AN ACT
|
|
relating to periodic rate adjustment by and to certain transactions |
|
involving electric utilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter D, Chapter 36, Utilities Code, is |
|
amended by adding Section 36.157 to read as follows: |
|
Sec. 36.157. RATE REVIEW SCHEDULE. (a) This section |
|
applies only to an electric utility, other than a river authority, |
|
that operates solely inside ERCOT. |
|
(b) Notwithstanding any other provision of this title, not |
|
later than June 1, 2018, the commission by rule shall establish a |
|
schedule that requires an electric utility to make periodic filings |
|
with the commission to modify or review base rates charged by the |
|
electric utility. The schedule may be established on the basis of: |
|
(1) the period since the commission entered the |
|
commission's final order in the electric utility's most recent base |
|
rate proceeding; |
|
(2) whether the electric utility has earned materially |
|
more than the utility's authorized rate of return on equity as |
|
demonstrated by earnings monitoring reports; or |
|
(3) other criteria that the commission determines is |
|
in the public interest. |
|
(c) The commission shall extend the date for the proceeding |
|
required by Subsection (b) by one year on a year-to-year basis if, |
|
180 days before the date the proceeding is required, the electric |
|
utility's most recent earnings monitoring report shows the electric |
|
utility is earning, on a weather-normalized basis, less than 50 |
|
basis points above: |
|
(1) for a transmission and distribution utility, the |
|
average of the most recent commission-approved rate of return on |
|
equity for each transmission and distribution utility with 175,000 |
|
or more metered customers; and |
|
(2) for a transmission-only utility, the average of |
|
the most recent commission-approved rate of return on equity for |
|
each transmission-only utility. |
|
(d) The commission may extend the date for the proceeding |
|
required by Subsection (b) for good cause shown or because of |
|
resource constraints of the commission. |
|
(e) This section does not limit the ability of a regulatory |
|
authority to initiate a base rate proceeding at any time under this |
|
title. |
|
SECTION 2. Section 36.210, Utilities Code, is amended by |
|
amending Subsection (d) and adding Subsection (d-1) to read as |
|
follows: |
|
(d) Except as provided by Subsection (d-1), an [An] electric |
|
utility may adjust the utility's rates under this section not more |
|
than once per year and not more than four times between |
|
comprehensive base rate proceedings. |
|
(d-1) For an electric utility subject to Section 36.157, |
|
beginning on the effective date of the schedule adopted by the |
|
commission under Section 36.157(b), the electric utility may adjust |
|
the utility's rates under this section more than four times between |
|
base rate proceedings. |
|
SECTION 3. Section 39.262(m), Utilities Code, is amended to |
|
read as follows: |
|
(m) The commission shall approve a transaction under |
|
Subsection (l) if the commission finds that the transaction is in |
|
the public interest. In making its determination, the commission |
|
shall consider whether the transaction will adversely affect the |
|
reliability of service, availability of service, or cost of service |
|
of the electric utility or transmission and distribution utility. |
|
The commission shall make the determination concerning a |
|
transaction under this subsection not later than the 180th day |
|
after the date the commission receives the relevant report. The |
|
commission may extend the deadline provided by this subsection for |
|
not more than 60 days if the commission determines the extension is |
|
needed to evaluate additional information, to consider actions |
|
taken by other jurisdictions concerning the transaction, to provide |
|
for administrative efficiency, or for other good cause. If the |
|
commission has not made a determination before the expiration of |
|
the deadline provided by or extended under this subsection [181st
|
|
day after that date], the transaction is considered approved. |
|
SECTION 4. Section 39.915(b), Utilities Code, is amended to |
|
read as follows: |
|
(b) The commission shall approve a transaction under |
|
Subsection (a) if the commission finds that the transaction is in |
|
the public interest. In making its determination, the commission |
|
shall consider whether the transaction will adversely affect the |
|
reliability of service, availability of service, or cost of service |
|
of the electric utility or transmission and distribution utility. |
|
The commission shall make the determination concerning a |
|
transaction under this subsection not later than the 180th day |
|
after the date the commission receives the relevant report. The |
|
commission may extend the deadline provided by this subsection for |
|
not more than 60 days if the commission determines the extension is |
|
needed to evaluate additional information, to consider actions |
|
taken by other jurisdictions concerning the transaction, to provide |
|
for administrative efficiency, or for other good cause. If the |
|
commission has not made a determination before the expiration of |
|
the deadline provided by or extended under this subsection [181st
|
|
day after that date], the transaction is considered approved. |
|
SECTION 5. Sections 36.210(h), (h-1), and (i), Utilities |
|
Code, are repealed. |
|
SECTION 6. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2017. |
|
|
|
|
|
|
|
|
______________________________ |
______________________________ |
|
President of the Senate |
Speaker of the House |
|
|
I hereby certify that S.B. No. 735 passed the Senate on |
|
April 19, 2017, by the following vote: Yeas 31, Nays 0. |
|
|
|
|
______________________________ |
|
Secretary of the Senate |
|
|
I hereby certify that S.B. No. 735 passed the House on |
|
May 17, 2017, by the following vote: Yeas 142, Nays 1, two |
|
present not voting. |
|
|
|
|
______________________________ |
|
Chief Clerk of the House |
|
|
|
|
|
Approved: |
|
|
|
______________________________ |
|
Date |
|
|
|
|
|
______________________________ |
|
Governor |