Overview
The Galveston Causeway Railroad Bridge (GCRB) is the most
dangerous place on the entire Gulf Intracoastal Waterway, from
Brownsville to Florida. In 2001, the Coast Guard has declared it an
unreasonable obstruction to navigation and set in motion plans to
replace it with a wider bridge offering over 300' of clearance. The
new bridge is under design and the best case estimate for completion
of the new bridge is approximately 2011.
TXDOT plans to remove the fenderworks that protect all three
bridges and facilitate barge transits through this tricky area as
soon as the highway bridges are complete in late 2007, even though
the GCRB will not be widened. This will greatly increase the risk to
marine traffic, all the bridges, the general public and the
environment pending completion of the new GCRB.
This rider continues the current maintenance by TXDOT of the
fenderworks of the Galveston Causeway Bridge.
Required Action
(1) On page ___ of the Department of Transportation's bill
pattern, State Highway Funds in Strategy C.1.31, Gulf Waterway
Contracted Maintenance.
(2) On page ___ of the Department of Transportation's bill
pattern, add the following rider:
____. Galveston Causeway. Out of funds appropriated above in
Strategy C.1.31, Gulf Waterway Contracted Maintenance. State
Highway Funds shall be used for the maintenance and preservation of
the fenderworks at the Galveston Causeway. Any unexpended balances
from this appropriation remaining as of August 31, 2007, are hereby
appropriated in the fiscal year beginning September 1, 2008, for
the same purpose.