          (f)  A person, other than a claimant requested to furnish

30-26    information under Subsection (d), who fails to furnish information

30-27    as required by this section is liable to the requesting person for

 31-1    that person's reasonable and necessary costs incurred in procuring

 31-2    the requested information.

 31-3              (Sections 62.180-62.200 reserved for expansion

 31-4               SUBCHAPTER H.  BOND TO INDEMNIFY AGAINST LIEN

 31-5          Sec. 62.201.  BOND.  (a)  If a lien, other than a lien

 31-6    granted by the owner in a written contract, is fixed or is

 31-7    attempted to be fixed by a recorded instrument under this chapter,

 31-8    any person may file a bond to indemnify against the lien.

 31-9          (b)  The bond shall be filed with the county clerk of the

31-10    county in which the property subject to the lien is located.

31-11          Sec. 62.202.  BOND REQUIREMENTS.  The bond must:

31-12                (1)  describe the property on which the liens are

31-13    claimed;

31-14                (2)  refer to each lien claimed in a manner sufficient

31-15    to identify it;

31-16                (3)  be in an amount that is double the amount of the

31-17    liens referred to in the bond unless the total amount claimed in

31-18    the liens exceeds $40,000, in which case the bond must be in an

31-19    amount that is the greater of one and one-half times the amount of

31-20    the liens or the sum of $40,000 and the amount of the liens;

31-21                (4)  be payable to the parties claiming the liens;

31-22                (5)  be executed by:

31-23                      (A)  the party filing the bond as principal; and

31-24                      (B)  a corporate surety authorized and admitted

31-25    to do business under the law in this state and licensed by this

31-26    state to execute the bond as surety; and

31-27                (6)  be conditioned substantially that the principal

 32-1    and sureties will pay to the named obligees or to their assignees

 32-2    the amount that the named obligees would have been entitled to

 32-3    recover if their claims had been proved to be valid and enforceable

 32-4    liens on the property.

 32-5          Sec. 62.203.  NOTICE OF BOND.  (a)  After the bond is filed,

 32-6    the county clerk shall issue notice of the bond to all named

 32-7    obligees.

 32-8          (b)  A copy of the bond must be attached to the notice.

 32-9          (c)  The notice may be served on each obligee by having a

32-10    copy delivered to the obligee by any means authorized for the

32-11    service of an original petition under the Texas Rules of Civil

32-12    Procedure.

32-13          (d)  The original notice shall be returned to the office of

32-14    the county clerk, and the person making service of copies shall

32-15    make an oath on the back of the copies showing on whom and on what

32-16    date the copies were served.

32-17          Sec. 62.204.  RECORDING OF BOND AND NOTICE.  (a)  The county

32-18    clerk shall record the bond, notice, and return in the real

32-19    property records.

32-20          (b)  In acquiring an interest in or insuring title to real

32-21    property, a purchaser, insurer of title, or lender may rely on and

32-22    is absolutely protected by the record of the bond, notice, and

32-23    return to the same extent as if the lien claimant had filed a

32-24    release of lien in the real property records.

32-25          Sec. 62.205.  ACTION ON BOND.  (a)  A party making or holding

32-26    a lien claim may not sue on the bond later than one year after the

32-27    date on which the notice is served or after the date on which the

 33-1    underlying lien claim becomes unenforceable under Section 62.178.

 33-2          (b)  The bond is not exhausted by one action against it.

 33-3    Each named obligee or assignee of an obligee may maintain a

 33-4    separate suit on the bond in any court of jurisdiction.

 33-5              (Sections 62.206-62.230 reserved for expansion

 33-6                SUBCHAPTER I.  BOND TO PAY LIENS OR CLAIMS

 33-7          Sec. 62.231.  BOND.  (a)  An original contractor who has a

 33-8    written contract with the owner may furnish a bond for the benefit

 33-9    of claimants.

33-10          (b)  If a valid bond is filed, a claimant may not file suit

33-11    against the owner or the owner's property and the owner is relieved

33-12    of obligations under Subchapter E.

