|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the delay of the transition to competition for an |
|
electric utility located in the Western Electricity Coordinating |
|
Council service area and net metering requirements for a certain |
|
non-ERCOT electric utility and relating to energy efficiency goals |
|
and programs for a certain non-ERCOT utility |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Chapter 39, Utilities Code, is amended by adding |
|
Subchapter L to read as follows: |
|
SUBCHAPTER L. TRANSITION TO COMPETITION FOR CERTAIN |
|
AREAS OUTSIDE OF ERCOT |
|
Sec. 39.551. APPLICABILITY. (a) This subchapter applies |
|
only to an investor-owned electric utility: |
|
(1) that is operating solely outside of ERCOT in areas |
|
of this state that were included in the Western Electricity |
|
Coordinating Council on January 1, 2011; |
|
(2) that was not affiliated with ERCOT on January 1, |
|
2011; and |
|
(3) to which Subchapters I, J, and K do not apply. |
|
(b) The legislature finds that an electric utility subject |
|
to this subchapter is unable at this time to offer fair competition |
|
and reliable service to all retail customer classes in the area |
|
served by the utility. As a result, the introduction of retail |
|
competition for such an electric utility is delayed until fair |
|
competition and reliable service are available to all retail |
|
customer classes as determined under this subchapter. |
|
Sec. 39.552. COST-OF-SERVICE REGULATION. (a) Until the |
|
date on which an electric utility subject to this subchapter is |
|
authorized by the commission under Section 39.553(f) to implement |
|
retail customer choice, the rates of the utility are subject to |
|
regulation under Chapter 36. |
|
(b) Until the date on which an electric utility subject to |
|
this subchapter implements customer choice, the provisions of this |
|
chapter, other than this subchapter and Sections 39.904 and 39.905, |
|
do not apply to that utility. |
|
Sec. 39.553. TRANSITION TO COMPETITION. (a) The events |
|
prescribed by Subsections (b)-(f) shall be followed to introduce |
|
retail competition in the service area of an electric utility |
|
subject to this subchapter. The commission shall ensure that the |
|
listed items in each stage are completed before the next stage is |
|
initiated. Unless stated otherwise, the commission shall conduct |
|
each activity with the electric utility and other interested |
|
parties. The commission may modify the sequence of events required |
|
by Subsections (b)-(e), but not the substance of the requirements, |
|
if the commission finds good cause to do so. Full retail |
|
competition may not begin in the service area of an electric utility |
|
subject to this subchapter until all actions prescribed by those |
|
subsections are completed. |
|
(b) The first stage for the transition to competition |
|
consists of the following activities: |
|
(1) approval of a regional transmission organization |
|
by the Federal Energy Regulatory Commission for the power region |
|
that includes the electric utility's service area and commencement |
|
of independent operation of the transmission network under the |
|
approved regional transmission organization; |
|
(2) development of retail market protocols to |
|
facilitate retail competition; and |
|
(3) completion of an expedited proceeding to develop |
|
nonbypassable delivery rates for the customer choice pilot project |
|
to be implemented under Subsection (c)(1). |
|
(c) The second stage for the transition to competition |
|
consists of the following activities: |
|
(1) initiation of the customer choice pilot project in |
|
accordance with Section 39.104; |
|
(2) development of a balancing energy market, a market |
|
for ancillary services, and a market-based congestion management |
|
system for the wholesale market in the power region in which the |
|
regional transmission organization operates; and |
|
(3) implementation of a seams agreement with adjacent |
|
power regions to reduce barriers to entry and facilitate |
|
competition. |
|
(d) The third stage for the transition to competition |
|
consists of the following activities: |
|
(1) the electric utility filing with the commission: |
|
(A) an application for business separation in |
|
accordance with Section 39.051; |
|
(B) an application for unbundled transmission |
|
and distribution rates in accordance with Section 39.201; |
|
(C) an application for certification of a |
|
qualified power region in accordance with Section 39.152; and |
|
(D) an application for price-to-beat rates in |
|
accordance with Section 39.202; |
|
(2) the commission: |
|
(A) approving a business separation plan for the |
|
utility; |
|
(B) setting unbundled transmission and |
|
distribution rates for the utility; |
|
(C) certifying a qualified power region, which |
|
includes conducting a formal evaluation of wholesale market power |
|
in the region, in accordance with Section 39.152; |
|
(D) setting price-to-beat rates for the utility; |
|
and |
|
(E) determining which competitive energy |
|
services must be separated from regulated utility activities in |
|
accordance with Section 39.051; and |
|
(3) completion of the testing of retail and wholesale |
|
systems, including those systems necessary for switching customers |
|
to the retail electric provider of their choice and for settlement |
|
of wholesale market transactions, by the regional transmission |
|
organization, the registration agent, and market participants. |
|
(e) The fourth stage for the transition to competition |
|
consists of the following activities: |
|
(1) commission evaluation of the results of the pilot |
|
project; |
|
(2) initiation by the electric utility of a capacity |
|
auction in accordance with Section 39.153 at a time to be determined |
|
by the commission; and |
|
(3) separation by the utility of competitive energy |
|
services from its regulated utility activities, in accordance with |
|
the commission order approving the separation of competitive energy |
|
services. |
|
(f) The fifth stage for the transition to competition |
|
consists of the following activities: |
|
(1) evaluation by the commission of whether the |
|
electric utility can offer fair competition and reliable service to |
|
all retail customer classes in the area served by the utility, and: |
|
(A) if the commission concludes that the electric |
|
