This website will be unavailable from Friday, April 26, 2024 at 6:00 p.m. through Monday, April 29, 2024 at 7:00 a.m. due to data center maintenance.

 
 
  S.B. No. 1910
 
 
 
 
AN ACT
  relating to the delay of the transition to competition in the
  Western Electricity Coordinating Council service area and to net
  metering and energy efficiency goals and programs for utilities in
  that area.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Chapter 39, Utilities Code, is amended by adding
  Subchapter L to read as follows:
  SUBCHAPTER L. TRANSITION TO COMPETITION AND OTHER PROVISIONS FOR
  CERTAIN AREAS OUTSIDE OF ERCOT
         Sec. 39.551.  APPLICABILITY. (a) This subchapter applies
  only to an investor-owned electric utility:
               (1)  that is operating solely outside of ERCOT in areas
  of this state that were included in the Western Electricity
  Coordinating Council on January 1, 2011;
               (2)  that was not affiliated with ERCOT on January 1,
  2011; and
               (3)  to which Subchapters I, J, and K do not apply.
         (b)  The legislature finds that an electric utility subject
  to this subchapter is unable at this time to offer fair competition
  and reliable service to all retail customer classes in the area
  served by the utility.  As a result, the introduction of retail
  competition for such an electric utility is delayed until fair
  competition and reliable service are available to all retail
  customer classes as determined under this subchapter.
         Sec. 39.552.  COST-OF-SERVICE REGULATION. (a) Until the
  date on which an electric utility subject to this subchapter is
  authorized by the commission under Section 39.553(f) to implement
  retail customer choice, the rates of the utility are subject to
  regulation under Chapter 36.
         (b)  Until the date on which an electric utility subject to
  this subchapter implements customer choice, the provisions of this
  chapter, other than this subchapter and Sections 39.904 and 39.905,
  do not apply to that utility.
         Sec. 39.553.  TRANSITION TO COMPETITION. (a) The events
  prescribed by Subsections (b)-(f) shall be followed to introduce
  retail competition in the service area of an electric utility
  subject to this subchapter. The commission shall ensure that the
  listed items in each stage are completed before the next stage is
  initiated.  Unless stated otherwise, the commission shall conduct
  each activity with the electric utility and other interested
  parties.  The commission may modify the sequence of events required
  by Subsections (b)-(e), but not the substance of the requirements,
  if the commission finds good cause to do so. Full retail
  competition may not begin in the service area of an electric utility
  subject to this subchapter until all actions prescribed by those
  subsections are completed.
         (b)  The first stage for the transition to competition
  consists of the following activities:
               (1)  approval of a regional transmission organization
  by the Federal Energy Regulatory Commission for the power region
  that includes the electric utility's service area and commencement
  of independent operation of the transmission network under the
  approved regional transmission organization;
               (2)  development of retail market protocols to
  facilitate retail competition; and
               (3)  completion of an expedited proceeding to develop
  nonbypassable delivery rates for the customer choice pilot project
  to be implemented under Subsection (c)(1).
         (c)  The second stage for the transition to competition
  consists of the following activities:
               (1)  initiation of the customer choice pilot project in
  accordance with Section 39.104;
               (2)  development of a balancing energy market, a market
  for ancillary services, and a market-based congestion management
  system for the wholesale market in the power region in which the
  regional transmission organization operates; and
               (3)  implementation of a seams agreement with adjacent
  power regions to reduce barriers to entry and facilitate
  competition.
         (d)  The third stage for the transition to competition
  consists of the following activities:
               (1)  the electric utility filing with the commission:
                     (A)  an application for business separation in
  accordance with Section 39.051;
                     (B)  an application for unbundled transmission
  and distribution rates in accordance with Section 39.201;
                     (C)  an application for certification of a
  qualified power region in accordance with Section 39.152; and
                     (D)  an application for price-to-beat rates in
  accordance with Section 39.202;
               (2)  the commission:
                     (A)  approving a business separation plan for the
  utility;
                     (B)  setting unbundled transmission and
  distribution rates for the utility;
                     (C)  certifying a qualified power region, which
  includes conducting a formal evaluation of wholesale market power
  in the region, in accordance with Section 39.152;
                     (D)  setting price-to-beat rates for the utility;
  and
                     (E)  determining which competitive energy
  services must be separated from regulated utility activities in
  accordance with Section 39.051; and
               (3)  completion of the testing of retail and wholesale
  systems, including those systems necessary for switching customers
  to the retail electric provider of their choice and for settlement
  of wholesale market transactions, by the regional transmission
  organization, the registration agent, and market participants.
         (e)  The fourth stage for the transition to competition
  consists of the following activities:
               (1)  commission evaluation of the results of the pilot
  project;
               (2)  initiation by the electric utility of a capacity
  auction in accordance with Section 39.153 at a time to be determined
  by the commission; and
               (3)  separation by the utility of competitive energy
  services from its regulated utility activities, in accordance with
  the commission order approving the separation of competitive energy
  services.
         (f)  The fifth stage for the transition to competition
  consists of the following activities:
               (1)  evaluation by the commission of whether the
  electric utility can offer fair competition and reliable service to
  all retail customer classes in the area served by the utility, and:
                     (A)  if the commission concludes that the electric
  utility can offer fair competition and reliable service to all
  retail customer classes in the area served by the utility, the
  commission issuing an order initiating retail competition for the
  utility; and
