SRC-MKV S.B. 910 77(R)   BILL ANALYSIS


Senate Research Center   S.B. 910
77R3831 SMH-FBy: Shapiro
Natural Resources
3/26/2001
As Filed


DIGEST AND PURPOSE 

Current Texas law does not require a rock quarry to reclaim the land once
it has completed its mining operations.  The Railroad Commission does
require a lignite coal or uranium mine to reclaim the land once mining
operations are complete.  The Railroad Commission's oversight of quarries
only covers safety issues under the Pit and Safety Act.  Quarries are
required to meet several environmental standards on the front end of
operation but are not required to meet any standard once mining operations
are complete.  Examples of permits required for operation include clean
air, clean water, stormwater runoff, and other federal workplace standards.
As proposed, S.B. 910 requires all new quarries to obtain a "certificate of
registration" from the Railroad Commission prior to beginning a mining
operation.  S.B. 910 also requires a quarry operator, as a part of
registration, to file a reclamation plan before mining can begin.   

RULEMAKING AUTHORITY

Rulemaking authority is expressly granted to the Railroad Commission of
Texas in SECTION 1 (Sections 135.051 and 135.102 Natural Resources Code) of
this bill. 

SECTION BY SECTION ANALYSIS

SECTION 1.  Amend Title 4, Natural Resources Code, by adding Chapter 135,
as follows: 

CHAPTER 135.  AGGREGATE QUARRYING AND RECLAMATION

SUBCHAPTER A.  GENERAL PROVISIONS

Sec. 135.001.  SHORT TITLE.  Provides that this chapter may be cited as the
Texas Aggregate Quarrying and Reclamation Act. 

Sec. 135.002.  DEFINITIONS.  Provides that "aggregates," "commission,"
"operator," "overburden," "owner," "pit," "quarrying," "quarry," "ridge,"
and "site" have the meanings assigned those terms in Section 133.003.
Defines "certificate holder," "land affected," and "reclamation." 

Sec. 135.003.  EXEMPTIONS.  (a) Provides that this chapter does not apply
to land under the jurisdiction of the General Land Office; land from which
aggregates are being produced on September 1, 2001; or a parcel of land
less than five acres. 

(b) Requires land covered by Subsection (a)(1) on which quarrying is
conducted to be reclaimed in a manner consistent with this chapter and
notwithstanding Subsection (a)(1). 

(c) Sets forth conditions under which an operator is prohibited from
expanding the surface acreage of a pit from which aggregates are being
produced on September 1, 2001. 
 
Reserves Section 135.004-135.050 for expansion.



SUBCHAPTER B.  AUTHORITY OF COMMISSION

Sec. 135.051.  GENERAL AUTHORITY OF COMMISSION.  (a) Sets forth the
authority of the Railroad Commission of Texas (commission) relating to this
chapter. 

(b) Provides that this chapter does not authorize the commission to
adjudicate property title or property rights disputes. 

Sec. 135.052.  INSPECTIONS.  (a) Authorizes the commission or an authorized
representative of the commission, on reasonable notice and on presentation
of appropriate credentials, to inspect a quarrying operation for the
purpose of determining whether the operation is properly reclaiming the
land affected by the operation. 
 
  (b) Authorizes an inspection to be conducted only during normal operating
hours. 

(c) Requires an inspector to provide a written statement of the reasons for
the inspection. 

(d) Requires an inspector to prepare an inspection report adequate to
enforce the requirements of, and to implement, this chapter.  Requires the
inspector to provide a copy of the report to the operator or an authorized
representative of the operator before departing the quarrying operation and
requires an inspector to file the report with the commission.  Requires the
commission to provide a copy of the report to the operator and each owner
of the sire of the quarry who is not the operator. 

  (e) Requires the commission to establish a system of rotation of
inspectors. 

Reserves Sections 135.053-135.100 for expansion.

SUBCHAPTER C.  CERTIFICATE OF REGISTRATION

Sec. 135.101.  CERTIFICATE OF REGISTRATION REQUIRED.  Prohibits a person
from conducting a quarrying operating in this state unless the person holds
a certificate of registration for that operation issued by the commission
under this chapter. 

