A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to surcharges for advanced metering of electric utility |
|
services. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 39.107(h), Utilities Code, is amended to |
|
read as follows: |
|
(h) The commission shall establish a nonbypassable |
|
surcharge for an electric utility or transmission and distribution |
|
utility to use to recover reasonable and necessary costs incurred |
|
in deploying advanced metering and meter information networks to |
|
residential customers and nonresidential customers other than |
|
those required by the independent system operator to have an |
|
interval data recorder meter. The commission shall ensure that the |
|
nonbypassable surcharge reflects a deployment of advanced meters |
|
that is no more than one-third of the utility's total meters over |
|
each calendar year and shall ensure that the nonbypassable |
|
surcharge does not result in the utility recovering more than its |
|
actual, fully allocated meter and meter information network costs. |
|
The expenses must be allocated to the customer classes receiving |
|
the services, based on the electric utility's most recently |
|
approved tariffs, and the amount of the surcharge must be stated |
|
separately on each customer's bill. The commission by rule shall |
|
provide that a surcharge under this subsection may not be imposed on |
|
a customer before the customer has an advanced meter installed |
|
unless the electric utility or transmission and distribution |
|
utility provides for the customer to recover the full amount of |
|
surcharges paid by means of a discount for billed services after |
|
installation of the meter. |
|
SECTION 2. The Public Utility Commission of Texas shall |
|
adopt rules to implement the changes in law made by Section |
|
39.107(h), Utilities Code, as amended by this Act. The rules must |
|
take effect not later than January 1, 2010. |
|
SECTION 3. This Act takes effect September 1, 2009. |