utility can offer fair competition and reliable service to all |
|
retail customer classes in the area served by the utility, the |
|
commission issuing an order initiating retail competition for the |
|
utility; and |
|
(B) if the commission determines that the |
|
electric utility cannot offer fair competition and reliable service |
|
to all retail customer classes in the area served by the utility, |
|
the commission issuing an order further delaying retail competition |
|
for the utility; and |
|
(2) on the issuance of an order from the commission |
|
initiating retail competition for the utility, completion by the |
|
utility of the business separation and unbundling in accordance |
|
with the commission order approving the unbundling. |
|
Sec. 39.554 INTERCONNECTION OF DISTRIBUTED RENEWABLE |
|
GENERATION. (a) In this section: |
|
(1) "Distributed renewable generation" means electric |
|
generation with a capacity of not more than 2,000 kilowatts |
|
provided by a renewable energy technology, as defined by Section |
|
39.904, that is installed on a retail electric customer's side of |
|
the meter. |
|
(2) "Renewable energy" means any technology that |
|
exclusively relies on an energy source that is naturally |
|
regenerated over a short period of time. |
|
(3) "Distributed renewable generation owner" has the |
|
same meaning as that assigned under Section 39.916(a). |
|
(4) "Interconnection" means the right of a distributed |
|
renewable generation owner to physically connect distributed |
|
renewable generation to an electricity distribution system, and the |
|
technical requirements, rules, or processes for the connection. |
|
(5) "Surplus electricity" means electricity generated |
|
by distributed renewable generation that is not consumed at the |
|
place the distributed renewable generation is installed and that |
|
flows onto the electric distribution system of an electric utility |
|
that this subsection applies. |
|
(6) "Net consumption" means the total load of the |
|
electric utility's retail customers less the power supplied by the |
|
qualifying facility to meet any portion of that load. |
|
(7) "Net production" means the total power supplied by |
|
the qualifying facility less the power requirements of the retail |
|
electric customer. |
|
(b) A distributed renewable generation owner may request |
|
interconnection by filing an application for interconnection with |
|
the electric utility. A retail customer's application for |
|
interconnection with an electricity utility in accordance with this |
|
subsection is subject to the safety and reliability requirements of |
|
the electric utility. Procedures of the electric utility for the |
|
submission and processing of a distributed renewable generation |
|
owner's application for interconnection shall be consistent with |
|
rules adopted by the commission regarding interconnection. |
|
(c) The electric utility shall install, own and maintain the |
|
meter and metering equipment. The retail electric customer shall |
|
install a customer-furnished meter socket or metering cabinet, or |
|
both, at the electric utility's designated location solely on the |
|
retail electric customer's premises. The electric utility, at its |
|
own expense, may install load research metering equipment solely on |
|
the retail electric customer's premises. The retail electric |
|
customer shall also supply, at no expense to the electric utility, a |
|
suitable location for meters and associated equipment that will be |
|
used for billing and for load research. |
|
(d) For a retail electric customer: |
|
(1) that is an apartment house for occupancy by |
|
low-income elderly tenants, reasonably expected to generate no less |
|
than 50% of its annual energy use with distributed renewable |
|
generation and qualifying for master metering pursuant to Utilities |
|
Code Section 184.012(b); or, |
|
(2) having a qualifying facility with a design |
|
capacity which is 50 kW or less, and such distributed renewable |
|
generation or qualifying facility is rated to produce an amount of |
|
electricity that is less than or equal to the amount of electricity |
|
the retail electricity customer consumed in the twelve month period |
|
prior to installation of the qualifying facility or for new |
|
facilities their estimated annual kilowatt hour consumption, in |
|
addition to the metering options in PURA § 39.916(f) shall also be |
|
provided with the additional option of interconnection with the |
|
electric utility through a single meter that runs forward and |
|
backward. Any net consumption for a given billing period shall be |
|
billed in accordance with the standard tariff applicable to the |
|
customer class to which the user of the qualifying facility's |
|
output belongs. Any production in excess of consumption for a given |
|
billing period shall be purchased in accordance with the provisions |
|
of the electric utility's rate schedule as approved by the |
|
commission in its most recent rate case. |
|
(e) An electric utility that purchases surplus generated |
|
electricity from a distributed renewable generation owner in |
|
accordance with this subsection shall purchase surplus generated |
|
electricity generated by the renewable generation owner at the cost |
|
of the electric utility as determined by commission rule, and: |
|
(1) the electric utility shall take reasonable steps |
|
to inform the distributed renewable generation owner of the amount |
|
of surplus electricity purchased as measured in kilowatt hours |
|
during the retail customers most recent billing cycle; and |
|
(2) the amount of any credit balance on a monthly bill |
|
of a retail electric customer with distributed renewable energy may |
|
be carried forward on the retail customer's bill until the credit |
|
exceeds $50 at which time the electric utility must provide a refund |
|
of the credit balance to the customer. |
|
Sec. 39.555 MARKETING OF ENERGY EFFICIENCY AND RENEWABLE |
|
ENERGY PROGRAMS. (a) an electric utility subject to this |
|
subchapter may directly market energy efficiency and renewable |
|
energy programs to retail electric customers within its service |
|
territory and provide rebate or incentive funds directly to its |
|
customers to promote or facilitate the success of the programs |
|
subject to Section 39.905. |
|
SECTION 2. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2011. |