A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to periodic rate adjustments by water and sewer utilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter F, Chapter 13, Water Code, is amended |
|
by adding Section 13.194 to read as follows: |
|
Sec. 13.194. RATE ADJUSTMENTS FOR INFRASTRUCTURE PROJECTS. |
|
(a) In this section, "infrastructure improvement project" means an |
|
engineering project to construct, improve, or renovate a facility |
|
used and useful for: |
|
(1) the production, transmission, storage, |
|
distribution, or provision of potable or recycled water to the |
|
public; or |
|
(2) the collection, transportation, treatment, or |
|
disposal of sewage. |
|
(b) The commission, on the petition of a water and sewer |
|
utility, may approve a tariff or rate schedule that includes an |
|
adjustable rate or charge designed to increase or decrease, without |
|
the necessity of a contested case hearing, in proportion to the |
|
utility's amount of invested capital committed to infrastructure |
|
improvement projects to serve the utility's certificated service |
|
area. |
|
(c) To be eligible for a tariff or rate schedule under this |
|
section, or to increase or decrease an adjustable rate or charge |
|
approved as part of a tariff or rate schedule under this section, a |
|
water and sewer utility, not later than the 60th day before the |
|
proposed effective date, as applicable, of the tariff or rate |
|
schedule or of the increase or decrease of the adjustable rate or |
|
charge, must file with the executive director for review and |
|
approval a written petition that contains: |
|
(1) the amount of the proposed rate or charge; |
|
(2) the proposed implementation date for the proposed |
|
rate or charge; |
|
(3) a list of completed, eligible capital projects and |
|
the depreciation and return on investment on the projects for which |
|
the utility seeks reimbursement through the proposed rate or |
|
charge; |
|
(4) a computation of the projected total annual |
|
increase or decrease in revenue expected from the proposed rate or |
|
charge; and |
|
(5) the cumulative annual amount the utility expects |
|
to recover from the proposed rate or charge. |
|
(d) The executive director may not approve a rate or charge |
|
that allows a water and sewer utility to recover more than five |
|
percent of the utility's annual revenue. If a water and sewer |
|
utility regionalizes or consolidates into a single tariff under |
|
Section 13.145, the executive director may not approve a rate or |
|
charge that exceeds five percent of the utility's annual revenue |
|
from the region or single tariff. |
|
(e) A water and sewer utility may not implement a rate or |
|
charge or an increase in a rate or charge under this section more |
|
than once in a calendar year. |
|
(f) The commission by rule shall require the water and sewer |
|
utility: |
|
(1) to apply a rate or charge to each customer included |
|
in the utility's tariff or rate schedule; and |
|
(2) to provide to each customer written notice of the |
|
rate or charge on the initial tariff filing that proposes to |
|
implement the rate or charge. |
|
(g) A water and sewer utility may not recover expenses |
|
related to the maintenance and operation of an infrastructure |
|
improvement project through a rate or charge under this section. |
|
(h) A rate or charge approved by the commission under this |
|
section is subject to a true-up or reconciliation at the water and |
|
sewer utility's next general rate case under Section 13.187. |
|
(i) A water and sewer utility that has filed four petitions |
|
under this section since the utility's most recent general rate |
|
case under Section 13.187 may not file another petition until after |
|
the utility's next general rate case under that section. |
|
(j) Notwithstanding any other provision of this code, the |
|
implementation of a utility facilities construction and |
|
improvement charge or an increase in a utility facilities |
|
construction and improvement charge is not subject to a contested |
|
case hearing. |
|
(k) The commission shall adopt rules to implement this |
|
section. |
|
(l) A regulatory authority other than the commission shall |
|
allow a water and sewer utility to use an adjustable rate or charge |
|
in a manner consistent with this section and rules adopted under |
|
this section. |
|
SECTION 2. The commission or regulatory authority shall |
|
adopt all rules necessary to implement Section 13.194, Water Code, |
|
as added by this Act, not later than September 1, 2015. |
|
SECTION 3. This Act takes effect September 1, 2013. |