BILL ANALYSIS

 

 

Senate Research Center                                                                                                     H.B. 2075

80R11054 JTS-F                                                                                               By: Krusee (Nichols)

                                                                                                 Transportation & Homeland Security

                                                                                                                                              5/4/2007

                                                                                                                                           Engrossed

 

 

AUTHOR'S / SPONSOR'S STATEMENT OF INTENT

 

Current law requires the Texas Department of Transportation (TxDOT) to retain five percent of the contract price for a highway project until the entire improvement has been completed and accepted.  The purpose of this retention is to ensure that all bills on a project are paid, and that if an excess payment is made by TxDOT, TxDOT has a mechanism to recoup the funds at the end of a project.  However, the stability of performance and payment bonds has eliminated the need for retainage.  Such bonds provide a full guaranty that all bills are paid and quantities adjusted at the end of a project. 

 

H.B. 2075 authorizes TxDOT, on projects that are solely funded by the state, to mirror the provision for no retainage that currently applies to federally-aided work. 

 

RULEMAKING AUTHORITY

 

This bill does not expressly grant any additional rulemaking authority to a state officer, institution, or agency.

 

SECTION BY SECTION ANALYSIS

 

SECTION 1.  Amends Section 223.009, Transportation Code, to delete existing text prohibiting the aggregate amount of payments at any time from exceeding 95 percent of the value of the work done.

 

SECTION 2.  Amends Section 223.010(a), Transportation Code, to authorize the Department of Transportation (TxDOT) to retain a percentage of the contract price until the entire improvement has been completed and accepted.  Deletes existing text requiring five percent of the contract price to be retained until those conditions are met.  Makes a conforming deletion.

 

SECTION 3.  Repealer:  Section 223.010(h) (requiring four percent of the contract price to be retained until the entire improvement has been completed and accepted on any contract that includes the use of recycled materials), Section 223.010(i) (authorizing TxDOT to release a portion of the amount, no more than is sufficient to ensure compliance with the contract, retained under Subsection (a) at the time construction of the improvement is completed), and Section 223.011 (Partial Payment Exception; Maintenance and Preconstruction Contracts), Transportation Code.

 

SECTION 4.  Effective date: upon passage or September 1, 2007.