Amend HB 2129 (Senate committee printing) by adding the 
following numbered SECTIONS and renumbering the subsequent 
SECTIONS of the bill accordingly.
	SECTION ___.  Section 36.053, Utilities Code, is amended by 
adding Subsection (d) to read as follows:
	(d)  If the commission issues a certificate of convenience 
and necessity or, acting under Section 39.203(e), orders an 
electric utility or a transmission and distribution utility to 
construct or enlarge transmission or transmission-related 
facilities to facilitate meeting the goal for generating capacity 
from renewable energy technologies under Section 39.904(a), the 
commission shall find that the facilities are used and useful to the 
utility in providing service for purposes of this section and are 
prudent and includable in the rate base, regardless of the extent of 
the utility's actual use of the facilities.
	SECTION ___.  Subsection (e), Section 39.203, Utilities 
Code, is amended to read as follows:
	(e)  The commission may require an electric utility or a 
transmission and distribution utility to construct or enlarge 
facilities to ensure safe and reliable service for the state's 
electric markets and to reduce transmission constraints within 
ERCOT in a cost-effective manner where the constraints are such 
that they are not being resolved through Chapter 37 or the ERCOT 
transmission planning process.  The commission shall require an 
electric utility or a transmission and distribution utility to 
construct or enlarge transmission or transmission-related 
facilities for the purpose of meeting the goal for generating 
capacity from renewable energy technologies under Section 
39.904(a).  In any proceeding brought under Chapter 37, an electric 
utility or transmission and distribution utility ordered to 
construct or enlarge facilities under this subchapter need not 
prove that the construction ordered is necessary for the service, 
accommodation, convenience, or safety of the public and need not 
address the factors listed in Sections 37.056(c)(1)-(3) and (4)(E).  
Notwithstanding any other law, including Section 37.057, in any 
proceeding brought under Chapter 37 by an electric utility or a 
transmission and distribution utility related to an application for 
a certificate of public convenience and necessity to construct or 
enlarge transmission or transmission-related facilities under this 
subsection, the commission shall issue a final order before the 
181st day after the date the application is filed with the 
commission.  If the commission does not issue a final order before 
that date, the application is approved.
	SECTION ____.  Section 39.904, Utilities Code, is amended by 
amending Subsection (a) and adding Subsections (g) through (n) to 
read as follows:
	(a)  It is the intent of the legislature that by January 1, 
2015 [2009], an additional 5,000 [2,000] megawatts of generating 
capacity from renewable energy technologies will have been 
installed in this state.  The cumulative installed renewable 
capacity in this state shall total 5,880 [1,280] megawatts by 
January 1, 2015, and the commission shall establish a target of 
10,000 megawatts of installed renewable capacity by January 1, 
2025.  The cumulative installed renewable capacity in this state 
shall total 2,280 megawatts by January 1, 2007, 3,272 megawatts by 
January 1, 2009, 4,264 megawatts by January 1, 2011, 5,256 
megawatts by January 1, 2013, and 5,880 megawatts by January 1, 
2015.  Of the renewable energy technology generating capacity 
installed to meet the goal of this subsection after September 1, 
2005, the commission shall establish a target of having at least 500 
megawatts of capacity from a renewable energy technology other than 
a source using wind energy [2003, 1,730 megawatts by January 1, 
2005, 2,280 megawatts by January 1, 2007, and 2,880 megawatts by 
January 1, 2009].
	(g)  The commission, after consultation with each 
appropriate independent organization, electric reliability 
council, or regional transmission organization:
		(1)  shall designate competitive renewable energy 
zones throughout this state in areas in which renewable energy 
resources and suitable land areas are sufficient to develop 
generating capacity from renewable energy technologies;
		(2)  shall develop a plan to construct transmission 
capacity necessary to deliver to electric customers, in a manner 
that is most beneficial and cost-effective to the customers, the 
electric output from renewable energy technologies in the 
competitive renewable energy zones; and
		(3)  shall consider the level of financial commitment 
by generators for each competitive renewable energy zone in 
determining whether to designate an area as a competitive renewable 
energy zone and whether to grant a certificate of convenience and 
necessity.
	(h)  In considering an application for a certificate of 
public convenience and necessity for a transmission project 
intended to serve a competitive renewable energy zone, the 
commission is not required to consider the factors provided by 
Sections 37.056(c)(1) and (2).
	(i)  Transmission service to a competitive renewable energy 
zone must be provided in a manner consistent with Subchapter A, 
Chapter 35.
	(j)  The commission, after consultation with each 
appropriate independent organization, electric reliability 
council, or regional transmission organization, shall file a report 
with the legislature not later than December 31 of each 
even-numbered year.  The report must include:
		(1)  an evaluation of the commission's implementation 
of competitive renewable energy zones;
		(2)  the estimated cost of transmission service 
improvements needed for each competitive renewable energy zone; and
		(3)  an evaluation of the effects that additional 
renewable generation has on system reliability and on the cost of 
alternatives to mitigate the effects.
	(k)  The commission and the independent organization 
certified for ERCOT shall study the need for increased transmission 
and generation capacity throughout this state and report to the 
legislature the results of the study and any recommendations for 
legislation.  The report must be filed with the legislature not 
later than December 31 of each even-numbered year and may be filed 
as a part of the report required by Subsection (j).
	(l)  The commission may adopt rules requiring renewable 
power facilities to have reactive power control capabilities or any 
other feasible technology designed to reduce the facilities' 
effects on system reliability.
	(m)  Notwithstanding any other provision of law, the 
commission shall ensure that all renewable capacity installed in 
this state and all renewable energy credits awarded, produced, 
procured, or sold in this state are counted toward the goal in 
Subsection (a).
	(n)  Notwithstanding any other provision of law, the 
commission shall have the authority to cap the price of renewable 
energy credits and may suspend the goal contained in Subsection (a) 
if such suspension is necessary to protect the reliability and 
operation of the grid.