33-13          Sec. 62.232.  BOND REQUIREMENTS.  The bond must:

33-14                (1)  be in a penal sum at least equal to the total of

33-15    the original contract amount;

33-16                (2)  be in favor of the owner;

33-17                (3)  have the written approval of the owner endorsed on

33-18    it;

33-19                (4)  be executed by:

33-20                      (A)  the original contractor as principal; and

33-21                      (B)  a corporate surety authorized and admitted

33-22    to do business in this state and licensed by this state to execute

33-23    bonds as surety; and

33-24                (5)  be conditioned on prompt payment for all labor,

33-25    subcontracts, materials, specially fabricated materials, and normal

33-26    and usual extras not exceeding 15 percent of the contract price.

33-27          Sec. 62.233.  RECORDING OF BOND AND CONTRACT.  (a)  The bond

 34-1    and the contract between the original contractor and the owner

 34-2    shall be filed with the county clerk of the county in which is

 34-3    located all or part of the owner's property on which the

 34-4    construction or repair is being performed or is to be performed.  A

 34-5    memorandum of the contract or a copy of the contract may be

 34-6    substituted for the original.

 34-7          (b)  The plans, specifications, and general conditions of the

 34-8    contract are not required to be filed.

 34-9          (c)  The county clerk shall record the bond and place the

34-10    contract on file in the clerk's office and shall index and

34-11    cross-index both in the names of the original contractor and the

34-12    owner in records kept for that purpose.

34-13          (d)  On request and payment of a reasonable fee, the county

34-14    clerk shall furnish a copy of the bond and contract to any person.

34-15          (e)  In any court of this state or in the United States, a

34-16    copy of the bond and contract certified by the county clerk

34-17    constitutes prima facie evidence of the contents, execution,

34-18    delivery, and filing of the originals.

34-19          Sec. 62.234.  RELIANCE ON RECORD.  A purchaser, lender, or

34-20    other person acquiring an interest in the owner's property or an

34-21    insurer of title is entitled to rely on the record of the bond and

34-22    contract as constituting payment of all claims and liens for labor,

34-23    subcontracts, materials, or specially fabricated materials incurred

34-24    by the original contractor as if the purchaser, lender, or other

34-25    person acquiring an interest in the owner's property or an insurer

34-26    of title were the owner who approved, accepted, and endorsed the

34-27    bond and as if each person furnishing labor or materials for the

 35-1    work performed under the original contract, other than the original

 35-2    contractor, had filed a complete release and relinquishment of lien

 35-3    of record.

 35-4          Sec. 62.235.  ENFORCEABLE CLAIMS.  (a)  The bond protects all

 35-5    persons with a claim that is:

 35-6                (1)  perfected in the manner prescribed for fixing a

 35-7    lien under Subchapter D; or

 35-8                (2)  perfected in the manner prescribed by Section

 35-9    62.236.

35-10          (b)  A claim or the rights to a claim under the bond may be

35-11    assigned.

35-12          Sec. 62.236.  PERFECTION OF CLAIM.  (a)  To perfect a claim

35-13    against a bond in a manner other than that prescribed by Subchapter

35-14    D for fixing a lien, a person must provide written notice to the

35-15    original contractor and the surety not later than the 15th day

35-16    after the date the person submits a written request under Section

35-17    28.002.

35-18          (b)  The notice must be sent by registered or certified mail

35-19    and must be addressed to the original contractor or surety, as

35-20    applicable, at the last known business or residence address.

35-21          (c)  A copy of the statement or billing in the usual and

35-22    customary form is sufficient as notice under this section.

35-23          Sec. 62.237.  OWNER'S NOTICE OF CLAIM TO SURETY.  (a)  If the

35-24    owner receives a notice under Section 62.086 or a lien is fixed

35-25    under Subchapter D, the owner shall mail to the surety on the bond

35-26    a copy of all notices received.

35-27          (b)  Failure of the owner to send copies of notices to the

 36-1    surety does not relieve the surety of any liability under the bond

 36-2    if the claimant has complied with the requirements of this

 36-3    subchapter, nor does that failure impose any liability on the

 36-4    owner.

