Amend CSSB 2349 (Senate committee printing) by striking all 
below the enacting clause and substituting the following:
	SECTION 1.  Section 31.002, Utilities Code, is amended by 
adding Subdivision (4-a) and amending Subdivision (10) to read as 
follows:
		(4-a) "Distributed natural gas generation facility" 
means a facility installed on the customer's side of the meter that 
is used for the generation of not more than 2,000 kilowatts of 
electricity.
		(10)  "Power generation company" means a person, 
including a person who owns or operates a distributed natural gas 
generation facility, that:
			(A)  generates electricity that is intended to be 
sold at wholesale;       
			(B)  does not own a transmission or distribution 
facility in this state other than an essential interconnecting 
facility, a facility not dedicated to public use, or a facility 
otherwise excluded from the definition of "electric utility" under 
this section; and
			(C)  does not have a certificated service area, 
although its affiliated electric utility or transmission and 
distribution utility may have a certificated service area.
	SECTION 2.  The heading to Subchapter B, Chapter 35, 
Utilities Code, is amended to read as follows:
SUBCHAPTER B. EXEMPT WHOLESALE GENERATORS, DISTRIBUTED NATURAL GAS GENERATION FACILITIES, AND POWER MARKETERS
SECTION 3. Subchapter B, Chapter 35, Utilities Code, is amended by adding Section 35.036 to read as follows: Sec. 35.036. DISTRIBUTED NATURAL GAS GENERATION FACILITIES. (a) A person who owns or operates a distributed natural gas generation facility may sell electric power generated by the facility. (1) The electric utility, electric cooperative, or retail electric provider that provides retail electricity service to the facility may purchase electric power tendered to it by the owner or operator of the facility at a value agreed to by the electric utility, electric cooperative, or retail electric provider and the owner or operator of the facility, which may include a value based on the clearing price of energy at the time of day and location that the electricity is made available to the electric grid. (2) At the request of the owner or operator of the facility, the electric utility or electric cooperative shall allow the owner or operator of the facility to use the transmission and distribution facilities to transmit the electric power to another entity that is acceptable to the owner or operator in accordance with commission rules or a tariff approved by the Federal Energy Regulatory Commission. (b) If the owner or operator of a distributed natural gas generation facility requests to be interconnected to an electric utility or electric cooperative that does not have a transmission tariff approved by the Federal Energy Regulatory Commission, the electric utility or electric cooperative may recover from the owner or operator of the facility the reasonable costs of interconnecting the facility with the electric utility or electric cooperative that are necessary for and directly attributable to the interconnection of the facility. If the rated capacity of the distributed natural gas generation exceeds the capacity of the electric utility or electric cooperative and the owner or operator of the facility requests that such an electric utility or electric cooperative make upgrades to accommodate the distributed natural generation capacity, the electric utility or electric cooperative may recover from the owner or operator of the facility the reasonable cost of electric facility upgrades and improvements that are necessary for and directly attributable to the requested accommodation of the distributed natural gas generation capacity. (c) In order to recover costs under Subsection (b), an electric utility or electric cooperative must have provided a good-faith cost estimate in writing to the owner or operator of the distributed natural gas generation facility and the owner or operator must have, prior to the incurring of any cost by the electric utility or electric cooperative, agreed in writing to pay the reasonable and necessary cost of interconnection or capacity accommodation requested by the owner or operator and described in the cost estimate. If an electric utility or electric cooperative seeks to recover from the owner or operator of the facility an amount that exceeds the good-faith estimate by more than 5 percent and the owner or operator of the facility disputes the amount that exceeds the good-faith estimate, the Public Utility Commission shall resolve the dispute at the request of the owner or operator of the facility. (d) A distributed natural gas generation facility must comply with emissions limitations established by the Texas Commission on Environmental Quality for a standard emissions permit for an electric generation facility unit installed after January 1, 1995. SECTION 4. Subsection (c), Section 39.351, Utilities Code, is amended to read as follows: (c) The commission may establish simplified filing requirements for distributed natural gas generation facilities [A power generation company may register any time after September 1, 2000]. SECTION 5. This Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution. If this Act does not receive the vote necessary for immediate effect, this Act takes effect September 1, 2009.