A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the removal of wind power facilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. The Utilities Code is amended by adding Title 6 |
|
to read as follows: |
|
TITLE 6. WIND POWER |
|
CHAPTER 301. WIND POWER FACILITY AGREEMENTS |
|
Sec. 301.0001. DEFINITIONS. In this chapter: |
|
(1) "Grantee" means a person who: |
|
(A) leases property from a landowner; and |
|
(B) operates a wind power facility on the |
|
property. |
|
(2) "Wind power facility" includes: |
|
(A) a wind turbine generator; and |
|
(B) a facility or equipment used to support the |
|
operation of a wind turbine generator, including an underground or |
|
aboveground electrical transmission or communications line, an |
|
electric transformer, a battery storage facility, an energy storage |
|
facility, telecommunications equipment, a road, a meteorological |
|
tower with wind measurement equipment, or a maintenance yard. |
|
(3) "Wind power facility agreement" means a lease |
|
agreement between a grantee and a landowner that authorizes the |
|
grantee to operate a wind power facility on the leased property. |
|
Sec. 301.0002. WAIVER VOID; REMEDIES. (a) A provision of a |
|
wind power facility agreement that purports to waive a right or |
|
exempt a grantee from a liability or duty established by this |
|
chapter is void. |
|
(b) A person who is harmed by a violation of this chapter is |
|
entitled to appropriate injunctive relief to prevent further |
|
violation of this chapter. |
|
(c) The provisions of this section are not exclusive. The |
|
remedies provided in this section are in addition to any other |
|
procedures or remedies provided by other law. |
|
Sec. 301.0003. REQUIRED AGREEMENT PROVISIONS ON FACILITY |
|
REMOVAL. (a) A wind power facility agreement must provide that the |
|
grantee is responsible for removing the grantee's wind power |
|
facilities from the landowner's property and that the grantee |
|
shall, in accordance with any other applicable laws or regulations, |
|
safely: |
|
(1) clear, clean, and remove from the property: |
|
(A) each wind turbine generator, including |
|
towers and pad-mount transformers; |
|
(B) all liquids, greases, or similar substances |
|
contained in a wind turbine generator; |
|
(C) each substation; and |
|
(D) all liquids, greases, or similar substances |
|
contained in a substation; |
|
(2) for each tower foundation and pad-mount |
|
transformer foundation installed in the ground: |
|
(A) clear, clean, and remove the foundation from |
|
the ground at least three feet from the grade of the land affected |
|
by the foundation; and |
|
(B) ensure that each hole or cavity created in |
|
the ground by the removal is filled with topsoil of the same type or |
|
a similar type as the predominant topsoil found on the property; |
|
(3) for each buried cable, including power, |
|
fiber-optic, and communications cables, installed in the ground: |
|
(A) clear, clean, and remove the cable from the |
|
ground at least three feet below the grade of the land affected by |
|
the cable; and |
|
(B) ensure that each hole or cavity created in |
|
the ground by the removal is filled with topsoil of the same type or |
|
a similar type as the predominant topsoil found on the property; and |
|
(4) clear, clean, and remove from the property each |
|
overhead power or communications line installed by the grantee on |
|
the property. |
|
(b) The agreement must provide that, at the request of the |
|
landowner, the grantee shall: |
|
(1) clear, clean, and remove each road constructed by |
|
the grantee on the property; and |
|
(2) ensure that each hole or cavity created in the |
|
ground by the removal is filled with topsoil of the same type or a |
|
similar type as the predominant topsoil found on the property. |
|
(c) The agreement must provide that, at the request of the |
|
landowner, if reasonable, the grantee shall: |
|
(1) remove from the property all rocks over 12 inches |
|
in diameter excavated during the decommissioning or removal |
|
process; |
|
(2) return the property to a tillable state using |
|
scarification, V-rip, or disc methods, as appropriate; and |
|
(3) ensure that: |
|
(A) each hole or cavity created in the ground by |
|
the removal is filled with topsoil of the same type or a similar |
|
type as the predominant topsoil found on the property; and |
|
(B) the surface is returned as near as reasonably |
|
possible to the same condition as before the grantee dug holes or |
|
