76R9835 PAM-F                           
         By Solomons                                           H.B. No. 2054
         Substitute the following for H.B. No. 2054:
         By Solomons                                       C.S.H.B. No. 2054
                                A BILL TO BE ENTITLED
 1-1                                   AN ACT
 1-2     relating to mechanic's, contractor's, and materialmen's liens.
 1-3           BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 1-4           SECTION 1.  Section 53.001, Property Code, is amended by
 1-5     adding Subsection (15) to read as follows:
 1-6                 (15)  "Completion" of an original contract means the
 1-7     actual completion of the work, including any extras or change
 1-8     orders reasonably required or contemplated under the original
 1-9     contract, other than warranty work or replacement or repair of the
1-10     work performed under the contract.
1-11           SECTION 2.  Section 53.055(a), Property Code, is amended to
1-12     read as follows:
1-13           (a)  A person who files an affidavit must send a copy of the
1-14     affidavit by registered or certified mail to the owner or reputed
1-15     owner at the owner's last known business or residence address not
1-16     later than the fifth [one business] day after the date the
1-17     affidavit is filed with the county clerk.
1-18           SECTION 3.  Sections 53.057(a) and (e), Property Code, are
1-19     amended to read as follows:
1-20           (a)  A [Except as provided by Subchapter K, a] claimant may
1-21     give notice under this section instead of or in addition to notice
1-22     under Section 53.056 or 53.252 if the claimant is to labor, furnish
1-23     labor or materials, or specially fabricate materials under an
1-24     agreement with an original contractor or a subcontractor providing
 2-1     for retainage.
 2-2           (e)  If a [A] claimant [who] gives notice under this section
 2-3     and Section 53.055 or, if the claim relates to a residential
 2-4     construction  project, under this section and Section 53.252, the
 2-5     claimant is not required to give any other notice as to the
 2-6     retainage.
 2-7           SECTION 4.  Section 53.158, Property Code, is amended to read
 2-8     as follows:
 2-9           Sec. 53.158.  PERIOD FOR BRINGING SUIT TO FORECLOSE LIEN.
2-10     (a)  Except as provided by Subsection (b), suit must be brought to
2-11     foreclose the lien within two years after the last day a claimant
2-12     may file [date of filing] the lien affidavit under Section 53.052
2-13     or within one year after completion, termination, or abandonment of
2-14     the work under the original contract under which the lien is
2-15     claimed, whichever is later.
2-16           (b)  For a claim arising from a residential construction
2-17     project, suit must be brought to foreclose the lien within one year
2-18     after the last day a claimant may file a lien affidavit  [not later
2-19     than the first anniversary of the date the lien affidavit is filed]
2-20     under Section 53.052 or within one year after completion,
2-21     termination, or abandonment of the work under the original contract
2-22     under which the lien is claimed, whichever is later.
2-23           SECTION 5.  Section 53.205(a), Property Code, is amended to
2-24     read as follows:
2-25           (a)  The bond protects all persons with a claim that is:
2-26                 (1)  perfected in the manner prescribed for fixing a
2-27     lien under Subchapter C or, if the claim relates to a residential
 3-1     construction project, under Subchapter K; or
 3-2                 (2)  perfected in the manner prescribed by Section
 3-3     53.206.
 3-4           SECTION 6.  Sections 53.206(a) and (b), Property Code, are
 3-5     amended to read as follows:
 3-6           (a)  To perfect a claim against a bond in a manner other than
 3-7     that prescribed by Subchapter C or K for fixing a lien, a person
 3-8     must:
 3-9                 (1)  give to the original contractor all applicable
3-10     notices under the appropriate [that] subchapter; and
3-11                 (2)  give to the surety on the bond, instead of the
3-12     owner, all notices under the appropriate [that] subchapter required
3-13     to be given to the owner.
3-14           (b)  To perfect a claim under this section, a person is not
3-15     required to:
3-16                 (1)  give notice to the surety under Section 53.057,
3-17     unless the claimant has a direct contractual relationship with the
3-18     original contractor and the agreed retainage is in excess of 10
3-19     percent of the contract;
3-20                 (2)  give notice to the surety under [Subsection (b)
3-21     of] Section 53.058(b) or, if the claim relates to a residential
3-22     construction project, under Section 53.253(c) [53.058]; or
3-23                 (3)  file any affidavit with the county clerk.
