This website will be unavailable from Friday, April 26, 2024 at 6:00 p.m. through Monday, April 29, 2024 at 7:00 a.m. due to data center maintenance.

  82R17798 PMO-F
 
  By: Deshotel, Bohac H.B. No. 1390
 
  Substitute the following for H.B. No. 1390:
 
  By:  Quintanilla C.S.H.B. No. 1390
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to retainage under certain construction contracts.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 53.053(e), Property Code, is amended to
  read as follows:
         (e)  A claim for retainage accrues on the last day of the
  month in which all work called for by the contract between the owner
  and the original contractor has been completed, finally settled,
  terminated, or abandoned.
         SECTION 2.  Section 53.056(d), Property Code, is amended to
  read as follows:
         (d)  Except as provided by Section 53.057, to [To] authorize
  the owner to withhold funds under Subchapter D, the notice to the
  owner must state that if the claim remains unpaid, the owner may be
  personally liable and the owner's property may be subjected to a
  lien unless:
               (1)  the owner withholds payments from the contractor
  for payment of the claim; or
               (2)  the claim is otherwise paid or settled.
         SECTION 3.  Section 53.057, Property Code, is amended to
  read as follows:
         Sec. 53.057.  DERIVATIVE CLAIMANT: NOTICE FOR [CONTRACTUAL]
  RETAINAGE CLAIM.  (a)  For the portion of a retainage claim not in
  excess of the amount of the required retainage under Section
  53.101, a [A] claimant may give notice under this section instead of
  or in addition to notice under Section 53.056 or 53.252 if the
  claimant is to labor, furnish labor or materials, or specially
  fabricate materials, or has labored, furnished labor or materials,
  or specially fabricated materials, under an agreement with an
  original contractor or a subcontractor providing for retainage.
         (b)  The claimant must give notice that the claimant may have
  a lien claim for retainage to the owner or reputed owner [notice of
  the retainage agreement] not later than the earliest of:
               (1)  the 15th day of the second month following the date
  the claimant completed the work required under the claimant's
  contract with the original contractor or subcontractor;
               (2)  the 25th day after the date the work under the
  original contract is completed, provided that the owner, if
  required, gave notice under Section 53.106 or 53.108 to the
  claimant;
               (3)  the 25th day after the date the original contract
  is terminated, provided that the owner, if required, gave notice
  under Section 53.107 to the claimant; or
               (4)  the 25th day after the date the original
  contractor abandons performance under the original contract,
  provided that the owner, if required, gave notice under Section
  53.107 to the claimant [the delivery of materials or the
  performance of labor by the claimant that first occurs after the
  claimant has agreed to the contractual retainage. If the agreement
  is with a subcontractor, the claimant must also give notice within
  that time to the original contractor].
         (c)  [The notice must contain:
               [(1)  the sum to be retained;
               [(2)  the due date or dates, if known; and
               [(3)     a general indication of the nature of the
  agreement.
         [(d)]  The notice must be sent by registered or certified
  mail to the last known business or residence address of the owner or
  reputed owner or the original contractor, as applicable.
         (d) [(e)]  If a claimant gives notice under this section [and
  Section 53.055 or, if the claim relates to a residential
  construction project, under this section and Section 53.252], the
  claimant is not required to give any other notice as to the
  retainage before the date the notice under Section 53.055 is
  required.
         SECTION 4.  Section 53.081(c), Property Code, is amended to
  read as follows:
         (c)  If notice is sent under Section 53.057, the owner may
  withhold funds immediately on receipt of the notice.  The owner may
  withhold funds by retaining funds under Subchapter E for the period
  required by Section 53.082 [a copy of the claimant's affidavit
  prepared in accordance with Sections 53.052 through 53.055].
         SECTION 5.  Section 53.103, Property Code, is amended to
  read as follows:
         Sec. 53.103.  LIEN ON RETAINED FUNDS. A claimant has a lien
  on the retained funds if the claimant:
               (1)  sends the notices required by this chapter in the
  time and manner required; and
               (2)  files an affidavit claiming a lien not later than
  the [30th day after the] earlier of [the date]:
                     (A)  the 60th day after the earliest of:
                           (i)  the date the work under the original
  contract is completed, provided that the owner, if required, gave
  notice under Section 53.106 or 53.108 to the claimant;
                           (ii)  the date the original contract is
  terminated, provided that the owner, if required, gave notice under
  Section 53.107 to the claimant; or
                           (iii)  the date the original contractor
  abandons performance under the original contract, provided that the
  owner, if required, gave notice under Section 53.107 to the
  claimant; or
                     (B)  the last day of the period provided under
  Section 53.052 [work is completed;
                     [(B)  the original contract is terminated; or
                     [(C)     the original contractor abandons
  performance under the original contract].
