A BILL TO BE ENTITLED
AN ACT
relating to rules and policies adopted by state agencies regarding
engineering or architectural errors or omissions.
       BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
       SECTION 1.  Subchapter Z, Chapter 2252, Government Code, is
amended by adding Section 2252.904 to read as follows:
       Sec. 2252.904.  CERTAIN RULES OR POLICIES OF STATE AGENCIES.
(a)  In this section:
             (1)  "Contract" means a contract awarded by a state
agency for general construction, an improvement, a service, or a
public works project, including a contract subject to Section
201.112, Transportation Code.
             (2)  "Private design professional" means an individual
registered as an architect under Chapter 1051, Occupations Code, or
an individual licensed as an engineer under Chapter 1001,
Occupations Code, who provides professional architectural or
engineering services.
             (3)  "State agency" means a board, commission, office,
department, or other agency in the judicial or executive branch of
state government.
       (b)  A rule or policy adopted by a state agency relating to
the recovery of costs arising from an engineering or architectural
error or omission by a private design professional on a project
must:
             (1)  provide that the private design professional be
notified at the time a problem with project plans or specifications
is identified by the agency;
             (2)  provide an opportunity for the private design
professional to be involved in the resolution of a problem
identified under Subdivision (1);
             (3)  provide guidelines for distinguishing an error or
omission from other reasons for the submission of a change order;
             (4)  provide a process for determining the cost of
errors or omissions by private design professionals;
             (5)  provide for an evaluation of the totality of
project services provided by private design professionals,
including the level of quality, performance, and value provided
over the term of the entire project;
             (6)  provide that an internal management review of the
agency's claim for costs may be used, if available, without
requiring that the claim be paid before the internal management
review may be used;
             (7)  provide a process for tracking the cost of errors
or omissions by agency employees; and
             (8)  recognize that some errors, omissions, or changes
are likely to occur during a design and construction project.
       SECTION 2.  This Act takes effect September 1, 2007.