AN ACT
|
|
relating to the authority of the Texas Water Development Board to |
|
approve the regional water plan for Region L and include the plan in |
|
the state water plan. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. (a) Notwithstanding Section 16.053(i), Water |
|
Code, and except as otherwise provided by this Act, the Texas Water |
|
Development Board may approve and include in the state water plan |
|
for the five-year period beginning January 5, 2007, the regional |
|
water plan that was submitted to the board by the Region L regional |
|
water planning group. |
|
(b) The Texas Water Development Board may approve the |
|
regional water plan for Region L only if the board: |
|
(1) strikes Sections 4C.7, 4C.8, and 4C.32 from the |
|
plan as submitted to the board; and |
|
(2) includes Section 4C.33 in the plan as the Lower |
|
Guadalupe Water Supply Project for Upstream GBRA Needs so as to: |
|
(A) require that the project be developed by the |
|
regional water planning group for Region L in association with the |
|
Guadalupe-Blanco River Authority; |
|
(B) include a transmission pipeline for the |
|
diversion of up to 60,000 acre-feet per year of surface water |
|
available under the water rights held by the Guadalupe-Blanco River |
|
Authority as of December 31, 2006, from the Guadalupe River below |
|
the city of Victoria to upstream points on the river to meet needs |
|
identified by the Region L regional water planning group; provided, |
|
however, that at least 100,000 acre-feet per year of the surface |
|
water must be reserved for lower basin needs; |
|
(C) prohibit the use of fresh groundwater for the |
|
project; |
|
(D) require the consent of the appropriate |
|
property owner before off-channel storage or an off-channel |
|
reservoir may be developed as part of the project; and |
|
(E) require freshwater inflows in an amount |
|
sufficient to meet the Parks and Wildlife Department, Texas |
|
Commission on Environmental Quality, and Texas Water Development |
|
Board's environmental consensus criteria for San Antonio Bay to be |
|
identified and included in the project. |
|
(c) The Texas Water Development Board shall amend the state |
|
water plan for the five-year period beginning January 5, 2007, as |
|
necessary to conform to the requirements of this Act. |
|
SECTION 2. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2007. |
|
|
|
______________________________ |
______________________________ |
|
President of the Senate |
Speaker of the House |
|
|
|
I certify that H.B. No. 3776 was passed by the House on May 8, |
|
2007, by the following vote: Yeas 146, Nays 0, 2 present, not |
|
voting. |
|
|
|
______________________________ |
|
Chief Clerk of the House |
|
|
|
I certify that H.B. No. 3776 was passed by the Senate on May |
|
23, 2007, by the following vote: Yeas 29, Nays 0. |
|
|
|
______________________________ |
|
Secretary of the Senate |
|
APPROVED: _____________________ |
|
Date |
|
|
|
_____________________ |
|
Governor |