* Estimated Two-year Net Impact to General Revenue Related Funds for *
* SB913, As Introduced: positive impact of $0 through the biennium *
* ending August 31, 2001. *
* *
* The bill would make no appropriation but could provide the legal *
* basis for an appropriation of funds to implement the provisions of *
* the bill. *
**************************************************************************
General Revenue-Related Funds, Five-Year Impact:
****************************************************
* Fiscal Year Probable Net Positive/(Negative) *
* Impact to General Revenue Related *
* Funds *
* 2000 $0 *
* 2001 0 *
* 2002 0 *
* 2003 0 *
* 2004 0 *
****************************************************
All Funds, Five-Year Impact:
***************************************************************************
*Fiscal Probable Cost from State Change in Number of State *
* Year Highway Fund Employees from FY 1999 *
* 0006 *
* 2000 $(2,196,997) 3.0 *
* 2001 (22,776,997) 3.0 *
* 2002 (696,997) 3.0 *
* 2003 (696,997) 3.0 *
* 2004 (696,997) 3.0 *
***************************************************************************
Fiscal Analysis
The bill would require the Texas Department of Transportation (TXDOT) to
establish and maintain an inspection station in Brownsville, Laredo, and
El Paso along a major highway at or near a border crossing from Mexico
so that all federal, state, and municipal agencies that regulate the
passage of commercial motor vehicles could be located in one place.
Methodology
TXDOT estimated costs for the Brownsville and Laredo inspection stations
to be approximately $5.2 million for each facility in fiscal year 2001.
The cost included weight in motion technology and illumination similar
to other new inspection stations. Cost for the El Paso inspection
station, also in fiscal year 2001, was estimated to be $7.5 million due
to increased right-of-way cost. TXDOT estimated $1.6 million per bridge
for Intelligent Transportation System, allowing for electronic motor
carrier credentialing and border clearance. Estimated costs for fiscal
year 2000 included design work at each facility of $400,000 per bridge
and engineering and contingency costs of $280,000 per bridge. TXDOT
included costs for one Engineer at each bridge to manage and oversee the
program.
Local Government Impact
No significant fiscal implication to units of local government is
anticipated.
Source Agencies: