1-1     By:  Solomons (Senate Sponsor - Shapleigh)            H.B. No. 2054
 1-2           (In the Senate - Received from the House April 29, 1999;
 1-3     April 30, 1999, read first time and referred to Committee on
 1-4     Economic Development; May 13, 1999, reported favorably by the
 1-5     following vote:  Yeas 7, Nays 0; May 13, 1999, sent to printer.)
 1-6                            A BILL TO BE ENTITLED
 1-7                                   AN ACT
 1-8     relating to mechanic's, contractor's, and materialmen's liens.
 1-9           BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
1-10           SECTION 1.  Section 53.001, Property Code, is amended by
1-11     adding Subsection (15) to read as follows:
1-12                 (15)  "Completion" of an original contract means the
1-13     actual completion of the work, including any extras or change
1-14     orders reasonably required or contemplated under the original
1-15     contract, other than warranty work or replacement or repair of the
1-16     work performed under the contract.
1-17           SECTION 2.  Section 53.055(a), Property Code, is amended to
1-18     read as follows:
1-19           (a)  A person who files an affidavit must send a copy of the
1-20     affidavit by registered or certified mail to the owner or reputed
1-21     owner at the owner's last known business or residence address not
1-22     later than the fifth [one business] day after the date the
1-23     affidavit is filed with the county clerk.
1-24           SECTION 3.  Sections 53.057(a) and (e), Property Code, are
1-25     amended to read as follows:
1-26           (a)  A [Except as provided by Subchapter K, a] claimant may
1-27     give notice under this section instead of or in addition to notice
1-28     under Section 53.056 or 53.252 if the claimant is to labor, furnish
1-29     labor or materials, or specially fabricate materials under an
1-30     agreement with an original contractor or a subcontractor providing
1-31     for retainage.
1-32           (e)  If a [A] claimant [who] gives notice under this section
1-33     and Section 53.055 or, if the claim relates to a residential
1-34     construction  project, under this section and Section 53.252, the
1-35     claimant is not required to give any other notice as to the
1-36     retainage.
1-37           SECTION 4.  Section 53.158, Property Code, is amended to read
1-38     as follows:
1-39           Sec. 53.158.  PERIOD FOR BRINGING SUIT TO FORECLOSE LIEN.
1-40     (a)  Except as provided by Subsection (b), suit must be brought to
1-41     foreclose the lien within two years after the last day a claimant
1-42     may file [date of filing] the lien affidavit under Section 53.052
1-43     or within one year after completion, termination, or abandonment of
1-44     the work under the original contract under which the lien is
1-45     claimed, whichever is later.
1-46           (b)  For a claim arising from a residential construction
1-47     project, suit must be brought to foreclose the lien within one year
1-48     after the last day a claimant may file a lien affidavit  [not later
1-49     than the first anniversary of the date the lien affidavit is filed]
1-50     under Section 53.052 or within one year after completion,
1-51     termination, or abandonment of the work under the original contract
1-52     under which the lien is claimed, whichever is later.
1-53           SECTION 5.  Section 53.205(a), Property Code, is amended to
1-54     read as follows:
1-55           (a)  The bond protects all persons with a claim that is:
1-56                 (1)  perfected in the manner prescribed for fixing a
1-57     lien under Subchapter C or, if the claim relates to a residential
1-58     construction project, under Subchapter K; or
1-59                 (2)  perfected in the manner prescribed by Section
1-60     53.206.
1-61           SECTION 6.  Sections 53.206(a) and (b), Property Code, are
1-62     amended to read as follows:
1-63           (a)  To perfect a claim against a bond in a manner other than
1-64     that prescribed by Subchapter C or K for fixing a lien, a person
 2-1     must:
 2-2                 (1)  give to the original contractor all applicable
 2-3     notices under the appropriate [that] subchapter; and
 2-4                 (2)  give to the surety on the bond, instead of the
 2-5     owner, all notices under the appropriate [that] subchapter required
 2-6     to be given to the owner.