Sec. 135.102.  APPLICATION.  (a) Requires a person to file an application
for a certificate of registration with the commission on a concise form
prescribed by the commission, accompanied by a fee of $200 and the bond or
alternative form of financial security required by Subchapter D, to obtain
a certificate of registration. 

  (b) Requires the application to include certain information.

(c) Requires a separate application for each quarrying operation.  Requires
the commission by rule to specify criteria for determining whether a
quarrying operation constitutes a separate operation for which a separate
application is required. 

Sec. 135.103.  ISSUANCE OF CERTIFICATE.  (a) Requires the commission to
carry out certain duties not later than the 30th day after the date the
commission receives a completed application, the application fee, and a
bond or alternative form of financial security as required by Subchapter D. 

 (b) Prohibits the commission from giving public notice or holding a public
hearing before issuing a certificate of registration. 

Sec. 135.104.  TERM OF CERTIFICATE.  Provides that a certificate of
registration expires on the first anniversary of the date of issuance. 

Sec. 135.105.  RENEWAL OF CERTIFICATE.  Authorizes a person to renew an
unexpired certificate of registration by paying a renewal fee of $500 to
the commission before the expiration date of the certificate. 

Sec. 135.106.  RECLAMATION STANDARDS.  Requires a certificate of
registration to require that the quarrying operations meet the applicable
reclamation standards of this chapter and commission rules. 

Sec. 135.107.  TRANSFER OF CERTIFICATE.  (a) Requires an operator to
provide written notice to the commission at least 15 days before the date
the operator transfers a certificate of registration and requires the
notice to meet certain criteria. 

(b) Authorizes an operator to transfer a certificate of registration on or
after the 15th day after the date the operator provides notice under
Subsection (a) unless the commission notifies the operator that the
transfer is disapproved before that day.  Sets forth procedures on the
transfer of the certificate. 

Sec. 135.108. AMENDMENT OF CERTIFICATE.  (a) Authorizes the commission to
amend a certificate of registration, on application, to cover additional
land that is in the immediate vicinity of the quarry for which the
certificate was issued, including land that is not contiguous to the
quarry. 

(b) Requires an application for an amended certificate of registration to
describe the additional land to be covered by the certificate and the
quarrying operations to be conducted on the land. 

(c) Provides that the filing of an application to amend a certificate of
registration does not affect the authority granted under the certificate of
which amendment is sought. 

Reserves Sections 135.109-135.150 for expansion.

SUBCHAPTER D.  BOND OR ALTERNATIVE FORM OF FINANCIAL SECURITY

Sec. 135.151.  BOND REQUIRED.  (a) Requires an application for a
certificate of registration to be accompanied by  a bond on a form
prescribed by the commission payable to the state and conditioned on the
operator's compliance with the requirements of this chapter, any rule
adopted or order issued by the commission under this chapter, and the
reclamation plan for the quarry. 

(b) Requires a bond to be signed by the operator as principal and by a good
and sufficient surety licensed to do business in this state. 

Sec. 135.152.  AMOUNT OF BOND.  Requires a bond to be in the amount of
$1,000 for each acre of land to be disturbed as provided by the reclamation
plan for the proposed quarry. 

Sec. 135.153.  TERM OF BOND.  (a) Requires a bond to remain in effect until
the commission determines that the quarry has been reclaimed in accordance
with this chapter, commission rules, and the reclamation plan for the
quarry. 

 (b) Authorizes the commission, notwithstanding Subsection (a), to release
a part of the amount of the bond if the commission determines that part of
a quarry site has been reclaimed in accordance with this chapter. 

Sec. 135.154.  CANCELLATION OF BOND.  Prohibits the surety on a bond from
canceling the bond until the 91st day after the date the surety gives the
commission written notice of intent to cancel the bond. 

Sec. 135.155.  SUBSTITUTION OF SURETY.  (a) Requires the operator, after
receiving notice from the commission, to substitute another good and
sufficient surety licensed to do business in this state, if the surety on a
bond ceases to do business in this state or the surety's license to do
business is suspended or revoked. 

(b) Authorizes the commission to suspend the operator's certificate of
registration until the substitution is made, if an operator fails to
substitute sureties as required by this section. 

