Amend the Deshotel amendment to CSHB 1390 as follows:
(1)  Strike page 2, line 15, through page 3, line 7, and substitute the following:
(f)  A claimant has a lien on, and the owner is personally liable to the claimant for, the retained funds under Subchapter E if the claimant:
(1)  gives notice in accordance with this section and:
(A)  complies with Subchapter E; or
(B)  files an affidavit claiming a lien not later than the earliest of:
(i)  the date required for filing an affidavit under Section 53.052;
(ii)  the 40th day after the date stated in an affidavit of completion as the date of completion of the work under the original contract, if the owner sent the claimant notice of an affidavit of completion in the time and manner required;
(iii)  the 40th day after the date of termination or abandonment of the original contract, if the owner sent the claimant a notice of such termination or abandonment in the time and manner required; or
(iv)  the 30th day after the date the owner sent to the claimant to the claimant's address provided in the notice for contractual retainage, as required under Subsection (c), a written notice of demand for the claimant to file the affidavit claiming a lien; and
(2)  gives the notice of the filed affidavit as required by Section 53.055.
(2)  On page 3, line 23, strike "provided" and substitute "allowed".