SRC-TAG C.S.S.B. 1271 78(R)    BILL ANALYSIS


Senate Research CenterC.S.S.B. 1271
By: Armbrister
Natural Resources
4/11/2003
Committee Report (Substituted)


DIGEST AND PURPOSE 

Currently, if a utility makes an investment after it has prepared a rate
case, it must wait until the next case to begin recovering on that
investment.  However, utilities are facing some challenges in obtaining
the necessary  capital for new investments to meet the continuing growth
in Texas and to replace facilities to enhance safety.  C.S.S.B. 1271
permits utility companies to begin recovery on new investment in the year
following completion of construction.   

RULEMAKING AUTHORITY

This bill does not expressly grant any additional rulemaking authority to
a state officer, institution, or agency. 

SECTION BY SECTION ANALYSIS

SECTION 1.  Amends Chapter 104, Utilities Code, by adding Subchapter G, as
follows: 

SUBCHAPTER G.  INTERIM COST RECOVERY AND RATE ADJUSTMENT

Sec.  104.301.  INTERIM ADJUSTMENT FOR CHANGES IN INVESTMENT.  (a)
Authorizes a gas utility that has filed a rate case under Subchapter C
within the preceding two years to file with the regulatory authority a
tariff or rate schedule that provides for an interim adjustment in the
utility's monthly customer charge or initial block rate to recover the
cost of changes in investment in service for gas utility services.
Requires the adjustment to be allocated among the gas utility's classes of
customers in the same manner as the cost of service was allocated among
the classes of customers in the utility's latest effective rates for the
area in which the tariff is implemented.  Requires the gas utility to file
the tariff or rate schedule, or the annual adjustment under Subsection
(c), with the regulatory authority at least 60 days before the proposed
implementation date of the tariff, rate schedule, or annual adjustment.
Requires the gas utility to provide notice of the tariff, rate schedule,
or annual adjustment to affected customers by bill insert or direct mail
by the 45th day after the date the utility files the tariff, rate schedule
or annual adjustment with the regulatory authority.   Authorizes the
regulatory authority, during the 60-day period, to act to suspend the
implementation of the tariff, rate schedule, or annual adjustment.
Requires, after the issuance of a final order or decision by a regulatory
authority in a rate case that is filed after the implementation of a
tariff or rate schedule under this section, any change in investment that
has been included in an interim adjustment in accordance with tariff or
rate schedule under this section to no longer be subject to  subsequent
review for reasonableness or prudence.  Provides that until the issuance
of a final order or decision by a regulatory authority in a rate case that
is filed after the implementation of a tariff or rate schedule under this
section, all amounts collected under the tariff or rate schedule before
the filing of the rate case are subject to refund. 

(b)  Provides that the amount the gas utility shall adjust the utility's
rates upward or downward under the tariff or rate schedule each calendar
year is based on the difference between the value of the invested capital
for the preceding calendar year and the value of the invested capital for
the calendar year preceding that calendar year.  Establishes that the
value of the invested capital is equal to the  original cost of the
investment at the time the investment was first dedicated to public use
minus the accumulated depreciation related to that investment. 

(c)   Requires the interim adjustment to be recalculated on an annual
basis in accordance with the requirements of Subsection (b).  Authorizes
the gas utility to file a request with the regulatory authority to suspend
the operation of the tariff or rate schedule for any year.  Requires the
request to be in writing and state the reasons why the suspension is
justified.  Authorizes the regulatory authority to grant the suspension on
a showing by the utility of reasonable justification. 

(d)  Authorizes a gas utility to only adjust the utility's rate under the
tariff or rate schedule for the return on investment, depreciation
expense, ad valorem taxes, revenues related taxes, and incremental federal
income taxes related to the difference in the value of the invested
capital as determined under Subsection (b). Requires the return on
investment, depreciation, and incremental federal income tax used in the
computation to be same as the factors reflected in the final order issued
by or settlement agreement approved by the regulatory authority
establishing  the gas utility's  latest effective rates for the area in
which the tariff or rate schedule is implemented.   

(e)  Requires a gas utility that implements a tariff or rate schedule
under this section to file with the regulatory authority an annual report
describing the investment projects completed and placed in service during
the preceding calendar year and the investments retired or abandoned
during the preceding calendar year. Requires the annual report to also
state the cost, need, and customers benefited by the change in investment. 

(f)  Requires the gas utility, in addition to the report required under
Subsection (e), to file with the regulatory authority an annual earnings
monitoring report demonstrating the utility's earnings during the
preceding calendar year.  

(g)  Requires a gas utility, if it is earning a return on invested
capital, as demonstrated by the report filed under Subsection (f), of more
than 75 basis points above the return established in the latest effective
rates approved by a regulatory authority for the area in which the tariff
or rate schedule is implemented under this section, to file a statement
with that report stating the reasons why the rates are not unreasonable or
in violation of law. 

(h)  Requires a gas utility, if it implements a tariff or rate schedule
under this section but does not file a rate case under Subchapter C before
the fifth anniversary of the date on which the tariff or rate schedule
takes effect, to file a rate case under that subchapter by the 180th day
after that anniversary in relation to any rates subject to the tariff or
rate schedule. 

(i)  Provides that this section does not limit the power of a regulatory
authority under Section 104.151. 

SECTION 2.  Effective date: September 1, 2003.