(a) The contractor who is awarded a contract by a public |
|
body or a subcontractor of the contractor: |
|
(1) shall pay not less than the rates determined under |
|
Section 2258.022 to a worker employed by it in the execution of the |
|
contract; and |
|
(2) may not improperly classify a worker employed by |
|
it in the execution of the contract as an independent contractor in |
|
order to avoid paying the worker under Subdivision (1). |
|
(b) A contractor or subcontractor who violates this section |
|
shall pay to the state or a political subdivision of the state on |
|
whose behalf the contract is made $90 [, $60] for: |
|
(1) each worker employed for each calendar day or part |
|
of the day that the worker is paid less than the wage rates |
|
stipulated in the contract; or |
|
(2) each worker misclassified as an independent |
|
contractor for each calendar day or part of the day that the worker |
|
is misclassified. |
|
(b-1) A public body awarding a contract shall specify the |
|
[this] penalty provided for by Subsection (b) in the contract. |
|
(d) The public body shall: |
|
(1) audit a public work contract to ensure compliance |
|
with this chapter: |
|
(A) throughout the term of the contract; and |
|
(B) not later than the 30th day before the date |
|
the work is scheduled to be completed on the contract; and |
|
(2) use any money collected under this section to |
|
offset the costs incurred in the administration of this chapter. |
|
(f) The payment requirement under Subsection (a)(1) may |
|
only be satisfied by payment to the employee in the form of per diem |
|
wages. |
|
SECTION 2. The change in law made by this Act applies only |
|
to a public work contract entered into on or after the effective |
|
date of this Act. A public work contract entered into before the |
|
effective date of this Act is governed by the law in effect on the |
|
date the contract was entered into, and the former law is continued |
|
in effect for that purpose. |
|
SECTION 3. This Act takes effect September 1, 2017. |