 2-7           (b)  To perfect a claim under this section, a person is not
 2-8     required to:
 2-9                 (1)  give notice to the surety under Section 53.057,
2-10     unless the claimant has a direct contractual relationship with the
2-11     original contractor and the agreed retainage is in excess of 10
2-12     percent of the contract;
2-13                 (2)  give notice to the surety under [Subsection (b)
2-14     of] Section 53.058(b) or, if the claim relates to a residential
2-15     construction project, under Section 53.253(c) [53.058]; or
2-16                 (3)  file any affidavit with the county clerk.
2-17           SECTION 7.  Section 53.207(a), Property Code, is amended to
2-18     read as follows:
2-19           (a)  If the owner receives any of the notices or a lien is
2-20     fixed under Subchapter C or K, the owner shall mail to the surety
2-21     on the bond a copy of all notices received.
2-22           SECTION 8.  Section 53.255(b), Property Code, is amended to
2-23     read as follows:
2-24           (b)  The disclosure statement must read substantially similar
2-25     to the following:
2-26           "KNOW YOUR RIGHTS AND RESPONSIBILITIES UNDER THE LAW.  You
2-27     are about to enter into a transaction to build a new home or
2-28     remodel existing residential property.  Texas law requires your
2-29     contractor to provide you with this brief overview of some of your
2-30     rights, responsibilities, and risks in this transaction.
2-31           "CONVEYANCE TO CONTRACTOR NOT REQUIRED [PROHIBITED]. Your
2-32     contractor may not require you to convey your real property to your
2-33     contractor as a condition to the agreement for the construction of
2-34     improvements on your property.
2-35           "KNOW YOUR CONTRACTOR.  Before you enter into your agreement
2-36     for the construction of improvements to your real property, make
2-37     sure that you have investigated your contractor.  Obtain and verify
2-38     references from other people who have used the contractor for the
2-39     type and size of construction project on your property.
2-40           "GET IT IN WRITING.  Make sure that you have a written
2-41     agreement with your contractor that includes:  (1) a description of
2-42     the work the contractor is to perform;  (2) the required or
2-43     estimated time for completion of the work;  (3) the cost of the
2-44     work or how the cost will be determined; and (4) the procedure and
2-45     method of payment, including provisions for statutory retainage and
2-46     conditions for final payment.  If your contractor made a promise,
2-47     warranty, or representation to you concerning the work the
2-48     contractor is to perform, make sure that promise, warranty, or
2-49     representation is specified in the written agreement.  An oral
2-50     promise that is not included in the written agreement may not be
2-51     enforceable under Texas law.
2-52           "READ BEFORE YOU SIGN.  Do not sign any document before you
2-53     have read and understood it.  NEVER SIGN A DOCUMENT THAT INCLUDES
2-54     AN UNTRUE STATEMENT.  Take your time in reviewing documents.  If
2-55     you borrow money from a lender to pay for the improvements, you are
2-56     entitled to have the loan closing documents furnished to you for
2-57     review at least one business day before the closing.  Do not waive
2-58     this requirement unless a bona fide emergency or another good cause
2-59     exists, and make sure you understand the documents before you sign
2-60     them.  If you fail to comply with the terms of the documents, you
2-61     could lose your property.  You are entitled to have your own
2-62     attorney review any documents.  If you have any question about the
2-63     meaning of a document, consult an attorney.
2-64           "GET A LIST OF SUBCONTRACTORS AND SUPPLIERS. Before
2-65     construction commences, your contractor is required to provide you
2-66     with a list of the subcontractors and suppliers the contractor
2-67     intends to use on your project.  Your contractor is required to
2-68     supply updated information on any subcontractors and suppliers
2-69     added after the list is provided.  Your contractor is not required
 3-1     to supply this information if you sign a written waiver of your
 3-2     rights to receive this information.
 3-3           "MONITOR THE WORK.  Lenders and governmental authorities may
 3-4     inspect the work in progress from time to time for their own
 3-5     purposes.  These inspections are not intended as quality control
 3-6     inspections.  Quality control is a matter for you and your
 3-7     contractor.  To ensure that your home is being constructed in
 3-8     accordance with your wishes and specifications, you should inspect
 3-9     the work yourself or have your own independent inspector review the
3-10     work in progress.
