A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the ability of electric utilities to provide electric |
|
service during a major power outage. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter D, Chapter 38, Utilities Code, is |
|
amended by adding Section 38.072 to read as follows: |
|
Sec. 38.072. ELECTRIC SERVICE DURING A MAJOR POWER OUTAGE. |
|
(a) For purposes of this section, "electric utility" includes: |
|
(1) a municipally owned utility; and |
|
(2) an electric cooperative. |
|
(b) The commission shall conduct a study to evaluate whether |
|
there is a need in this state for electric utilities to improve |
|
their ability to restore electric service to customers after a |
|
major power outage that is expected to last for more than 24 hours. |
|
(c) On a determination that there is a need in this state for |
|
a particular electric utility to improve its ability to restore |
|
electric service to customers after a major power outage, the |
|
commission may require the electric utility to maintain: |
|
(1) an additional physical interconnection with |
|
another electric utility, regardless of whether the electric |
|
utilities operate within the same power region; |
|
(2) an emergency electricity supply agreement with at |
|
least one other electric utility; or |
|
(3) a joint restoration procedure with at least one |
|
other electric utility. |
|
(d) The commission may require an electric utility to |
|
provide information regarding: |
|
(1) the utility's ability to restore service during a |
|
major power outage; and |
|
(2) a report regarding the utility's progress in |
|
implementing a measure the commission requires under Subsection |
|
(c). |
|
SECTION 2. Not later than September 1, 2011, the Public |
|
Utility Commission of Texas shall submit a report of the results of |
|
the study required by Section 38.072, Utilities Code, as added by |
|
this Act, to the legislature. |
|
SECTION 3. This Act takes effect September 1, 2009. |