 36-5          Sec. 62.238.  ACTION ON BOND.  (a)  A claimant may sue the

 36-6    principal and surety on the bond either jointly or severally, if

 36-7    his claim remains unpaid for 60 days after the claimant perfects

 36-8    the claim.

 36-9          (b)  The claimant may sue for the amount of the claim and

36-10    court costs.

36-11          (c)  The suit must be brought in the county in which the

36-12    property being improved is located.

36-13          (d)  If the bond is recorded at the time the lien is filed,

36-14    the claimant must sue on the bond within one year following

36-15    perfection of his claim.  If the bond is not recorded at the time

36-16    the lien is filed, the claimant must sue on the bond within two

36-17    years following perfection of his claim.

36-18          Sec. 62.239.  CLAIMS IN EXCESS OF BOND AMOUNT.  If valid

36-19    claims against the bond exceed the penal sum of the bond, each

36-20    claimant is entitled to a pro rata share of the penal sum.

36-21          Sec. 62.240.  ATTEMPTED COMPLIANCE.  (a)  A bond shall be

36-22    construed to comply with this subchapter, and the rights and

36-23    remedies on the bond are enforceable in the same manner as on other

36-24    bonds under this subchapter, if the bond:

36-25                (1)  is furnished and filed in attempted compliance

36-26    with this subchapter; or

36-27                (2)  evidences by its terms intent to comply with this

 37-1    subchapter.

 37-2          (b)  Any provision in any payment bond furnished or filed in

 37-3    attempted compliance with this subchapter that expands or restricts

 37-4    the rights or liabilities provided under this chapter shall be

 37-5    disregarded, and the provisions of this subchapter shall be read

 37-6    into that bond.

 37-7          SECTION 15.  Section 162.001, Property Code, is amended by

 37-8    adding Subsection (c) to read as follows:

 37-9          (c)  If a contractor and property owner have entered into a

37-10    written construction contract for the improvement of specific real

37-11    property in this state before the commencement of construction of

37-12    the improvement and the contract provides for the payment by the

37-13    owner of the costs of construction and a reasonable fee specified

37-14    in the contract payable to the contractor, the fee paid to the

37-15    contractor is not considered trust funds.

37-16          SECTION 16.  Section 162.003, Property Code, is amended to

37-17    read as follows:

37-18          Sec. 162.003.  BENEFICIARIES OF TRUST FUNDS.  An artisan

37-19    [artist], laborer, mechanic, contractor, subcontractor, or

37-20    materialman who labors or who furnishes labor or material for the

37-21    construction or repair of an improvement on specific real property

37-22    in this state is a beneficiary of any trust funds paid or received

37-23    in connection with the improvement.

37-24          SECTION 17.  Section 162.005, Property Code, is amended to

37-25    read as follows:

37-26          Sec. 162.005.  DEFINITIONS.  In this chapter:

37-27                (1)  A trustee acts with "intent to defraud" when the

 38-1    trustee:

 38-2                      (A)  [he] retains, uses, disburses, or diverts

 38-3    trust funds with the intent to deprive the beneficiaries of the

 38-4    trust funds;

 38-5                      (B)  retains, uses, disburses, or diverts trust

 38-6    funds and fails to establish or maintain a construction account as

 38-7    required by Section 162.006 or fails to establish or maintain an

 38-8    account record for the construction account as required by Section

 38-9    162.007; or

38-10                      (C)  uses, disburses, or diverts trust funds that

38-11    were paid to the trustee in reliance on an affidavit furnished by

38-12    the trustee under Section 53.085 or 62.024 if the affidavit

38-13    contains false information relating to the trustee's payment of

38-14    current or past due obligations.

38-15                (2)  "Current or past due obligations" are those

38-16    obligations incurred or owed by the trustee for labor or materials

38-17    furnished in the direct prosecution of the work under the

38-18    construction contract prior to the receipt of the trust funds and

38-19    which are due and payable by the trustee no later than 30 days

38-20    following receipt of the trust funds.