3-11           "MONITOR PAYMENTS.  If you use a lender, your lender is
3-12     required to provide you with a periodic statement showing the money
3-13     disbursed by the lender from the proceeds of your loan.  Each time
3-14     your contractor requests payment from you or your lender for work
3-15     performed, your [Your] contractor is also required to furnish you
3-16     with a disbursement statement that lists the name and address of
3-17     each subcontractor or supplier that the contractor intends to pay
3-18     from the requested funds [at least once each month of money
3-19     disbursed to subcontractors and suppliers for this project].
3-20     Review these statements and make sure that the money is being
3-21     properly disbursed.
3-22           "CLAIMS BY SUBCONTRACTORS AND SUPPLIERS.  Under Texas law, if
3-23     a subcontractor or supplier who furnishes labor or materials for
3-24     the construction of improvements on your property is not paid, you
3-25     may become liable and your property may be subject to a lien for
3-26     the unpaid amount, even if you have not contracted directly with
3-27     the subcontractor or supplier.  To avoid liability, you should take
3-28     the following actions:
3-29                       (1)  If you receive a written notice from a
3-30           subcontractor or supplier, you should withhold payment from
3-31           your contractor for the amount of the claim stated in the
3-32           notice until the dispute between your contractor and the
3-33           subcontractor or supplier is resolved.  If your lender is
3-34           disbursing money directly to your contractor, you should
3-35           immediately provide a copy of the notice to your lender and
3-36           instruct the lender to withhold payment in the amount of the
3-37           claim stated in the notice.  If you continue to pay the
3-38           contractor after receiving the written notice without
3-39           withholding the amount of the claim, you may be liable and
3-40           your property may be subject to a lien for the amount you
3-41           failed to withhold.
3-42                       (2)  During construction and for 30 days after
3-43           final completion, termination, or abandonment of the contract
3-44           by the contractor, you should withhold or cause your lender
3-45           to withhold 10 percent of the amount of payments made for the
3-46           work performed by your contractor.  This is sometimes
3-47           referred to as 'statutory retainage.'  If you choose not
3-48           [fail] to withhold the 10 percent for at least 30 days after
3-49           final completion, termination, or abandonment of the contract
3-50           by the contractor and if a valid claim is timely made by a
3-51           claimant and your contractor fails to pay the claim, you may
3-52           be personally liable and your property may be subject to a
3-53           lien up to the amount that you failed to withhold.
3-54           "If a claim is not paid within a certain time period, the
3-55     claimant is required to file a mechanic's lien affidavit in the
3-56     real property records in the county where the property is located.
3-57     A mechanic's lien affidavit is not a lien on your property, but the
3-58     filing of the affidavit could result in a court imposing a lien on
3-59     your property if the claimant is successful in litigation to
3-60     enforce the lien claim.
3-61           "SOME CLAIMS MAY NOT BE VALID. When you receive a written
3-62     notice of a claim or when a mechanic's lien affidavit is filed on
3-63     your property, you should know your legal rights and
3-64     responsibilities regarding the claim.  Not all claims are valid.  A
3-65     notice of a claim by a subcontractor or supplier is required to be
3-66     sent, and the mechanic's lien affidavit is required to be filed,
3-67     within strict time periods.  The notice and the affidavit must
3-68     contain certain information.  All claimants may not fully comply
3-69     with the legal requirements to collect on a claim.  If you have
 4-1     paid the contractor in full before receiving a notice of a claim
 4-2     and have fully complied with the law regarding statutory retainage,
 4-3     you may not be liable for that claim.    Accordingly, you should
 4-4     consult your attorney when you receive a written notice of a claim
 4-5     to determine the true extent of your liability or potential
 4-6     liability for that claim.