Sec. 135.156.  ALTERNATIVE FORM OF FINANCIAL SECURITY.  Sets forth
alternative forms of financial security . 

Reserves Sections 135.157-135.200 for expansion.

SUBCHAPTER E.  CONDUCT OF QUARRYING OPERATIONS

Sec. 135.201.  DISTANCE OF PIT PERIMETER FROM PROPERTY LINE.  Sets forth
the requirements for the location of a pit perimeter. 

Reserves Sections 135.202-135.250 for expansion.

SUBCHAPTER F.  RECLAMATION

Sec. 135.251.  RECLAMATION PLAN.  (a) Requires a reclamation plan submitted
as part of an application for a certificate of registration to be developed
in a manner consistent with certain conditions and technologies. 

  (b) Requires a reclamation plan to specify certain information.

(c) Authorizes an operator to amend a reclamation plan at any time, subject
to commission approval. 

Sec. 135.252.  ACCESS TO LAND ABOVE BENCH OR HIGHWALL.  Requires that, if a
quarrying operation produces a bench or solid rock highwall, the operator
provide at least one suitable access to land above the bench or highwall. 

Sec. 135.253.  RESTRICTION OF WATERWAY.  Prohibits an operator from moving
overburden in a manner that restricts a waterway unless a drainway can be
constructed with the approval of each proper state agency. 

Sec. 135.254.  GRADING OF OVERBURDEN.  (a) Requires an operator to perform
certain duties relating to grading of overburden. 

(b) Provides that this section does not apply to a quarrying operation
conducted in the flood plain of a river or stream and subject to periodic
flooding or in a wetland; or the pit of which is covered by a lake or
settlement pond as provided by Section 135.255. 

 (c) Provides that notwithstanding Subsection (a), an operator is not
required to backfill a pit and may leave boulders in a pit. 

Sec. 135.255.  CONSTRUCTION OF DAM.  Authorizes an operator to construct a
dam to form a lake or settlement pond in a pit resulting from a quarrying
operation. 

Sec. 135.256.  REVEGETATION.  Provides that revegetation of land affected
by a quarrying operation is not required if the chemical or physical
characteristics of the soil seriously inhibit plant growth or the land is
to be covered by a permanent lake or pond. 

Reserves Sections 135.257-135.300 for expansion.

SUBCHAPTER G.  ADMINISTRATIVE PENALTY.

Sec. 135.301.  IMPOSITION OF PENALTY.  Requires the commission to impose an
administrative penalty on an owner or operator of a quarrying operation who
violates this chapter or a rule adopted or order issued under this chapter. 

Sec. 135.302.  AMOUNT OF PENALTY.  Provides that the amount of the penalty
is $5,000, and each day that a violation continues or occurs is a separate
violation for purposes of imposing a penalty. 

Sec. 135.303.  NOTICE OF VIOLATION AND PENALTY.  (a) Requires the
commission to give written notice of a violation to the person alleged to
have committed the violation if, after investigation of a possible
violation and the facts surrounding that possible violation, the commission
determines that a violation has occurred. 

  (b) Requires the notice to include certain information.

Sec. 135.304.  PENALTY TO BE PAID OR HEARING REQUESTED.  (a) Authorizes the
person receiving the notice, not later than the 20th day after the date the
person receives the notice, in writing to accept the determination and the
proposed administrative penalty or make a request for a hearing on the
occurrence of the violation, the amount of the penalty, or both. 

(b) Requires the commission by order to approve the determination and
impose the proposed penalty if the person accepts the determination and
proposed penalty. 

Sec. 135.305.  HEARING.  (a) Requires the commission to set a hearing and
give written notice of the hearing to the person if the person requests a
hearing or fails to respond in a timely manner to the notice.  Authorizes
the commission to employ a hearings officer to hold the hearing. 

(b) Requires the hearings officer to make findings of fact and conclusions
of law and promptly issue to the commission a proposal for a decision about
the occurrence of the violation and the amount of a proposed penalty. 

Sec. 135.306.  DECISION BY COMMISSION.  (a) Authorizes the commission by
order, based on findings of fact, conclusions of law, and proposal for a
decision, to find that a violation occurred and impose a penalty or find
that a violation did not occur. 

