A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the duties of excavators to notify operators of the |
|
location of planned excavations and the duties of operators to mark |
|
the location of underground facilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 251.151(a), Utilities Code, is amended |
|
to read as follows: |
|
(a) Except as provided by Sections 251.155 and 251.156, a |
|
person who intends to excavate shall notify a notification center |
|
not earlier than the 14th day before the date the excavation is to |
|
begin or later than the 48th hour before the time the excavation is |
|
to begin, excluding Saturdays, Sundays, and legal holidays. For a |
|
planned excavation activity that will extend to a location that is |
|
one-quarter mile or more from the beginning point of an excavation |
|
project, each one-quarter mile portion of the planned excavation |
|
project is considered a separate excavation and the excavator shall |
|
provide a separate notification under this section for each |
|
excavation. |
|
SECTION 2. Section 251.152, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 251.152. INFORMATION INCLUDED IN NOTICE. The |
|
excavator shall include in the notice required under Section |
|
251.151: |
|
(1) the name of the person serving the notice; |
|
(2) the location of the proposed area of excavation |
|
and the location of the beginning point of the proposed excavation, |
|
including: |
|
(A) the street address, if available, and the |
|
location of the excavation at the street address; or |
|
(B) if there is no street address, an accurate |
|
description of the excavation area using any available designations |
|
such as the closest street, road, or intersection; |
|
(3) the name, address, and telephone number of the |
|
excavator or the excavator's company; |
|
(4) the excavator's field telephone number, if one is |
|
available; |
|
(5) a telephone facsimile number, e-mail address, or |
|
another electronic number or address approved by the board to which |
|
an operator may send the notification required by Section |
|
251.157(d); |
|
(6) the starting date and time and the anticipated |
|
completion date of excavation; and |
|
(7) a statement as to whether explosives will be used. |
|
SECTION 3. This Act takes effect September 1, 2015. |