A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the partition and transfer of a geographic portion of |
|
service area certificate of convenience and necessity by |
|
municipally owned electric utility systems. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter C, Utilities Code, is amended by |
|
adding Section 37.103 to read as follows: |
|
Sec. 37.103. PARTITION AND TRANSFER OF CERTIFICATE FOR |
|
CERTAIN UTILITIES. (a) This section applies only to a municipally |
|
owned electric utility system with 400,000 or more customers that |
|
is owned by a municipality with a population of less than 850,000. |
|
(b) A municipally owned electric utility system shall |
|
identify and transfer to a nonprofit electric cooperative created |
|
under Chapter 161 that serves more than 64,000 members the part of |
|
the system's certificated service area that is not in the |
|
certificated service area of another utility or dually certificated |
|
and that is: |
|
(1) outside the owning municipality's city limits; and |
|
(2) located inside the county in which the owning |
|
municipality is primarily located. |
|
(c) The utility system shall sell to the electric |
|
cooperative that will provide service to the partitioned area at |
|
net book value all of the system's electric distribution assets |
|
attributable to the transferred service area that are used to serve |
|
the area. Generation assets and transmission service facilities |
|
are not subject to sale under this subsection. |
|
(d) The commission shall: |
|
(1) review and approve the identification and transfer |
|
of the service area to ensure compliance with this section; |
|
(2) as necessary, amend or issue certificates of |
|
convenience and necessity to implement the transfer of the service |
|
area; and |
|
(3) identify, oversee, and approve the sale of assets. |
|
(e) This section expires September 1, 2019. |
|
SECTION 2. The Public Utility Commission of Texas shall |
|
ensure that the transfer and sales required by Section 37.103, |
|
Utilities Code, as added by this Act, shall be completed not later |
|
than September 1, 2018. |
|