         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 2253.021(a), Government Code, is amended
  to read as follows:
         (a)  A governmental entity that makes a public work contract
  with a prime contractor shall require the contractor, before
  beginning the work, to execute to the governmental entity:
               (1)  a performance bond if the contract is in excess of
  $100,000; and
               (2)  a payment bond if:
                     (A)  the contract is in excess of $25,000, and the
  governmental entity is not a municipality or a joint board created
  under Subchapter D, Chapter 22, Transportation Code; or
                     (B)  the contract is in excess of $50,000, and the
  governmental entity is a municipality or a joint board created
  under Subchapter D, Chapter 22, Transportation Code.
         SECTION 2.  Section 53.231, Property Code, is amended to
  read as follows:
         Sec. 53.231.  LIEN. (a) A person who furnishes material
  or labor to a contractor under a prime contract with a governmental
  entity other than a municipality or a joint board created under
  Subchapter D, Chapter 22, Transportation Code, that does not exceed
  $25,000 and that is for public improvements in this state and who
  gives notice required by this subchapter has a lien on the money,
  bonds, or warrants due the contractor for the improvements.
         (b)  A person who furnishes material or labor to a contractor
  under a prime contract with a municipality or a joint board created
  under Subchapter D, Chapter 22, Transportation Code, that does not
  exceed $50,000 and that is for public improvements in this state and
  who gives notice required by this subchapter has a lien on the
  money, bonds, or warrants due the contractor for the improvements.
         SECTION 3.  Section 53.234, Property Code, is amended to
  read as follows:
         Sec. 53.234.  TIME FOR NOTICE.  The lien claimant must give
  notice [before any payment is made to the contractor and] not later
  than the 15th day of the second month following the month in which
  the labor was performed or the material furnished.
         SECTION 4.  The changes in law made by this Act to Section
  2253.021(a), Government Code, apply only to a contract entered into
  on or after the effective date of this Act. A contract entered into
  before the effective date of this Act is governed by the law in
  effect when the contract was entered into, and the former law is
  continued in effect for that purpose.
         SECTION 5.  This Act takes effect September 1, 2009.
 
 
  ______________________________ ______________________________
     President of the Senate Speaker of the House     
 
 
         I certify that H.B. No. 2515 was passed by the House on April
  28, 2009, by the following vote:  Yeas 147, Nays 0, 1 present, not
  voting; and that the House concurred in Senate amendments to H.B.
  No. 2515 on May 29, 2009, by the following vote:  Yeas 141, Nays 0,
  1 present, not voting.
 
  ______________________________
  Chief Clerk of the House   
 
         I certify that H.B. No. 2515 was passed by the Senate, with
  amendments, on May 26, 2009, by the following vote:  Yeas 31, Nays
  0.
 