|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to certificates of public convenience and necessity for |
|
certain transmission projects. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. The legislature finds that: |
|
(1) this state has long been a leader in energy policy |
|
that has delivered economic, electricity, and environmental |
|
benefits to millions of electricity consumers, businesses, |
|
state-owned lands, and landowners; |
|
(2) this state continues to experience population, |
|
business, industrial, and manufacturing growth that increases the |
|
need for reliable, low-cost electricity; |
|
(3) the ERCOT electric power grid is experiencing |
|
congestion, constraint, and curtailment that are economically |
|
undesirable; |
|
(4) the ERCOT electric power grid is experiencing load |
|
growth management challenges; |
|
(5) while this state does not import large amounts of |
|
electricity, working to ensure that this state's electricity needs |
|
are met as fully as possible from in-state resources is of strategic |
|
interest to the legislature; |
|
(6) all of the electric power industry's available |
|
power generation resources, including its wind and solar |
|
generation, natural gas-fired generation, energy storage, and |
|
transmission components, can play a substantial role in this |
|
state's economic recovery; |
|
(7) this state's oil and natural gas industries |
|
continue to grow and prosper, and those industries require low-cost |
|
electricity and a reliable electric power grid to thrive; and |
|
(8) to attract new capital projects to this state, |
|
create jobs, promote substantial new economic development, ensure a |
|
reliable and stable electric power grid that is powered by in-state |
|
resources, and keep this state as a leader on energy policy in the |
|
United States, a timely and targeted expansion of this state's |
|
electric transmission system is necessary to enhance the |
|
reliability of the system. |
|
SECTION 2. Section 37.0541, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 37.0541. CONSOLIDATION OF CERTAIN PROCEEDINGS. The |
|
commission shall consolidate the proceeding on an application to |
|
obtain or amend a certificate of convenience and necessity for the |
|
construction of a transmission line with the proceeding on another |
|
application to obtain or amend a certificate of convenience and |
|
necessity for the construction of a transmission line if it is |
|
apparent from the applications or a motion to intervene in either |
|
proceeding that the transmission lines that are the subject of the |
|
separate proceedings share a common point of interconnection. [This |
|
section does not apply to a proceeding on an application for a |
|
certificate of convenience and necessity for a transmission line to |
|
serve a competitive renewable energy zone as part of a plan |
|
developed by the commission under Section 39.904(g)(2).] |
|
SECTION 3. Section 37.056, Utilities Code, is amended by |
|
adding Subsections (a-1), (d-1), (d-2), and (d-3) and amending |
|
Subsection (d) to read as follows: |
|
(a-1) In this section: |
|
(1) "Interzonal" means involving more than one ERCOT |
|
load zone. |
|
(2) "Intrazonal" means involving a single ERCOT load |
|
zone. |
|
(d) The commission by rule shall establish criteria, in |
|
addition to the criteria described by Subsection (c), for granting |
|
a certificate for a transmission project that serves the ERCOT |
|
power region and[,] that is not necessary to meet state or federal |
|
reliability standards[, and that does not serve a competitive |
|
renewable energy zone]. |
|
(d-1) Except as provided by Subsection (d-2), an |
|
application for a certificate described by Subsection (d) [The |
|
criteria] must include a comparison of the levelized estimated cost |
|
of the transmission project and the levelized estimated cost |
|
savings and economic benefits that may result from the |
|
[transmission] project. The commission shall include with the |
|
commission's decision to grant or deny the certificate the |
|
commission's findings on the comparison. The comparison must |
|
account for: |
|
(1) the probable improvement of service and reduction |
|
of costs for consumers that may be realized from the project; |
|
(2) an estimated value of the reduction in interzonal |
|
and intrazonal constraint and congestion costs and interzonal and |
|
intrazonal curtailment costs that may be realized from the project; |
|
(3) an estimation of reduced transmission losses that |
|
may be realized from the project; |
|
(4) an assessment of whether the project will provide |
|
improved access to ERCOT for new generation facilities and the |
|
benefits that improved access could provide to generation |
|
facilities, industrial load, and the ERCOT market; |
|
(5) an estimation of reduced future transmission |
|
investment costs that may be realized from the project; |
|
(6) an estimation of costs of projects described by |
|
Subsection (d-2) that may be avoided as a result of the project; and |
|
(7) an estimation of direct economic benefits that may |
|
be realized from the construction of the project [The commission |
|
shall include with its decision on an application for a certificate |
|
to which this subsection applies findings on the criteria]. |
|
(d-2) If an application does not include a comparison |
|
described by Subsection (d-1), the commission may not grant a |
|
certificate for a project described by Subsection (d) unless the |
|
commission finds that the project is needed to support a reliable |
|
and adequate transmission network, to facilitate wholesale |
|
competition, or to minimize curtailments due to interzonal |
|
constraints and intrazonal congestion. |
|
(d-3) Not less than once per year, the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region shall identify transmission projects that will meet |
|
commission findings under Subsection (d-2). |
|
SECTION 4. Section 39.904(k), Utilities Code, is amended to |