 4-7           "OBTAIN A LIEN RELEASE AND A BILLS-PAID AFFIDAVIT. When you
 4-8     receive a notice of claim, do not release withheld funds without
 4-9     obtaining a signed and notarized release of lien and claim from the
4-10     claimant.  You can also reduce the risk of having a claim filed by
4-11     a subcontractor or supplier by requiring as a condition of each
4-12     payment made by you or your lender that your contractor furnish you
4-13     with an affidavit stating that all bills have been paid.  Under
4-14     Texas law, on final completion of the work and before final
4-15     payment, the contractor is required to furnish you with an
4-16     affidavit stating that all bills have been paid.  If the contractor
4-17     discloses any unpaid bill in the affidavit, you should withhold
4-18     payment in the amount of the unpaid bill until you receive a waiver
4-19     of lien or release from that subcontractor or supplier.
4-20           "OBTAIN TITLE INSURANCE PROTECTION. You may be able to obtain
4-21     a title insurance policy to insure that the title to your property
4-22     and the existing improvements on your property are free from liens
4-23     claimed by subcontractors and suppliers.  If your policy is issued
4-24     before the improvements are completed and covers the value of the
4-25     improvements to be completed, you should obtain, on the completion
4-26     of the improvements and as a condition of your final payment, a
4-27     'completion of improvements' policy endorsement.  This endorsement
4-28     will protect your property from liens claimed by subcontractors and
4-29     suppliers that may arise from the date the original title policy is
4-30     issued to the date of the endorsement."
4-31           SECTION 9.  Section 53.256, Property Code, is amended by
4-32     amending Subsections (a)  and (b) and adding Subsection (d) to read
4-33     as follows:
4-34           (a)  Except as provided by Subsection (d), for [For] the
4-35     construction of improvements under a residential construction
4-36     contract, the original contractor shall:
4-37                 (1)  [must attach to the disclosure statement required
4-38     by Section 53.255 or] furnish to the owner before the commencement
4-39     of construction a written list that identifies by name, address,
4-40     and telephone number each subcontractor and supplier the contractor
4-41     intends to use in the work to be performed; and
4-42                 (2)  [.  The contractor shall] provide the owner with
4-43     an updated list of subcontractors and suppliers not later than the
4-44     15th day after the date a subcontractor or supplier is added or
4-45     deleted.
4-46           (b)  The list must contain the following notice conspicuously
4-47     printed, stamped, or typed in a size equal to at least 10-point
4-48     boldface or the computer equivalent:
4-49           "NOTICE:  THIS LIST OF SUBCONTRACTORS AND SUPPLIERS MAY NOT
4-50     BE A FINAL LISTING. UNLESS YOU SIGN A WAIVER OF YOUR RIGHT TO
4-51     RECEIVE UPDATED INFORMATION, THE CONTRACTOR IS REQUIRED BY LAW TO
4-52     SUPPLY UPDATED INFORMATION, AS THE INFORMATION BECOMES AVAILABLE,
4-53     FOR EACH SUBCONTRACTOR OR SUPPLIER USED IN THE WORK PERFORMED ON
4-54     YOUR RESIDENCE."
4-55           (d)  An owner may waive the right to receive the list of
4-56     subcontractors and suppliers or any updated information required by
4-57     this section only as provided by this subsection.  The waiver must
4-58     be in writing and may be included in the residential construction
4-59     contract.  If the waiver is not included as a provision of the
4-60     residential construction contract, the separate waiver statement
4-61     must be signed by the owner.  The waiver must be conspicuously
4-62     printed in at least 10-point bold-faced type and read substantially
4-63     similar to the following:
4-64           "WAIVER OF THE LIST OF SUBCONTRACTORS AND SUPPLIERS.  AN
4-65     OWNER IS NOT REQUIRED TO WAIVE THE RIGHT GRANTED BY SECTION 53.256,
4-66     PROPERTY CODE, TO RECEIVE FROM THE CONTRACTOR AN ORIGINAL OR
4-67     UPDATED LIST OF SUBCONTRACTORS AND SUPPLIERS.
4-68           "BY SIGNING THIS DOCUMENT, I AGREE TO WAIVE MY RIGHT TO
4-69     RECEIVE FROM THE CONTRACTOR AN ORIGINAL OR UPDATED LIST OF
 5-1     SUBCONTRACTORS AND SUPPLIERS.
