87R19140 CXP-F
 
  By: Goldman H.B. No. 3916
 
  Substitute the following for H.B. No. 3916:
 
  By:  Paddie C.S.H.B. No. 3916
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the interconnection and operation of certain
  distributed electric generation facilities.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 39.002, Utilities Code, is amended to
  read as follows:
         Sec. 39.002.  APPLICABILITY. This chapter, other than
  Sections 39.1516, 39.155, 39.157(e), 39.203, 39.904, 39.9051,
  39.9052, [and] 39.914(e), and 39.9161, does not apply to a
  municipally owned utility or an electric cooperative. Sections
  39.157(e), 39.203, and 39.904, however, apply only to a municipally
  owned utility or an electric cooperative that is offering customer
  choice. If there is a conflict between the specific provisions of
  this chapter and any other provisions of this title, except for
  Chapters 40 and 41, the provisions of this chapter control.
         SECTION 2.  Subchapter Z, Chapter 39, Utilities Code, is
  amended by adding Section 39.9161 to read as follows:
         Sec. 39.9161.  INTERCONNECTION AND OPERATION OF CERTAIN
  DISTRIBUTED GENERATION FACILITIES. (a) In this section:
               (1)  "Distributed generation facility" means a
  facility installed on the customer's side of the meter:
                     (A)  with a nameplate capacity of at least 250
  kilowatts and not more than 2,500 kilowatts; and
                     (B)  that is capable of providing backup or
  supplementary power to the customer's premises.
               (2)  "Electric utility" includes an electric utility, a
  municipally owned utility, and an electric cooperative.
         (b)  A person who owns or operates a distributed generation
  facility in the ERCOT power region may sell electric power
  generated by the distributed generation facility:
               (1)  in areas where retail customer choice exists, to
  the retail electric customer on whose side of the meter the
  distributed generation facility is installed and operated;
               (2)  notwithstanding Sections 37.051 and 39.105, in
  areas where retail customer choice does not exist, to the retail
  electric customer on whose side of the meter the distributed
  generation facility is installed and operated for on-site use:
                     (A)  during an emergency declared by the
  independent organization certified under Section 39.151 for the
  ERCOT power region;
                     (B)  during times of service interruption or
  inadequacy at the customer's premises;
                     (C)  during construction on the customer's
  premises;
                     (D)  for maintenance and testing of the
  distributed generation facility; and
                     (E)  up to an additional 75 hours per calendar
  year in a situation not described by Paragraph (A), (B), (C), or
  (D); and
               (3)  at wholesale in the ERCOT power region market,
  including for ancillary services in that market.
         (c)  An electric cooperative, municipally owned utility, or
  retail electric provider that provides retail electric service to
  the owner or operator of a distributed generation facility may
  purchase electric power provided to the cooperative, utility, or
  provider by the owner or operator of the distributed generation
  facility at a value agreed to by the cooperative, utility, or
  provider and the owner or operator of the distributed generation
  facility. The value of the electric power may be based wholly or
  partly on the ERCOT power region market clearing price of energy at
  the time of day and at the location at which the electric power is
  made available.
         (d)  An electric utility shall allow interconnection and
  provide distribution and transmission service to a distributed
  generation facility on a nondiscriminatory basis and in a timely
  manner. An electric utility may recover from the owner or operator
  of the distributed generation facility the reasonable costs
  directly attributable to the interconnection of the facility,
  including the reasonable costs of necessary system upgrades and
  improvements directly attributable and proportionate to the
  capacity of the distributed generation facility.
         (e)  When an electric utility receives a request for
  interconnection from the owner or operator of a distributed
  generation facility, the electric utility:
               (1)  shall provide the owner or operator with a written
  good-faith cost estimate for interconnection-related costs; and 
               (2)  may not incur a cost for the interconnection
  without entering into a written agreement for payment of the costs
  by the owner or operator of the distributed generation facility.
         (f)  An electric utility shall interconnect a distributed
  generation facility not later than the 90th day after the date the
  electric utility receives a request from the owner or operator of
  the facility for interconnection, except that the process may be
  extended for up to an additional 30 days if the request for
  interconnection requires the construction of an additional feeder
  line or upgrades to an existing line.
         (g)  An electric utility may charge the owner or operator of
  a distributed generation facility reasonable and nondiscriminatory
  rates for distribution service only to the extent that the rates are
  in accordance with a tariff filed with the commission.
         (h)  If the distributed generation facility is located in the
  certificated area of an electric utility that owns and operates
  generation and that has adopted retail customer choice, the owner
  or operator of the distributed generation facility shall contract
  with the electric utility for any services required to participate
  in the ERCOT power region wholesale market if the electric utility
  offers the services on a nondiscriminatory basis at a commercially
  reasonable cost. If the owner or operator of the distributed
  generation facility, in the owner's or operator's sole reasonable
  discretion, determines that the services are not offered on a
  nondiscriminatory basis at a commercially reasonable cost, the
  owner or operator may contract with a third-party provider to
  obtain the services. 
         (i)  Except as provided by this section, an electric utility
  or political subdivision may not impose an additional charge or
  pricing difference on a development, building permit application,
  ERCOT power region wholesale market access request, or
  interconnection agreement related to the connection or
  reconnection of a distributed generation facility.
         (j)  The commission has jurisdiction to resolve a dispute
  between an electric utility and the owner or operator of a
  distributed generation facility that arises under this section.
         (k)  A distributed generation facility must comply with
  emissions limitations established by the Texas Commission on
  Environmental Quality for electric generation facilities installed
  after January 1, 1995, that are subject to standard permit
  requirements under Section 39.264 of this code or Chapter 382,
  Health and Safety Code.
         SECTION 3.  This Act takes effect immediately if it receives
  a vote of two-thirds of all the members elected to each house, as
  provided by Section 39, Article III, Texas Constitution.  If this
  Act does not receive the vote necessary for immediate effect, this
  Act takes effect September 1, 2021.