          A BILL TO BE ENTITLED
         | 
      
      
        | 
           
			 | 
        
          AN ACT
         | 
      
      
        | 
           
			 | 
        relating to deadlines for the Railroad Commission of Texas to  | 
      
      
        | 
           
			 | 
        review certain applications for surface coal mining operation  | 
      
      
        | 
           
			 | 
        permits. | 
      
      
        | 
           
			 | 
               BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | 
      
      
        | 
           
			 | 
               SECTION 1.  Section 134.004, Natural Resources Code, is  | 
      
      
        | 
           
			 | 
        amended by adding Subdivision (7-a) to read as follows: | 
      
      
        | 
           
			 | 
                     (7-a)  "Director" means the director, Surface Mining  | 
      
      
        | 
           
			 | 
        and Reclamation Division, Railroad Commission of Texas, or the  | 
      
      
        | 
           
			 | 
        director's representative. | 
      
      
        | 
           
			 | 
               SECTION 2.  Section 134.080, Natural Resources Code, is  | 
      
      
        | 
           
			 | 
        amended to read as follows: | 
      
      
        | 
           
			 | 
               Sec. 134.080.  APPROVAL [OR DISAPPROVAL] OF PERMIT REVISION.   | 
      
      
        | 
           
			 | 
        [(a)]  The commission may not approve an application for a permit  | 
      
      
        | 
           
			 | 
        revision unless the commission finds that reclamation as required  | 
      
      
        | 
           
			 | 
        by this chapter can be accomplished under the revised reclamation  | 
      
      
        | 
           
			 | 
        plan. | 
      
      
        | 
           
			 | 
               [(b)
           
           
          The commission shall approve or disapprove the 
         | 
      
      
        | 
           
			 | 
        
          revision not later than the 90th day after the date the permit 
         | 
      
      
        | 
           
			 | 
        
          holder submits the application to the commission.] | 
      
      
        | 
           
			 | 
               SECTION 3.  Subchapter D, Chapter 134, Natural Resources  | 
      
      
        | 
           
			 | 
        Code, is amended by adding Section 134.085 to read as follows: | 
      
      
        | 
           
			 | 
               Sec. 134.085.  REVIEW PERIODS FOR NEW PERMITS, RENEWALS, AND  | 
      
      
        | 
           
			 | 
        REVISIONS.  (a)  Not later than the seventh day after the date the  | 
      
      
        | 
           
			 | 
        commission receives an application for a new permit or for renewal  | 
      
      
        | 
           
			 | 
        or a significant revision of a permit, the director shall complete a  | 
      
      
        | 
           
			 | 
        review of the application to determine whether the application is  | 
      
      
        | 
           
			 | 
        complete. | 
      
      
        | 
           
			 | 
               (b)  If the director determines that the application is  | 
      
      
        | 
           
			 | 
        complete, the director shall file the application with the  | 
      
      
        | 
           
			 | 
        commission's office of general counsel for processing under  | 
      
      
        | 
           
			 | 
        commission rules and Chapter 2001, Government Code. | 
      
      
        | 
           
			 | 
               (c)  If the director determines that the application is not  | 
      
      
        | 
           
			 | 
        complete, the director shall send a written notice to the applicant  | 
      
      
        | 
           
			 | 
        that identifies the specific information that the applicant must  | 
      
      
        | 
           
			 | 
        provide to the commission.  Not later than the seventh day after the  | 
      
      
        | 
           
			 | 
        date the commission receives the requested information, the  | 
      
      
        | 
           
			 | 
        director shall complete another review of the application to assess  | 
      
      
        | 
           
			 | 
        the completeness of the application. | 
      
      
        | 
           
			 | 
               (d)  Not later than the 120th day after the date the  | 
      
      
        | 
           
			 | 
        commission receives an application described by Subsection (a) that  | 
      
      
        | 
           
			 | 
        the director determines is complete, the director shall complete  | 
      
      
        | 
           
			 | 
        the technical review of the application and make a recommendation  | 
      
      
        | 
           
			 | 
        to approve or deny the application to the commission's office of  | 
      
      
        | 
           
			 | 
        general counsel. | 
      
      
        | 
           
			 | 
               (e)  If the director determines that the application is  | 
      
      
        | 
           
			 | 
        deficient under Subsection (d): | 
      
      
        | 
           
			 | 
                     (1)  the period required by Subsection (d) for  | 
      
      
        | 
           
			 | 
        completing the review of the application is tolled until the date  | 
      
      
        | 
           
			 | 
        the commission receives the requested information from the  | 
      
      
        | 
           
			 | 
        applicant; and | 
      
      
        | 
           
			 | 
                     (2)  the director shall send a written notice to the  | 
      
      
        | 
           
			 | 
        applicant that notifies the applicant: | 
      
      
        | 
           
			 | 
                           (A)  that the review period required by Subsection  | 
      
