BILL ANALYSIS |
C.S.H.B. 3913 |
By: Shine |
Urban Affairs |
Committee Report (Substituted) |
BACKGROUND AND PURPOSE
Interested parties maintain that the amount of a public works contract payment that is retained to secure performance of the contract should be more adequately addressed in statute to avoid excessive retainage that places a significant financial burden on a contractor's ability to pay subcontractors and suppliers and realize a profit. C.S.H.B. 3913 seeks to achieve this goal by setting out provisions relating to the retainage withheld by a governmental entity and by a prime contractor or subcontractor in connection with a public works contract.
|
||||||||||||||
CRIMINAL JUSTICE IMPACT
It is the committee's opinion that this bill does not expressly create a criminal offense, increase the punishment for an existing criminal offense or category of offenses, or change the eligibility of a person for community supervision, parole, or mandatory supervision.
|
||||||||||||||
RULEMAKING AUTHORITY
It is the committee's opinion that this bill does not expressly grant any additional rulemaking authority to a state officer, department, agency, or institution.
|
||||||||||||||
ANALYSIS
C.S.H.B. 3913 amends the Government Code to require a governmental entity to include in each public works contract to which the governmental entity is a party a provision that establishes, for the project that is the subject of the contract, the circumstances under which the project will be considered substantially complete and if retainage will be released on substantial completion of the project and, if so, the percentage of the amount of retainage that will be released on substantial completion. The bill replaces the requirement that a governmental entity deposit in an interest-bearing account the retainage of a public works contract that provides for retainage of more than five percent of the periodic contract payment with a requirement that a governmental entity deposit in such an account the retainage of a periodic contract payment of a public works contract and provides for the payment of the retainage remaining in the account to the prime contractor on completion of the contract. The bill prohibits a governmental entity that has entered into a public works contract that has a total value of $1 million or more from withholding retainage in an amount that exceeds five percent of the contract price and authorizes such a governmental entity to release retainage for completed portions of the work and to release a portion of the retainage on substantial completion of the project. The bill prohibits a governmental entity from withholding retainage after completion of the contract by the prime contractor, including during any warranty period after completion of the contract, or withholding retainage for the purpose of requiring the prime contractor, after completion of the contract, to perform work on manufactured goods or systems that were specified by the designer of record and properly installed by the contractor.
C.S.H.B. 3913 includes in the definition of "retainage" under provisions relating to retained public works contract payments the part of a payment under a public works contract withheld by a prime contractor or subcontractor to secure performance of any work that is required of the prime contractor under the contract that a subcontractor contracts to perform. The bill prohibits a prime contractor who enters into a subcontract that has a total value of at least $250,000 for the purpose of fulfilling an obligation of the prime contractor under a public works contract from withholding from a subcontractor a greater percentage of retainage than the percentage being withheld from the prime contractor by the governmental entity under the public works contract and prohibits a subcontractor who enters into a contract with another subcontractor to provide labor or materials under the public works contract from withholding from that subcontractor a greater percentage of retainage than the percentage that may be withheld from the subcontractor by the prime contractor.
C.S.H.B. 3913 requires a prime contractor who receives a payment of interest earned on retainage to pay to any subcontractor of the prime contractor from whom the prime contractor has withheld retainage under a public works contract a proportionate share of the interest the prime contractor receives in an amount based on a specified ratio. The bill requires a subcontractor who receives a payment of interest to pay to any contracting subcontractor from whom the subcontractor withheld retainage a proportionate share of the interest the subcontractor receives in an amount based on a specified ratio.
|
||||||||||||||
EFFECTIVE DATE
On passage, or, if the bill does not receive the necessary vote, September 1, 2017.
|
||||||||||||||
COMPARISON OF ORIGINAL AND SUBSTITUTE
While C.S.H.B. 3913 may differ from the original in minor or nonsubstantive ways, the following comparison is organized and formatted in a manner that indicates the substantial differences between the introduced and committee substitute versions of the bill.
|
||||||||||||||
|