 5-2           "I UNDERSTAND AND ACKNOWLEDGE THAT, AFTER SIGNING THIS
 5-3     DOCUMENT, THIS WAIVER MAY NOT BE CANCELED AT A LATER DATE.
 5-4           "I HAVE VOLUNTARILY CONSENTED TO THIS WAIVER."
 5-5           SECTION 10.  Sections 53.258(a), (b), and (e), Property Code,
 5-6     are amended to read as follows:
 5-7           (a)  At the time the original contractor requests payment
 5-8     from the owner or the owner's lender for the construction of
 5-9     improvements under a residential construction contract, the
5-10     original contractor shall provide to the owner a disbursement
5-11     statement.  The statement may include any information agreed to by
5-12     the owner and the original contractor and must include at least the
5-13     name and address of each person who subcontracted directly with the
5-14     original contractor and who the original contractor intends to pay
5-15     from the requested funds.  The original contractor shall provide
5-16     the disbursement statement:
5-17                 (1)  in the manner agreed to in writing by the owner
5-18     and original contractor; or
5-19                 (2)  if no agreement exists, by depositing the
5-20     statement in the United States mail, first class, postage paid, and
5-21     properly addressed to the owner or by hand delivering the statement
5-22     to the owner before the original contractor receives the requested
5-23     funds [For the construction of improvements under a residential
5-24     construction contract, the original contractor shall provide to the
5-25     owner a signed periodic statement that lists the bills or expenses
5-26     that the original contractor represents will be paid or that have
5-27     been paid and for which the original contractor is requesting
5-28     payment.  The original contractor is not required to include in the
5-29     statement the bills or expenses for which the original contractor
5-30     has obtained a valid lien release or waiver from the subcontractor
5-31     or supplier to whom the bills or expenses are owed if the statement
5-32     includes a written representation that the balance of any funds
5-33     that are not itemized in the statement will be paid to:]
5-34                 [(1)  the subcontractor or supplier who provided the
5-35     lien release or waiver; or]
5-36                 [(2)  the original contractor as reimbursement for
5-37     expenses incurred, profit, or overhead].
5-38           (b)  If the owner finances the construction of improvements
5-39     through a third party that advances loan proceeds directly to the
5-40     original contractor, the lender shall:
5-41                 (1)  obtain from the original contractor the signed
5-42     disbursement [periodic] statement required by Subsection (a) that
5-43     covers the funds for which the original contractor is requesting
5-44     payment; and
5-45                 (2)  provide to the owner a statement of funds
5-46     disbursed by the lender since the last statement was provided to
5-47     the owner.
5-48           (e)  The failure of a lender or an original contractor to
5-49     comply with this section does not invalidate a lien under this
5-50     chapter, a contract lien, or a deed of trust.
5-51           SECTION 11.  Section 53.260, Property Code, is amended to
5-52     read as follows:
5-53           Sec. 53.260.  CONVEYANCE TO CONTRACTOR NOT REQUIRED
5-54     [PROHIBITED].  An original contractor may not require an owner of
5-55     real property to convey the real property to the original
5-56     contractor or an entity controlled by the original contractor as a
5-57     condition to the performance of the residential construction
5-58     contract for improvements to the real property.
5-59           SECTION 12.  Section 53.106(e), Property Code, is repealed.
5-60           SECTION 13.  (a)  This Act takes effect September 1, 1999.
5-61           (b)  The changes in law made by this Act apply only to
5-62     matters relating to or claims arising under an original contract,
5-63     as that term is defined by Section 53.001, Property Code, that is
5-64     entered into on or after September 1, 1999.  Matters relating to or
5-65     claims arising from an original contract, as that term is defined
5-66     by Section 53.001, Property Code, that was entered into before
5-67     September 1, 1999, are governed by the law in effect when the
5-68     contract was entered into, and the former law is continued in
5-69     effect for that purpose.
 6-1           SECTION 14.  The importance of this legislation and the
 6-2     crowded condition of the calendars in both houses create an
 6-3     emergency and an imperative public necessity that the
 6-4     constitutional rule requiring bills to be read on three several
 6-5     days in each house be suspended, and this rule is hereby suspended.
 6-6                                  * * * * *