3-24           SECTION 7.  Section 53.207(a), Property Code, is amended to
3-25     read as follows:
3-26           (a)  If the owner receives any of the notices or a lien is
3-27     fixed under Subchapter C or K, the owner shall mail to the surety
 4-1     on the bond a copy of all notices received.
 4-2           SECTION 8.  Section 53.255(b), Property Code, is amended to
 4-3     read as follows:
 4-4           (b)  The disclosure statement must read substantially similar
 4-5     to the following:
 4-6           "KNOW YOUR RIGHTS AND RESPONSIBILITIES UNDER THE LAW.  You
 4-7     are about to enter into a transaction to build a new home or
 4-8     remodel existing residential property.  Texas law requires your
 4-9     contractor to provide you with this brief overview of some of your
4-10     rights, responsibilities, and risks in this transaction.
4-11           "CONVEYANCE TO CONTRACTOR NOT REQUIRED [PROHIBITED]. Your
4-12     contractor may not require you to convey your real property to your
4-13     contractor as a condition to the agreement for the construction of
4-14     improvements on your property.
4-15           "KNOW YOUR CONTRACTOR.  Before you enter into your agreement
4-16     for the construction of improvements to your real property, make
4-17     sure that you have investigated your contractor.  Obtain and verify
4-18     references from other people who have used the contractor for the
4-19     type and size of construction project on your property.
4-20           "GET IT IN WRITING.  Make sure that you have a written
4-21     agreement with your contractor that includes:  (1) a description of
4-22     the work the contractor is to perform;  (2) the required or
4-23     estimated time for completion of the work;  (3) the cost of the
4-24     work or how the cost will be determined; and (4) the procedure and
4-25     method of payment, including provisions for statutory retainage and
4-26     conditions for final payment.  If your contractor made a promise,
4-27     warranty, or representation to you concerning the work the
 5-1     contractor is to perform, make sure that promise, warranty, or
 5-2     representation is specified in the written agreement.  An oral
 5-3     promise that is not included in the written agreement may not be
 5-4     enforceable under Texas law.
 5-5           "READ BEFORE YOU SIGN.  Do not sign any document before you
 5-6     have read and understood it.  NEVER SIGN A DOCUMENT THAT INCLUDES
 5-7     AN UNTRUE STATEMENT.  Take your time in reviewing documents.  If
 5-8     you borrow money from a lender to pay for the improvements, you are
 5-9     entitled to have the loan closing documents furnished to you for
5-10     review at least one business day before the closing.  Do not waive
5-11     this requirement unless a bona fide emergency or another good cause
5-12     exists, and make sure you understand the documents before you sign
5-13     them.  If you fail to comply with the terms of the documents, you
5-14     could lose your property.  You are entitled to have your own
5-15     attorney review any documents.  If you have any question about the
5-16     meaning of a document, consult an attorney.
5-17           "GET A LIST OF SUBCONTRACTORS AND SUPPLIERS. Before
5-18     construction commences, your contractor is required to provide you
5-19     with a list of the subcontractors and suppliers the contractor
5-20     intends to use on your project.  Your contractor is required to
5-21     supply updated information on any subcontractors and suppliers
5-22     added after the list is provided.  Your contractor is not required
5-23     to supply this information if you sign a written waiver of your
5-24     rights to receive this information.
5-25           "MONITOR THE WORK.  Lenders and governmental authorities may
5-26     inspect the work in progress from time to time for their own
5-27     purposes.  These inspections are not intended as quality control
 6-1     inspections.  Quality control is a matter for you and your
 6-2     contractor.  To ensure that your home is being constructed in
 6-3     accordance with your wishes and specifications, you should inspect
 6-4     the work yourself or have your own independent inspector review the
 6-5     work in progress.