                     (B)  if the commission determines that the
  electric utility cannot offer fair competition and reliable service
  to all retail customer classes in the area served by the utility,
  the commission issuing an order further delaying retail competition
  for the utility; and
               (2)  on the issuance of an order from the commission
  initiating retail competition for the utility, completion by the
  utility of the business separation and unbundling in accordance
  with the commission order approving the unbundling.
         Sec. 39.554.  INTERCONNECTION OF DISTRIBUTED RENEWABLE
  GENERATION. (a)  In this section:
               (1)  "Distributed renewable generation" has the
  meaning assigned by Section 39.916.
               (2)  "Distributed renewable generation owner" means an
  owner of distributed renewable generation that is a retail electric
  customer.
               (3)  "Interconnection" has the meaning assigned by
  Section 39.916.
         (b)  A distributed renewable generation owner in the service
  area of an electric utility subject to this subchapter may request
  interconnection by filing an application for interconnection with
  the utility.  An application for interconnection is subject to the
  utility's safety and reliability requirements.  The utility's
  procedures for the submission and processing of an application for
  interconnection shall be consistent with rules adopted by the
  commission regarding interconnection.
         (c)  An electric utility that approves an application of a
  distributed renewable generation owner under Subsection (b):
               (1)  shall install, maintain, and retain ownership of
  the meter and metering equipment; and
               (2)  may install load research metering equipment on
  the premises of the owner, at no expense to the owner.
         (d)  At the request of an electric utility that approves an
  application of a distributed renewable generation owner under
  Subsection (b), the owner shall:
               (1)  provide and install a meter socket, a metering
  cabinet, or both a socket and cabinet at a location designated by
  the utility on the premises of the owner; and
               (2)  provide, at no expense to the utility, a suitable
  location for the utility to install meters and equipment associated
  with billing and load research.
         (e)  An electric utility that approves an application of a
  distributed renewable generation owner under Subsection (b) shall
  provide to the owner the metering options described by Section
  39.916(f) and an option to interconnect with the utility through a
  single meter that runs forward and backward if:
               (1)  the owner:
                     (A)  intends to interconnect the distributed
  renewable generation at an apartment house, as defined by Section
  184.011, occupied by low-income elderly tenants that qualifies for
  master metering under Section 184.012(b) and the distributed
  renewable generation is reasonably expected to generate not less
  than 50 percent of the apartment house's annual electricity use; or
                     (B)  has a qualifying facility with a design
  capacity of not more than 50 kilowatts; and
               (2)  the distributed renewable generation or
  qualifying facility that is the subject of the application is rated
  to produce an amount of electricity that is less than or equal to:
                     (A)  the owner's estimated annual kilowatt hour
  consumption for a new apartment house or qualifying facility; or
                     (B)  the amount of electricity the owner consumed
  in the year before installation of the distributed renewable
  generation or qualifying facility.
         (f)  For a distributed renewable generation owner that
  chooses interconnection through a single meter under Subsection
  (e):
               (1)  the amount of electricity the owner generates
  through distributed renewable generation or a qualifying facility
  for a given billing period offsets the owner's consumption for that
  billing period; and
               (2)  any electricity the owner generates through
  distributed renewable generation or a qualifying facility that
  exceeds the owner's consumption for a given billing period shall be
  credited to the owner under Subsection (g).
         (g)  An electric utility that purchases surplus electricity
  under Subsection (f)(2) shall purchase the electricity from the
  distributed renewable generation owner at the cost of the utility
  as determined by commission rule. The utility shall take
  reasonable steps to inform the owner of the amount of surplus
  electricity purchased from the owner in kilowatt hours during the
  owner's most recent billing cycle.  A credit balance of not more
  than $50 on the owner's monthly bill may be carried forward onto the
  owner's next monthly bill.  The utility shall refund to the owner a
  credit balance that is not carried forward or the portion of a
  credit balance that exceeds $50 if the credit balance is carried
  forward.
         (h)  In a base rate proceeding or fuel cost recovery
  proceeding conducted under Chapter 36, the commission shall ensure
  that any additional cost associated with the metering and payment
  options described by Subsections (e), (f), and (g) is allocated
  only to customer classes that include distributed renewable
  generation owners who have chosen those metering options.
         Sec. 39.555.  MARKETING OF ENERGY EFFICIENCY AND RENEWABLE
  ENERGY PROGRAMS. An electric utility subject to this subchapter
  may market an energy efficiency or renewable energy program
  directly to a retail electric customer in its service territory and
  provide rebate or incentive funds directly to a customer to promote
  or facilitate the success of programs implemented under Section
  39.905.
         SECTION 2.  This Act takes effect immediately if it receives
  a vote of two-thirds of all the members elected to each house, as
  provided by Section 39, Article III, Texas Constitution.  If this
  Act does not receive the vote necessary for immediate effect, this
  Act takes effect September 1, 2011.
 
 
 
 
 
  ______________________________ ______________________________
     President of the Senate Speaker of the House     
 
         I hereby certify that S.B. No. 1910 passed the Senate on
  May 5, 2011, by the following vote: Yeas 31, Nays 0; and that the
  Senate concurred in House amendment on May 25, 2011, by the
  following vote: Yeas 31, Nays 0.
 
 
  ______________________________
  Secretary of the Senate    
 
         I hereby certify that S.B. No. 1910 passed the House, with
  amendment, on May 20, 2011, by the following vote: Yeas 148,
  Nays 1, one present not voting.
 
 
  ______________________________
  Chief Clerk of the House   
 
 
 
  Approved:
 
  ______________________________ 
              Date
 
 
  ______________________________ 
            Governor