SRC-ARR S.B. 1593 76(R)BILL ANALYSIS


Senate Research CenterS.B. 1593
By: Brown
Natural Resources
6/30/1999
Enrolled


DIGEST 

Currently, Texas does not provide for a water supply reservoir project at a
site known as the Allens Creek Reservoir site in Austin County, Texas. S.B.
1593 will create a water supply reservoir project at a site known as the
Allens Creek Reservoir site in Austin County, Texas and provide for the
issuance of certain water rights permits to the Texas Water Development
Board. 

PURPOSE

As enrolled, S.B. 1593 creates a water supply reservoir project at a site
known as the Allens Creek Reservoir site in Austin County, Texas and
provides for the issuance of certain water rights permits to the Texas
Water Development Board. 

RULEMAKING AUTHORITY

This bill does not grant any additional rulemaking authority to a state
officer, institution, or agency. 

SECTION BY SECTION ANALYSIS

ARTICLE 1. 

SECTION 1.01 Sets forth site requirements for a dam and reservoir to be
constructed at the confluence of Allens Creek and the Brazos River. Sets
forth the findings of the legislature.  

SECTION 1.02. Sets forth requirements for the Texas water Development Board
(board) to construct a dam and reservoir on Allen Creek and the issuance of
permits.  

SECTION 1.03. Authorizes the board to acquire the entire or any undivided
interest in the Allens Creek site, provided that the total amount of money
invested by the board in the site shall not exceed $20,000,000 with
$1,800,000 of such investment to be for reimbursement to the Brazos River
Authority for costs incurred to obtain and hold its it option to acquire
such site, using the state participation account of the Texas Water
Development Fund II to encourage regional development of the Allens Creek
Reservoir project.  

SECTION 1.04. Authorizes the board to issue certain bonds. Sets forth
certain legislative findings.  

SECTION 1.05. Requires any contract providing for state participation in
the Allens Creek site or the construction of a reservoir at such site to
provide for the purchase of the board's interest in the facility pursuant
to the provisions of Section 16.186(b), Water Code. Authorizes the board to
contract for such a sale with a municipality, a river authority, a
political subdivision, or a water supply corporation organized under
Chapter 67 of the Water Code. 

ARTICLE 2.

SECTION 2.01. Amends Chapter 11, Water Code, by adding Section 11.1311, as
follows: 

Sec. 11.1311. APPROVAL OF CERTAIN APPLICATIONS WITHOUT HEARING. Authorizes
the Texas Natural Resource Conservation Commission to reissue the same
permit with a new priority date to the board without notice or hearing,
upon submission of an  application by the board, if a permit for a
reservoir project which is listed on the effective date of this Act as a
recommended project in the current state water plan has been abandoned,
voluntarily canceled, or forfeited for failure to commence construction
within the time specified by law.  Authorizes the board to transfer
interest in a permit issued under this section to certain entities.
Requires a permit issued pursuant to this section to be administered in
accordance with this chapter and as otherwise provided by law. 

ARTICLE 3.

SECTION 3.01. Provides that nothing in this Act shall be construed as
prohibiting or impairing any lawful use, sale, or other curtailment or
diminution of waters that contribute to the flows of the Brazos River at
the proposed point of diversion for the Allens Creek Reservoir project,
including certain actions, whether due to use or sale of such groundwater
or any other reason. 

SECTION 3.02. Effective date: September 1, 1999.

SECTION 3.03. Emergency clause.