cavities, including by reseeding pastureland with native grasses |
|
prescribed by an appropriate governmental agency, if any. |
|
(d) The agreement may not authorize the landowner to make a |
|
request under Subsection (b) or (c) after the first anniversary of |
|
the date on which the wind power facility is no longer capable of |
|
generating electricity in commercial quantities. |
|
Sec. 301.0004. REQUIRED AGREEMENT PROVISIONS ON REMOVAL |
|
BOND. (a) A wind power facility agreement must provide that the |
|
grantee shall obtain and deliver to the landowner a bond or other |
|
form of financial assurance, such as a letter of credit, an escrow |
|
account, or other form of financial assurance acceptable to the |
|
landowner, that conforms to the requirements of this section to |
|
secure the performance of the grantee's obligation to remove the |
|
grantee's wind power facilities located on the landowner's property |
|
as described by Section 301.0003. |
|
(b) The amount of the bond or other financial assurance must |
|
be at least equal to the estimated amount by which the cost of |
|
removing the wind power facilities from the landowner's property |
|
and restoring the property to as near as reasonably possible the |
|
condition of the property as of the date the agreement begins |
|
exceeds the salvage value of the wind power facilities, less any |
|
portion of the value of the wind power facilities pledged to secure |
|
outstanding debt. |
|
(c) The agreement must provide that: |
|
(1) the estimated cost of removing the wind power |
|
facilities from the landowner's property and restoring the property |
|
to as near as reasonably possible the condition of the property as |
|
of the date the agreement begins and the estimated salvage value of |
|
the wind power facilities must be determined by an independent, |
|
third-party professional engineer licensed in this state; |
|
(2) the grantee must deliver to the landowner an |
|
updated estimate, prepared by an independent, third-party |
|
professional engineer licensed in this state, of the cost of |
|
removal and the salvage value at least once every five years for the |
|
remainder of the term of the agreement; and |
|
(3) the grantee is responsible for ensuring that the |
|
amount of the bond or other financial assurance remains sufficient |
|
to cover the amount required by Subsection (b), consistent with the |
|
estimates required by this subsection. |
|
(d) The grantee is responsible for the costs of obtaining a |
|
bond or other financial assurance described by this section and |
|
costs of determining the estimated removal costs and salvage value. |
|
(e) The agreement must provide that the grantee shall |
|
deliver the bond or other financial assurance not later than the |
|
earlier of: |
|
(1) the date the wind power facility agreement is |
|
terminated; or |
|
(2) the 10th anniversary of the commercial operations |
|
date of the wind power facilities located on the landowner's leased |
|
property. |
|
(f) For purposes of this section, "commercial operations |
|
date" means the date on which the wind power facilities are approved |
|
for participation in market operations by a regional transmission |
|
organization and does not include the generation of electrical |
|
energy or other operations conducted before that date for purposes |
|
of maintenance and testing. |
|
(g) The grantee may not cancel a bond or other financial |
|
assurance before the date the grantee has completed the grantee's |
|
obligation to remove the grantee's wind power facilities located on |
|
the landowner's property in the manner provided by this chapter, |
|
unless the grantee provides the landowner with a replacement bond |
|
or replacement financial assurance at the time of or before the |
|
cancellation. In the event of a transfer of ownership of the |
|
grantee's wind power facilities, the financial security provided by |
|
the grantee shall remain in place until the date evidence of |
|
financial security meeting the requirements of this chapter is |
|
provided to the landowner. |
|
SECTION 2. Chapter 301, Utilities Code, as added by this |
|
Act, applies only to a wind power facility agreement entered into on |
|
or after the effective date of this Act. A wind power facility |
|
agreement entered into before the effective date of this Act is |
|
governed by the law as it existed immediately before that date, and |
|
that law is continued in effect for that purpose. |
|
SECTION 3. This Act takes effect September 1, 2019. |