      
        | 
           
			 | 
        (d) is being tolled; | 
      
      
        | 
           
			 | 
                           (B)  of the reason the review period is being  | 
      
      
        | 
           
			 | 
        tolled; | 
      
      
        | 
           
			 | 
                           (C)  of the information the applicant must submit  | 
      
      
        | 
           
			 | 
        to the commission before the commission will resume the review of  | 
      
      
        | 
           
			 | 
        the application; and | 
      
      
        | 
           
			 | 
                           (D)  of the number of days remaining that the  | 
      
      
        | 
           
			 | 
        commission has to review the application after the commission  | 
      
      
        | 
           
			 | 
        receives the requested information from the applicant. | 
      
      
        | 
           
			 | 
               (f)  If the applicant submits supplemental information to  | 
      
      
        | 
           
			 | 
        the commission that is not in response to a request for information  | 
      
      
        | 
           
			 | 
        under Subsection (e), the director may extend the review period  | 
      
      
        | 
           
			 | 
        required by Subsection (d) for an additional period of not more than  | 
      
      
        | 
           
			 | 
        60 days.  The director shall provide written notice to the applicant  | 
      
      
        | 
           
			 | 
        that includes the director's decision regarding whether to extend  | 
      
      
        | 
           
			 | 
        the review period, the reason for the decision, and the number of  | 
      
      
        | 
           
			 | 
        days remaining in the review period. | 
      
      
        | 
           
			 | 
               (g)  This subsection and Subsection (h) apply only to an  | 
      
      
        | 
           
			 | 
        application for a permit revision that the director determines is  | 
      
      
        | 
           
			 | 
        not a significant departure from the approved method or conduct of  | 
      
      
        | 
           
			 | 
        mining and reclamation operations.  Not later than the 90th day  | 
      
      
        | 
           
			 | 
        after the date the commission receives a complete application, the  | 
      
      
        | 
           
			 | 
        director shall provide written notice to the applicant that the  | 
      
      
        | 
           
			 | 
        permit revision request has been approved or denied. | 
      
      
        | 
           
			 | 
               (h)  If the director determines that the application is  | 
      
      
        | 
           
			 | 
        deficient: | 
      
      
        | 
           
			 | 
                     (1)  the review period required by Subsection (g) to  | 
      
      
        | 
           
			 | 
        approve or deny the application under this section is tolled until  | 
      
      
        | 
           
			 | 
        the date the commission receives the requested information from the  | 
      
      
        | 
           
			 | 
        applicant; and | 
      
      
        | 
           
			 | 
                     (2)  the director shall send a written notice to the  | 
      
      
        | 
           
			 | 
        applicant that notifies the applicant: | 
      
      
        | 
           
			 | 
                           (A)  that the review period required by Subsection  | 
      
      
        | 
           
			 | 
        (g) is being tolled; | 
      
      
        | 
           
			 | 
                           (B)  of the reason the review period is being  | 
      
      
        | 
           
			 | 
        tolled; | 
      
      
        | 
           
			 | 
                           (C)  of the information that the applicant must  | 
      
      
        | 
           
			 | 
        submit to the commission before the commission will resume the  | 
      
      
        | 
           
			 | 
        review of the revision application; and | 
      
      
        | 
           
			 | 
                           (D)  of the number of days remaining that the  | 
      
      
        | 
           
			 | 
        commission has to review the application after the commission  | 
      
      
        | 
           
			 | 
        receives the requested information from the applicant. | 
      
      
        | 
           
			 | 
               SECTION 4.  The change in law made by this Act applies only  | 
      
      
        | 
           
			 | 
        to a permit to conduct mining operations the application for which  | 
      
      
        | 
           
			 | 
        is filed with the Railroad Commission of Texas on or after the  | 
      
      
        | 
           
			 | 
        effective date of this Act.  A permit the application for which is  | 
      
      
        | 
           
			 | 
        filed before the effective date of this Act is subject to the law in  | 
      
      
        | 
           
			 | 
        effect on the date the application is filed, and that law is  | 
      
      
        | 
           
			 | 
        continued in effect for that purpose. | 
      
      
        | 
           
			 | 
               SECTION 5.  This Act takes effect immediately if it receives  | 
      
      
        | 
           
			 | 
        a vote of two-thirds of all the members elected to each house, as  | 
      
      
        | 
           
			 | 
        provided by Section 39, Article III, Texas Constitution.  If this  | 
      
      
        | 
           
			 | 
        Act does not receive the vote necessary for immediate effect, this  | 
      
      
        | 
           
			 | 
        Act takes effect September 1, 2011. |