A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the regulation of aggregate production operations; |
|
requiring a permit; authorizing a fee. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. The heading to Subchapter B, Chapter 28A, Water |
|
Code, is amended to read as follows: |
|
SUBCHAPTER B. PERMIT [REGISTRATION] AND INSPECTION |
|
SECTION 2. Subchapter B, Chapter 28A, Water Code, is |
|
amended by adding Sections 28A.0525, 28A.0526, and 28A.0527 to read |
|
as follows: |
|
Sec. 28A.0525. PERMIT REQUIRED. (a) A person may not begin |
|
or conduct extraction activities at an aggregate production |
|
operation unless the responsible party has obtained a standard |
|
permit for the aggregate production operation from the commission |
|
under this section. |
|
(b) The commission by rule shall: |
|
(1) adopt a standard permit for aggregate production |
|
operations; |
|
(2) prescribe an application for a standard permit |
|
under this section; and |
|
(3) provide for the issuance of a standard permit |
|
under this section. |
|
(c) A permit does not become a vested right in the permit |
|
holder. |
|
(d) A permit may be issued under this section for a term set |
|
by the board not to exceed six years from the date of issuance. |
|
(e) The commission may charge fees for the issuance of |
|
permits under this section in an amount sufficient to recover the |
|
costs of administering this chapter. |
|
Sec. 28A.0526. NOTICE AND HEARING. (a) Except as provided |
|
by Subsection (b), the notice and hearing provisions of Subchapter |
|
M, Chapter 5, Water Code, apply to an application under this section |
|
for a permit or a permit renewal. |
|
(b) A public hearing on an application for a permit or |
|
permit renewal issued under this section must be held in the |
|
municipality located closest to the proposed or existing aggregate |
|
production operation. |
|
Sec. 28A.0527. CERTAIN LOCATIONS RESTRICTED. (a) This |
|
section applies only to an aggregate production operation located: |
|
(1) in the Guadalupe River watershed according to the |
|
National Hydrography Dataset and the Watershed Boundary Dataset; |
|
and |
|
(2) west of the Canyon Lake Dam. |
|
(b) An aggregate production operation may not operate |
|
within 1500 feet of a navigable waterway. |
|
(c) An application for a permit to operate an aggregate |
|
production operation must include: |
|
(1) information satisfying criteria determined by the |
|
commission regarding: |
|
(A) slope gradients sufficient to minimize the |
|
potential for erosion and water quality degradation; |
|
(B) the potential for significant damage to |
|
important historical and cultural values or ecological systems; |
|
(C) the effect on: |
|
(i) natural resources, including aquifers |
|
and aquifer recharge zones; |
|
(ii) agricultural activity; and |
|
(iii) areas subject to frequent flooding or |
|
geological events; and |
|
(D) concerns relevant to the substantial |
|
endangerment of life or property; |
|
(2) a plan for the: |
|
(A) control of water drainage and accumulation |
|
that prevents erosion and damage to fish or wildlife habitat; and |
|
(B) reclamation and revegetation of the quarried |
|
land consistent with best management practices adopted by the |
|
commission; and |
|
(3) evidence of sufficient financial assurance to |
|
cover the remediation of potential negative effects on the |
|
Guadalupe River and surrounding areas, as determined by commission |
|
rule. |
|
SECTION 3. Section 28A.053(a), Water Code, is amended to |
|
read as follows: |
|
(a) The commission shall inspect each active permitted |
|
aggregate production operation in this state for compliance with |
|
applicable permit conditions and environmental laws and rules under |
|
the jurisdiction of the commission at least once every three years. |
|
SECTION 4. The heading to Subchapter C, Chapter 28A, Water |
|
Code, is amended to read as follows: |
|
SUBCHAPTER C. [FEES AND] ENFORCEMENT |
|
SECTION 5. Section 28A.102, Water Code, is amended to read |
|
as follows: |
|
Sec. 28A.102. PENALTY. The commission may assess a penalty |
|
of not less than $5,000 and not more than $10,000 for each year in |
|
which an aggregate production operation operates without a permit |
|
issued [being registered] under this chapter. The total penalty |
|
under this section may not exceed $25,000 for an aggregate |
|
production operation that is operated in three or more years |
|
without a permit [being registered]. |
|
SECTION 6. The following provisions of the Water Code are |
|
repealed: |
|
(1) Section 28A.051; |
|
(2) Section 28A.052; |
|
(3) Section 28A.054; and |
|
(4) Section 28A.101. |
|
SECTION 7. (a) Not later than March 1, 2020, the Texas |
|
Commission on Environmental Quality shall adopt rules to implement |
|
the changes in law made by this Act to Chapter 28A, Water Code. |
|
(b) Notwithstanding Section 28A.0525, Water Code, as added |
|
by this Act, a person beginning extraction activities at an |
|
aggregate production operation on or after the effective date of |
|
this Act is not required to hold a permit required by that section |
|
for the extraction activities until September 1, 2020. |
|
SECTION 8. The changes in law made by this Act apply only to |
|
an aggregate production operation at which extraction activities |
|
begin on or after the effective date of this Act. An aggregate |
|
production operation at which extraction activities began before |
|
the effective date of this Act is governed by the law in effect |
|
immediately before the effective date of this Act, and the former |
|
law is continued in effect for that purpose. |
|
SECTION 9. This Act takes effect September 1, 2019. |