 6-6           "MONITOR PAYMENTS.  If you use a lender, your lender is
 6-7     required to provide you with a periodic statement showing the money
 6-8     disbursed by the lender from the proceeds of your loan.  Each time
 6-9     your contractor requests payment from you or your lender for work
6-10     performed, your [Your] contractor is also required to furnish you
6-11     with a disbursement statement that lists the name and address of
6-12     each subcontractor or supplier that the contractor intends to pay
6-13     from the requested funds [at least once each month of money
6-14     disbursed to subcontractors and suppliers for this project].
6-15     Review these statements and make sure that the money is being
6-16     properly disbursed.
6-17           "CLAIMS BY SUBCONTRACTORS AND SUPPLIERS.  Under Texas law, if
6-18     a subcontractor or supplier who furnishes labor or materials for
6-19     the construction of improvements on your property is not paid, you
6-20     may become liable and your property may be subject to a lien for
6-21     the unpaid amount, even if you have not contracted directly with
6-22     the subcontractor or supplier.  To avoid liability, you should take
6-23     the following actions:
6-24                       (1)  If you receive a written notice from a
6-25           subcontractor or supplier, you should withhold payment from
6-26           your contractor for the amount of the claim stated in the
6-27           notice until the dispute between your contractor and the
 7-1           subcontractor or supplier is resolved.  If your lender is
 7-2           disbursing money directly to your contractor, you should
 7-3           immediately provide a copy of the notice to your lender and
 7-4           instruct the lender to withhold payment in the amount of the
 7-5           claim stated in the notice.  If you continue to pay the
 7-6           contractor after receiving the written notice without
 7-7           withholding the amount of the claim, you may be liable and
 7-8           your property may be subject to a lien for the amount you
 7-9           failed to withhold.
7-10                       (2)  During construction and for 30 days after
7-11           final completion, termination, or abandonment of the contract
7-12           by the contractor, you should withhold or cause your lender
7-13           to withhold 10 percent of the amount of payments made for the
7-14           work performed by your contractor.  This is sometimes
7-15           referred to as 'statutory retainage.'  If you choose not
7-16           [fail] to withhold the 10 percent for at least 30 days after
7-17           final completion, termination, or abandonment of the contract
7-18           by the contractor and if a valid claim is timely made by a
7-19           claimant and your contractor fails to pay the claim, you may
7-20           be personally liable and your property may be subject to a
7-21           lien up to the amount that you failed to withhold.
7-22           "If a claim is not paid within a certain time period, the
7-23     claimant is required to file a mechanic's lien affidavit in the
7-24     real property records in the county where the property is located.
7-25     A mechanic's lien affidavit is not a lien on your property, but the
7-26     filing of the affidavit could result in a court imposing a lien on
7-27     your property if the claimant is successful in litigation to
 8-1     enforce the lien claim.
 8-2           "SOME CLAIMS MAY NOT BE VALID. When you receive a written
 8-3     notice of a claim or when a mechanic's lien affidavit is filed on
 8-4     your property, you should know your legal rights and
 8-5     responsibilities regarding the claim.  Not all claims are valid.  A
 8-6     notice of a claim by a subcontractor or supplier is required to be
 8-7     sent, and the mechanic's lien affidavit is required to be filed,
 8-8     within strict time periods.  The notice and the affidavit must
 8-9     contain certain information.  All claimants may not fully comply
8-10     with the legal requirements to collect on a claim.  If you have
8-11     paid the contractor in full before receiving a notice of a claim
8-12     and have fully complied with the law regarding statutory retainage,
8-13     you may not be liable for that claim.    Accordingly, you should
8-14     consult your attorney when you receive a written notice of a claim
8-15     to determine the true extent of your liability or potential
8-16     liability for that claim.
