87R26508 BRG-F
 
  By: Hancock S.B. No. 1281
 
  (King of Parker)
 
  Substitute the following for S.B. No. 1281:  No.
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to a reliability assessment of the ERCOT power grid and
  certificates of public convenience and necessity for certain
  transmission projects.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 37.052, Utilities Code, is amended by
  adding Subsection (c) to read as follows:
         (c)  An electric utility is not required to amend the
  utility's certificate of public convenience and necessity to
  construct a transmission line that connects the utility's existing
  transmission facilities to a load-serving substation or metering
  point if:
               (1)  the transmission line does not exceed three miles
  in length;
               (2)  each landowner whose property would be directly
  affected by the transmission line, as provided by commission rules,
  provides written consent for the transmission line; and
               (3)  all rights-of-way necessary for construction of
  the transmission line have been purchased.
         SECTION 2.  Section 37.056, Utilities Code, is amended by
  adding Subsection (c-1) and amending Subsection (d) to read as
  follows:
         (c-1)  In considering the need for additional service under
  Subsection (c)(2) for a reliability transmission project that
  serves the ERCOT power region, the commission must consider the
  following:
               (1)  historical load, forecasted load growth, and
  additional load currently seeking interconnection; and
               (2)  security constrained optimal power flows for a
  reasonable range of power generation dispatch scenarios, including
  reliability limitations in serving load during high and low
  renewable generation output.
         (d)  The commission by rule shall establish criteria, in
  addition to the criteria described by Subsection (c), for granting
  a certificate for a transmission project that serves the ERCOT
  power region, that is not necessary to meet state or federal
  reliability standards, and that is not included in a plan developed
  under Section 39.904(g) [does not serve a competitive renewable
  energy zone]. The criteria must include a comparison of the
  estimated cost of the transmission project for consumers and the
  estimated congestion cost savings for consumers that may result
  from the transmission project, considering both current and future
  expected congestion levels and the transmission project's ability
  to reduce those congestion levels. The commission shall include
  with its decision on an application for a certificate to which this
  subsection applies findings on the criteria.
         SECTION 3.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Section 39.159 to read as follows:
         Sec. 39.159.  GRID RELIABILITY ASSESSMENT. (a)  The
  independent organization certified under Section 39.151 for the
  ERCOT power region shall conduct an annual assessment of the ERCOT
  power grid to assess the grid's reliability in extreme weather
  scenarios.
         (b)  Each assessment must:
               (1)  consider the impact of different levels of thermal
  and renewable generation availability; and
               (2)  recommend transmission projects that may increase
  the grid's reliability in extreme weather scenarios.
         SECTION 4.  The changes in law made by this Act apply only to
  a proceeding affecting a certificate of public convenience and
  necessity that commences on or after the effective date of this Act.
  A proceeding affecting a certificate of public convenience and
  necessity that commenced before the effective date of this Act is
  governed by the law in effect on the date the proceeding is
  commenced, and that law is continued in effect for that purpose.
         SECTION 5.  This Act takes effect September 1, 2021.