         SECTION 6.  Section 53.106, Property Code, is amended to
  read as follows:
         Sec. 53.106.  AFFIDAVIT OF COMPLETION. (a)  An owner may
  file with the county clerk of the county in which the property is
  located an affidavit of completion. The affidavit must contain:
               (1)  the name and address of the owner;
               (2)  the name and address of the original contractor;
               (3)  a description, legally sufficient for
  identification, of the real property on which the improvements are
  located;
               (4)  a description of the improvements furnished under
  the original contract;
               (5)  a statement that the improvements under the
  original contract have been completed and the date of completion;
  and
               (6)  a conspicuous statement that a claimant may not
  have a lien on retained funds unless the claimant:
                     (A)  complies with the notice requirement under
  Section 53.057 not later than the earlier of:
                           (i)  the 15th day of the second month
  following the date the claimant completed the work required under
  the claimant's contract with the original contractor or
  subcontractor; or
                           (ii)  the 25th day after the date the work
  under the original contract is completed; and
                     (B)  files an [the] affidavit claiming a lien not
  later than the 60th [30th] day after the date the work under the
  original contract is completed [of completion].
         (b)  A copy of the affidavit must be sent by certified or
  registered mail to the original contractor not later than the date
  the affidavit is filed and to each claimant who sends a notice of
  lien liability to the owner under Section 53.056, 53.057, 53.058,
  53.252, or 53.253 not later than the date the affidavit is filed or
  the fifth [10th] day after the date the owner receives the notice of
  lien liability, whichever is later.
         (c)  A copy of the affidavit must also be sent to each person
  who furnishes labor or materials for the property and who furnishes
  the owner with a written request for the copy. The owner must
  furnish the copy to the person not later than the date the affidavit
  is filed or the fifth [10th] day after the date the request is
  received, whichever is later.
         (d)  Except as provided by this subsection, an affidavit
  filed under this section on or before the fifth [10th] day after the
  date of completion of the improvements is prima facie evidence of
  the date the work under the original contract is completed for
  purposes of this subchapter and Section 53.057. If the affidavit is
  filed after the fifth [10th] day after the date of completion, the
  date of completion for purposes of this subchapter and Section
  53.057 is the date the affidavit is filed. This subsection does not
  apply to a person to whom the affidavit was not sent as required by
  this section.
         SECTION 7.  Sections 53.107(a), (b), (c), and (d), Property
  Code, are amended to read as follows:
         (a)  Not later than the fifth [10th] day after the date an
  original contract is terminated or the original contractor abandons
  performance under the original contract, the owner shall give
  notice to each subcontractor who, before the date of termination or
  abandonment, has:
               (1)  given notice to the owner as provided by Section
  53.056, 53.057, or 53.058; or
               (2)  sent to the owner by certified or registered mail a
  written request for notice of termination or abandonment.
         (b)  The notice must contain:
               (1)  the name and address of the owner;
               (2)  the name and address of the original contractor;
               (3)  a description, legally sufficient for
  identification, of the real property on which the improvements are
  located;
               (4)  a general description of the improvements agreed
  to be furnished under the original contract;
               (5)  a statement that the original contract has been
  terminated or that performance under the contract has been
  abandoned;
               (6)  the date of the termination or abandonment; and
               (7)  a conspicuous statement that a claimant may not
  have a lien on the retained funds unless the claimant:
                     (A)  complies with the notice requirement in
  Section 53.057 not later than the earlier of:
                           (i)  the 15th day of the second month
  following the date the claimant completed the work required under
  the claimant's contract with the original contractor or
  subcontractor; or
                           (ii)  the 25th day after the date the
  original contract is terminated or abandoned; and
                     (B)  files an affidavit claiming a lien not later
  than the 60th [30th] day after the date of the termination or
  abandonment.
         (c)  A notice sent in compliance with this section on or
  before the fifth [10th] day after the date of termination or
  abandonment is prima facie evidence of the date the original
  contract was terminated or work was abandoned for purposes of this
  subchapter.
         (d)  A subcontractor to whom an owner fails to send notice
  under this section is not required to comply with Section 53.057 to
  claim retainage and may claim a lien by filing a lien affidavit as
  prescribed by Section 53.052 [who fails to file a lien affidavit in
  the time prescribed by Section 53.103(2) has a lien to the extent
  authorized under this subchapter if:
               [(1)     the subcontractor otherwise complies with this
  chapter; and
               [(2)     the owner did not provide the subcontractor
  notice as required by this section].
         SECTION 8.  Subchapter E, Chapter 53, Property Code, is
  amended by adding Section 53.108 to read as follows:
         Sec. 53.108.  NOTICE OF COMPLETION TO SECURE RETAINAGE
  CLAIM. (a)  Not later than the fifth day after the date of
  completion, an owner shall send by certified mail, return receipt
  requested, or registered mail a notice of completion to:
               (1)  the original contractor;
               (2)  any person who provides a notice under Section
  53.056, 53.057, 53.058, 53.252, or 53.253; and
               (3)  any person who furnished labor or provided
  materials for the improvement and requests a copy of the notice of
  completion.
