79R5289 JJT-F
By:  Duncan                                                       S.B. No. 836
A BILL TO BE ENTITLED
AN ACT
relating to the state's goal for electric generation capacity by 
renewable energy technologies and the rate treatment of utility 
expenditures for interconnecting generating capacity by certain 
renewable technologies.
	BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:                        
	SECTION 1.  Section 36.053, Utilities Code, is amended by 
adding Subsection (d) to read as follows:
	(d)  If, in a proceeding in which transmission or 
transmission related facilities are certificated under Chapter 37, 
the commission found that the facilities are needed to accommodate 
future development or future interconnection of renewable energy 
technology generation capacity, the commission shall find that the 
facilities are used by and useful to the utility in providing 
service, regardless of the extent of the actual use of the 
facilities.
	SECTION 2.  Section 39.904, Utilities Code, is amended by 
amending Subsection (a) and adding Subsections (c-1) and (c-2) to 
read as follows:
	(a)  It is the intent of the legislature that by January 1, 
2015 [2009], an additional 10,000 [2,000] megawatts of generating 
capacity from renewable energy technologies will have been 
installed in this state.  The cumulative installed renewable 
capacity in this state shall total [1,280 megawatts by January 1, 
2003, 1,730 megawatts by January 1, 2005,] 2,280 megawatts by 
January 1, 2007, [and] 2,880 megawatts by January 1, 2009, 4,880 
megawatts by January 1, 2011, 7,880 megawatts by January 1, 2013, 
and 10,880 megawatts by January 1, 2015.  At least 500 megawatts of 
the generating capacity from renewable energy technologies 
installed in this state by January 1, 2015, must be from distributed 
renewable energy generation technologies.
	(c-1)  The commission by rule shall establish competitive 
renewable energy generation zones in appropriate areas of this 
state and annually shall consider designating new competitive 
renewable energy generation zones.  The commission may designate as 
a competitive renewable energy generation zone any defined 
geographic area in which renewable energy resources and suitable 
land areas are sufficient to develop at least 1,000 megawatts of 
nameplate generating capacity from renewable energy technology.  
The initial competitive renewable energy generation zones 
designated by the commission must define a contiguous area of not 
more than four counties in which renewable energy technology 
generation capacity of at least 80 megawatts of nameplate capacity 
is available or under construction on December 31, 2005.
	(c-2)  For the purposes of Section 39.101(b)(3) and to 
promote the development of renewable energy technology, the 
commission shall take all necessary actions, including:
		(1)  ordering the construction of transmission 
facilities to alleviate local or regional transmission capacity 
constraints or congestion measured by the nameplate capacity of 
renewable energy technology generation that is operational or under 
construction on December 31, 2005;
		(2)  directing the appropriate independent 
organization or electric reliability council and transmission and 
distribution service providers to study, plan for, and route 
additional transmission facilities to anticipate and to facilitate 
the further development of renewable energy technology generation 
capacity in those partially developed competitive renewable energy 
generation zones in which existing transmission capacity is already 
constrained, congested, or at capacity;
		(3)  designating competitive renewable energy 
generation zones and, in conjunction with each appropriate 
independent organization, electric reliability council, or 
regional transmission organization, develop a plan to construct 
transmission capacity to interconnect and deliver full output to 
customers of energy generated by existing and anticipated renewable 
energy technology in the zones in a manner that is most beneficial 
and cost-effective for electric consumers; and
		(4)  establishing a process by which, if the commission 
finds that the evidence shows the transmission facilities will be 
needed by the time anticipated renewable energy generation 
facilities can become operational, the commission may grant a 
certificate of convenience and necessity for transmission 
facilities to provide retail customer access to energy from 
competitive renewable energy generation zones, without requiring 
that an interconnection agreement be executed by a renewable energy 
technology generator.
	SECTION 3.  The Public Utility Commission of Texas shall 
designate the initial competitive renewable energy generation 
zones under Section 39.904, Utilities Code, as amended by this Act, 
not later than January 1, 2006.
	SECTION 4.  The Public Utility Commission of Texas shall 
adopt rules to implement this Act as soon as practicable.
	SECTION 5.  This Act takes effect September 1, 2005.