(b) Requires the notice of the commissioner's order given to the person to
include a statement of the right of the person to judicial review of the
order. 

Sec. 135.307.  OPTIONS FOLLOWING DECISION; PAY OR APPEAL.  Requires the
person, not later than the 30th day after the date the commission's order
becomes final, to pay  the penalty or file a petition for a judicial review
contesting the occurrence of the violation, the amount of the penalty, or
both.  

Sec. 135.308.  STAY OF ENFORCEMENT OF PENALTY.  (a) Authorizes a person who
files a petition for judicial review within the 30-day period prescribed by
Section 135.307 to stay enforcement of the penalty or request the court to
stay the enforcement of the penalty by following certain procedures. 

(b) Sets forth procedures regarding an affidavit filed under Subsection
(a)(2). 

Sec. 135.309.  COLLECTION OF PENALTY.  (a) Authorizes the penalty to be
collected if the person does not pay the penalty and the enforcement of the
penalty is not stayed. 

  (b) Authorizes the attorney general to sue to collect the penalty.

(c) Requires a penalty collected under this subchapter to be deposited in
the state treasury to the credit of the Texas aggregate quarry reclamation
account. 

Sec. 135.310.  DECISION BY COURT.  (a) Authorizes the court, if the court
sustains the finding that a violation occurred, to uphold or reduce the
amount of the penalty and order the person to pay the full or reduced
amount of the penalty. 

(b) Requires the court, if the court does not sustain the finding that a
violation occurred, to order that a penalty is not owed. 

Sec. 135.311.  REMITTANCE OF PENALTY AND INTEREST.  (a) Requires the court
to order, when the court's judgment becomes final, that the appropriate
amount plus accrued interest be remitted to the person, if the person paid
the penalty and if the amount of the penalty is reduced or the penalty is
not upheld by the court. 

(b) Provides that the interest accrues at the rate charged on loans to
depository institutions by the New York Federal Reserve Bank. 

(c) Requires the interest to be paid for the period beginning on the date
the penalty is paid and ending on the date the penalty is remitted. 

Sec. 135.312.  RELEASE OF BOND.  (a) Requires the court to order, when the
court's judgment becomes final, the release of the bond if the person gave
a supersedeas bond and the penalty is not upheld in court. 

(b) Requires the court to order the release of the bond after the person
pays the reduced amount if the person gave a supersedeas bond and the
amount of the penalty is reduced. 

Sec. 135.313.  ADMINISTRATIVE PROCEDURE.  Provides that a proceeding to
impose the penalty is considered to be a contested case under Chapter 2001
(Administrative Procedure), Government Code. 

Reserves Sections 135.314-135.350 for expansion.

SUBCHAPTER H.  RECLAMATION ACCOUNT

Sec. 135.351.  TEXAS AGGREGATE QUARRY RECLAMATION ACCOUNT.  (a) Requires
the commission to deposit the amount recovered on a bond or alternative
form of financial security as required by Subchapter D or an administrative
penalty collected under  Subchapter G to the credit to the Texas aggregate
quarry reclamation account (account). 

(b) Provides the account is an account in the general revenue fund that may
be appropriated only for the purpose of undertaking corrective or
enforcement action under this chapter. 

SECTION 2.  (a) Effective date: September 1, 2001.

(b) Requires the Railroad Commission of Texas to adopt rules as necessary
to implement this Act not later than March 1, 2002. 

(c) Authorizes an operator to begin conducting a quarrying operation in
this state on or after the effective date of this Act and before the
commission adopts rules as provided by Subsection (b) of this section
without obtaining a certificate of registration for that operation from the
commission under Chapter 135, Natural Resources Code, as added by this Act,
and notwithstanding Section 135.101, Natural Resources Code, as added by
this Act.  Requires an operator described by this subsection to file an
application for a certificate of registration under Section 135.102,
Natural Resources Code, as added by this Act, accompanied by a reclamation
plan under Section 135.251, Natural Resources Code, as added by this Act,
as soon as practicable after the commission adopts rules.  Authorizes an
operator who files an application accompanied by a reclamation plan to
continue conducting the operation under this subsection until the
commission approves or disapproves the application and reclamation plan.