|
read as follows: |
|
(k) The commission and the independent organization |
|
certified for ERCOT shall study the need for increased transmission |
|
and generation capacity throughout this state and report to the |
|
legislature the results of the study and any recommendations for |
|
legislation. The report must be filed with the legislature not |
|
later than December 31 of each even-numbered year [and may be filed |
|
as a part of the report required by Subsection (j)]. |
|
SECTION 5. Subchapter Z, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.918 to read as follows: |
|
Sec. 39.918. CRITICAL DESIGNATION TRANSMISSION |
|
INFRASTRUCTURE PROJECTS. (a) In this section: |
|
(1) "Interzonal" means involving more than one ERCOT |
|
load zone. |
|
(2) "Intrazonal" means involving a single ERCOT load |
|
zone. |
|
(b) Not later than December 30, 2021, the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region shall: |
|
(1) identify, in consultation with the commission, |
|
critical designation transmission infrastructure projects and the |
|
electric utilities or transmission and distribution utilities that |
|
will construct and operate the projects in a manner consistent with |
|
Section 37.056; and |
|
(2) submit a written description of each project to |
|
the commission. |
|
(c) Projects identified under Subsection (b) must |
|
facilitate a timely and targeted expansion of the electric power |
|
grid in ERCOT for the purposes of: |
|
(1) resolving existing interzonal and intrazonal |
|
transmission constraints, congestion, or curtailments, including |
|
generic transmission constraints; and |
|
(2) ensuring the future reliability of the ERCOT |
|
electric power grid. |
|
(d) To the extent practicable, projects identified under |
|
Subsection (b) should: |
|
(1) be cost-effective and designed to transmit high |
|
volumes of electricity in and across ERCOT load zones efficiently; |
|
(2) minimize the need for the acquisition of new |
|
rights-of-way by replacing aging infrastructure or following |
|
routes that align with existing rights-of-way or existing |
|
transmission infrastructure; |
|
(3) minimize interzonal constraints and intrazonal |
|
congestion during construction activities; |
|
(4) be designed to accommodate new solutions, |
|
including higher voltages, if the independent organization |
|
determines that new solutions are required; and |
|
(5) be designed to significantly reduce present or |
|
expected future interzonal constraints and intrazonal congestion. |
|
(e) The independent organization certified under Section |
|
39.151 for the ERCOT power region shall identify as a critical |
|
designation transmission infrastructure project under Subsection |
|
(b) a project addressing an interzonal constraint or intrazonal |
|
congestion in an area if: |
|
(1) the constraint or congestion has been present for |
|
three years or longer; and |
|
(2) the area has experienced constraint or congestion |
|
costs greater than or equal to $100 million per year in each of the |
|
previous three years. |
|
(f) The independent organization certified under Section |
|
39.151 for the ERCOT power region may consult with the independent |
|
organization's market participant segments and other stakeholders |
|
to identify projects under Subsection (b) that could facilitate: |
|
(1) the growth of the economy of this state; or |
|
(2) oil and gas, commercial, and industrial |
|
development that could provide substantial new tax revenue, |
|
landowner income, or new jobs in this state. |
|
(g) Not later than the 450th day after the date that the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region submits a written description of a project to the |
|
commission under Subsection (b), the utility that will construct |
|
and operate the project shall submit to the commission an |
|
application for a certificate of public convenience and necessity |
|
for the project. |
|
(h) In considering an application for a certificate of |
|
public convenience and necessity for a project identified under |
|
Subsection (b), the commission is not required to consider the |
|
factors provided by Sections 37.056(c)(1) and (2). The commission |
|
shall consider all factors provided by Section 37.056, including |
|
Sections 37.056(c)(1) and (2), for a project not identified under |
|
Subsection (b). |
|
(i) If the commission issues a certificate of public |
|
convenience and necessity for a project identified under Subsection |
|
(b), the commission shall find that the project is used and useful |
|
to the utility in providing service for purposes of this section, |
|
prudent, and includable in the rate base, regardless of the extent |
|
of the utility's actual use of the project. |
|
(j) Transmission service that is facilitated through a |
|
project identified under Subsection (b) must be provided in a |
|
manner consistent with Subchapter A, Chapter 35. |
|
(k) This section expires September 1, 2030. |
|
SECTION 6. Sections 39.904(g), (h), (i), and (j), Utilities |
|
Code, are repealed. |
|
SECTION 7. The changes in law made by this Act apply only to |
|
a proceeding affecting a certificate of public convenience and |
|
necessity that commences on or after the effective date of this Act. |
|
A proceeding affecting a certificate of public convenience and |
|
necessity that commenced before the effective date of this Act is |
|
governed by the law in effect on the date the proceeding is |
|
commenced, and that law is continued in effect for that purpose. |
|
SECTION 8. The recovery of a transmission facility |
|
investment made by an electric utility to serve a competitive |
|
renewable energy zone is governed by the law in effect on the date |
|
the facility is placed in service, regardless of whether the |
|
facility is completed before, on, or after the effective date of |
|
this Act, and that law is continued in effect for that purpose. |
|
SECTION 9. This Act takes effect September 1, 2021. |