38-21                (3)  "Direct cost" means a cost included under a

38-22    construction contract that is specific to the construction of the

38-23    improvement that is the subject of the contract.

38-24                (4)  "Indirect cost" means a cost included under a

38-25    construction contract that is not specific to the construction of

38-26    the improvement that is the subject of the contract.

38-27                (5)  "Financial institution" means a bank, trust

 39-1    company, insurance company, credit union, savings and loan

 39-2    association, investment trust, investment company, or any other

 39-3    organization held out to the public as a place for deposit of funds

 39-4    or medium of savings or collective investment.

 39-5                (6)  "Construction account" means an account in a

 39-6    financial institution into which only trust funds and funds

 39-7    deposited by the contractor that are necessary to pay charges

 39-8    imposed on the account by the financial institution may be

 39-9    maintained.

39-10          SECTION 18.  Subchapter A, Chapter 162, Property Code, is

39-11    amended by adding Sections 162.006 and 162.007 to read as follows:

39-12          Sec. 162.006.  CONSTRUCTION ACCOUNT REQUIRED IN CERTAIN

39-13    CIRCUMSTANCES.  (a)  A contractor who agrees with a property owner

39-14    to construct improvements to a residential homestead for an amount

39-15    exceeding $5,000 shall deposit the trust funds received from the

39-16    owner in a construction account in a financial institution.

39-17          (b)  The periodic statement received from the financial

39-18    institution must refer to the account as a "construction account"

39-19    to satisfy the requirements of this section.

39-20          Sec. 162.007.  MANAGEMENT OF CONSTRUCTION ACCOUNTS.  (a)  A

39-21    contractor required to maintain a construction account under this

39-22    subchapter shall maintain an account record for the construction

39-23    account that provides information relating to:

39-24                (1)  the source and amount of the funds in the account

39-25    and the date the funds were deposited;

39-26                (2)  the date and amount of each disbursement from the

39-27    account and the person to whom the funds were disbursed; and

 40-1                (3)  the current balance of the account.

 40-2          (b)  The contractor shall maintain an account record for each

 40-3    construction project that specifies the direct costs and indirect

 40-4    costs charged to the owner.

 40-5          (c)  The contractor shall retain all invoices and other

 40-6    supporting documentation received relating to funds that were

 40-7    disbursed from the construction account.

 40-8          (d)  The contractor shall ensure that all deposit and

 40-9    disbursement documentation includes the construction account number

40-10    or information that provides a direct connection between the

40-11    documentation and the account.

40-12          (e)  The contractor may not destroy information required to

40-13    be maintained under this section before the first anniversary of

40-14    the date the improvement that is the subject of the contract is

40-15    completed.

40-16          SECTION 19.  Section 162.032, Property Code, is amended by

40-17    adding Subsection (c) to read as follows:

40-18          (c)  A trustee who fails to establish or maintain a

40-19    construction account in violation of Section 162.006 or fails to

40-20    establish or maintain an account record for the construction

40-21    account in violation of Section 162.007 commits a Class A

40-22    misdemeanor.

40-23          SECTION 20.  Section 53.059, Property Code, is repealed.

40-24          SECTION 21.  (a)  This Act takes effect September 1, 1997.

40-25          (b)  The changes in law made by this Act apply only to a

40-26    construction contract entered into on or after September 1, 1997,

40-27    and funds received under a construction contract entered into on or

 41-1    after September 1, 1997.  A construction contract entered into

 41-2    before September 1, 1997, or funds received under a construction

 41-3    contract entered into before September 1, 1997, are governed by the

 41-4    law as it existed immediately before September 1, 1997, and that

 41-5    law is continued in effect for this purpose.

 41-6          SECTION 22.  The importance of this legislation and the

 41-7    crowded condition of the calendars in both houses create an

 41-8    emergency and an imperative public necessity that the

 41-9    constitutional rule requiring bills to be read on three several

41-10    days in each house be suspended, and this rule is hereby suspended.