         (b)  The notice must contain:
               (1)  the name and address of the owner;
               (2)  the name and address of the original contractor;
               (3)  a description, legally sufficient for
  identification, of the real property on which the improvements are
  located;
               (4)  a description of the improvements furnished under
  the original contract;
               (5)  a statement that the improvements under the
  original contract have been completed; and
               (6)  the date of completion.
         (c)  A notice sent in compliance with this section is prima
  facie evidence under Sections 53.053(e) and 53.057 of the date the
  work under the original contract was completed.
         (d)  An owner who sends a copy of an affidavit of completion
  as prescribed by Section 53.106 satisfies the requirements of this
  section.
         (e)  A person described by Subsection (a) to whom an owner
  fails to send notice under this section is not required to comply
  with Section 53.057 to claim contractual retainage and may claim a
  lien by filing a lien affidavit as prescribed by Section 53.052.
         SECTION 9.  Sections 53.159(a), (b), and (e), Property Code,
  are amended to read as follows:
         (a)  An owner, on written request, shall furnish the
  following information within a reasonable time, but not later than
  the 10th day after the date the request is received, to any person
  furnishing labor or materials for the project:
               (1)  a description of the real property being improved
  legally sufficient to identify it;
               (2)  whether there is a surety bond and if so, the name
  and last known address of the surety and a copy of the bond; [and]
               (3)  whether there are any prior recorded liens or
  security interests on the real property being improved and if so,
  the name and address of the person having the lien or security
  interest; and
               (4)  the date on which the original contract for the
  project was executed.
         (b)  An original contractor, on written request by a person
  who furnished work under the original contract, shall furnish to
  the person the following information within a reasonable time, but
  not later than the 10th day after the date the request is received:
               (1)  the name and last known address of the person to
  whom the original contractor furnished labor or materials for the
  construction project; [and]
               (2)  whether the original contractor has furnished or
  has been furnished a payment bond for any of the work on the
  construction project and if so, the name and last known address of
  the surety and a copy of the bond; and
               (3)  the date on which the original contract for the
  project was executed.
         (e)  If a person from whom information is requested does not
  have a direct contractual relationship on the project with the
  person requesting the information, the person from whom information
  is requested, other than a claimant requested to furnish
  information under Subsection (d), may require payment of the actual
  costs, not to exceed $25, in furnishing the requested information.
  A subcontractor who does not receive information requested under
  Subsection (a)(4) within the period prescribed by Subsection (a) is
  not required to comply with Section 53.057 and may perfect a lien
  for retainage by filing a lien affidavit under Section 53.052.
         SECTION 10.  Section 53.160(b), Property Code, is amended to
  read as follows:
         (b)  The grounds for objecting to the validity or
  enforceability of the claim or lien for purposes of the motion are
  limited to the following:
               (1)  notice of claim was not furnished to the owner or
  original contractor as required by Section 53.056, 53.057, 53.058,
  53.252, or 53.253;
               (2)  an affidavit claiming a lien failed to comply with
  Section 53.054 or was not filed as required by Section 53.052;
               (3)  notice of the filed affidavit was not furnished to
  the owner or original contractor as required by Section 53.055;
               (4)  the deadlines for perfecting a lien claim for
  retainage under this chapter have expired and the owner complied
  with the requirements of Section 53.101 and paid the retainage and
  all other funds owed to the original contractor before:
                     (A)  the claimant perfected the lien claim; and
                     (B)  the owner received a notice of the claim as
  required by this chapter;
               (5)  all funds subject to the notice of a claim to the
  owner and a notice regarding the [perfection of a claim against the
  statutory] retainage have been deposited in the registry of the
  court and the owner has no additional liability to the claimant;
               (6)  when the lien affidavit was filed on homestead
  property:
                     (A)  no contract was executed or filed as required
  by Section 53.254;
                     (B)  the affidavit claiming a lien failed to
  contain the notice as required by Section 53.254; or
                     (C)  the notice of the claim failed to include the
  statement required by Section 53.254; and
               (7)  the claimant executed a valid and enforceable
  waiver or release of the claim or lien claimed in the affidavit.
         SECTION 11.  Chapter 53, Property Code, as amended by this
  Act, applies only to a lien claim for labor or materials furnished
  under a subcontract where the original contract was entered into on
  or after the effective date of this Act.  A lien claim for labor or
  materials furnished under a subcontract where the original contract
  was entered into before the effective date of this Act is governed
  by the law in effect immediately before the effective date of this
  Act, and that law is continued in effect for that purpose.
         SECTION 12.  This Act takes effect September 1, 2011.