8-17           "OBTAIN A LIEN RELEASE AND A BILLS-PAID AFFIDAVIT. When you
8-18     receive a notice of claim, do not release withheld funds without
8-19     obtaining a signed and notarized release of lien and claim from the
8-20     claimant.  You can also reduce the risk of having a claim filed by
8-21     a subcontractor or supplier by requiring as a condition of each
8-22     payment made by you or your lender that your contractor furnish you
8-23     with an affidavit stating that all bills have been paid.  Under
8-24     Texas law, on final completion of the work and before final
8-25     payment, the contractor is required to furnish you with an
8-26     affidavit stating that all bills have been paid.  If the contractor
8-27     discloses any unpaid bill in the affidavit, you should withhold
 9-1     payment in the amount of the unpaid bill until you receive a waiver
 9-2     of lien or release from that subcontractor or supplier.
 9-3           "OBTAIN TITLE INSURANCE PROTECTION. You may be able to obtain
 9-4     a title insurance policy to insure that the title to your property
 9-5     and the existing improvements on your property are free from liens
 9-6     claimed by subcontractors and suppliers.  If your policy is issued
 9-7     before the improvements are completed and covers the value of the
 9-8     improvements to be completed, you should obtain, on the completion
 9-9     of the improvements and as a condition of your final payment, a
9-10     'completion of improvements' policy endorsement.  This endorsement
9-11     will protect your property from liens claimed by subcontractors and
9-12     suppliers that may arise from the date the original title policy is
9-13     issued to the date of the endorsement."
9-14           SECTION 9.  Section 53.256, Property Code, is amended by
9-15     amending Subsections (a)  and (b) and adding Subsection (d) to read
9-16     as follows:
9-17           (a)  Except as provided by Subsection (d), for [For] the
9-18     construction of improvements under a residential construction
9-19     contract, the original contractor shall:
9-20                 (1)  [must attach to the disclosure statement required
9-21     by Section 53.255 or] furnish to the owner before the commencement
9-22     of construction a written list that identifies by name, address,
9-23     and telephone number each subcontractor and supplier the contractor
9-24     intends to use in the work to be performed; and
9-25                 (2)  [.  The contractor shall] provide the owner with
9-26     an updated list of subcontractors and suppliers not later than the
9-27     15th day after the date a subcontractor or supplier is added or
 10-1    deleted.
 10-2          (b)  The list must contain the following notice conspicuously
 10-3    printed, stamped, or typed in a size equal to at least 10-point
 10-4    boldface or the computer equivalent:
 10-5          "NOTICE:  THIS LIST OF SUBCONTRACTORS AND SUPPLIERS MAY NOT
 10-6    BE A FINAL LISTING. UNLESS YOU SIGN A WAIVER OF YOUR RIGHT TO
 10-7    RECEIVE UPDATED INFORMATION, THE CONTRACTOR IS REQUIRED BY LAW TO
 10-8    SUPPLY UPDATED INFORMATION, AS THE INFORMATION BECOMES AVAILABLE,
 10-9    FOR EACH SUBCONTRACTOR OR SUPPLIER USED IN THE WORK PERFORMED ON
10-10    YOUR RESIDENCE."
10-11          (d)  An owner may waive the right to receive the list of
10-12    subcontractors and suppliers or any updated information required by
10-13    this section only as provided by this subsection.  The waiver must
10-14    be in writing and may be included in the residential construction
10-15    contract.  If the waiver is not included as a provision of the
10-16    residential construction contract, the separate waiver statement
10-17    must be signed by the owner.  The waiver must be conspicuously
10-18    printed in at least 10-point bold-faced type and read substantially
10-19    similar to the following:
10-20          "WAIVER OF THE LIST OF SUBCONTRACTORS AND SUPPLIERS.  AN
10-21    OWNER IS NOT REQUIRED TO WAIVE THE RIGHT GRANTED BY SECTION 53.256,
10-22    PROPERTY CODE, TO RECEIVE FROM THE CONTRACTOR AN ORIGINAL OR
10-23    UPDATED LIST OF SUBCONTRACTORS AND SUPPLIERS.
10-24          "BY SIGNING THIS DOCUMENT, I AGREE TO WAIVE MY RIGHT TO
10-25    RECEIVE FROM THE CONTRACTOR AN ORIGINAL OR UPDATED LIST OF
10-26    SUBCONTRACTORS AND SUPPLIERS.
10-27          "I UNDERSTAND AND ACKNOWLEDGE THAT, AFTER SIGNING THIS
 11-1    DOCUMENT, THIS WAIVER MAY NOT BE CANCELED AT A LATER DATE.
 11-2          "I HAVE VOLUNTARILY CONSENTED TO THIS WAIVER."
 11-3          SECTION 10.  Sections 53.258(a), (b), and (e), Property Code,
 11-4    are amended to read as follows:
 11-5          (a)  At the time the original contractor requests payment
 11-6    from the owner or the owner's lender for the construction of
 11-7    improvements under a residential construction contract, the
 11-8    original contractor shall provide to the owner a disbursement
 11-9    statement.  The statement may include any information agreed to by
11-10    the owner and the original contractor and must include at least the
11-11    name and address of each person who subcontracted directly with the
11-12    original contractor and who the original contractor intends to pay
11-13    from the requested funds.  The original contractor shall provide
11-14    the disbursement statement:
11-15                (1)  in the manner agreed to in writing by the owner
11-16    and original contractor; or
11-17                (2)  if no agreement exists, by depositing the
11-18    statement in the United States mail, first class, postage paid, and
11-19    properly addressed to the owner or by hand delivering the statement
11-20    to the owner before the original contractor receives the requested
11-21    funds [For the construction of improvements under a residential
11-22    construction contract, the original contractor shall provide to the
11-23    owner a signed periodic statement that lists the bills or expenses
11-24    that the original contractor represents will be paid or that have
11-25    been paid and for which the original contractor is requesting
11-26    payment.  The original contractor is not required to include in the
11-27    statement the bills or expenses for which the original contractor
 12-1    has obtained a valid lien release or waiver from the subcontractor
 12-2    or supplier to whom the bills or expenses are owed if the statement
 12-3    includes a written representation that the balance of any funds
 12-4    that are not itemized in the statement will be paid to:]
 12-5                [(1)  the subcontractor or supplier who provided the
 12-6    lien release or waiver; or]
 12-7                [(2)  the original contractor as reimbursement for
 12-8    expenses incurred, profit, or overhead].
 12-9          (b)  If the owner finances the construction of improvements
12-10    through a third party that advances loan proceeds directly to the
12-11    original contractor, the lender shall:
12-12                (1)  obtain from the original contractor the signed
12-13    disbursement [periodic] statement required by Subsection (a) that
12-14    covers the funds for which the original contractor is requesting
12-15    payment; and
12-16                (2)  provide to the owner a statement of funds
12-17    disbursed by the lender since the last statement was provided to
12-18    the owner.
12-19          (e)  The failure of a lender or an original contractor to
12-20    comply with this section does not invalidate a lien under this
12-21    chapter, a contract lien, or a deed of trust.
12-22          SECTION 11.  Section 53.260, Property Code, is amended to
12-23    read as follows:
12-24          Sec. 53.260.  CONVEYANCE TO CONTRACTOR NOT REQUIRED
12-25    [PROHIBITED].  An original contractor may not require an owner of
12-26    real property to convey the real property to the original
12-27    contractor or an entity controlled by the original contractor as a
 13-1    condition to the performance of the residential construction
 13-2    contract for improvements to the real property.
 13-3          SECTION 12.  Section 53.106(e), Property Code, is repealed.
 13-4          SECTION 13.  (a)  This Act takes effect September 1, 1999.
 13-5          (b)  The changes in law made by this Act apply only to
 13-6    matters relating to or claims arising under an original contract,
 13-7    as that term is defined by Section 53.001, Property Code, that is
 13-8    entered into on or after September 1, 1999.  Matters relating to or
 13-9    claims arising from an original contract, as that term is defined
13-10    by Section 53.001, Property Code, that was entered into before
13-11    September 1, 1999, are governed by the law in effect when the
13-12    contract was entered into, and the former law is continued in
13-13    effect for that purpose.
13-14          SECTION 14.  The importance of this legislation and the
13-15    crowded condition of the calendars in both houses create an
13-16    emergency and an imperative public necessity that the
13-17    constitutional rule requiring bills to be read on three several
13-18    days in each house be suspended, and this rule is hereby suspended.