By: Hancock |
S.B. No. 1281 |
|
(In the Senate - Filed March 9, 2021; March 18, 2021, read |
|
first time and referred to Committee on Business & Commerce; |
|
April 9, 2021, reported adversely, with favorable Committee |
|
Substitute by the following vote: Yeas 9, Nays 0; April 9, 2021, |
|
sent to printer.) |
Click here to see the committee vote |
|
|
COMMITTEE SUBSTITUTE FOR S.B. No. 1281 |
By: Hancock |
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
|
relating to certificates of public convenience and necessity for |
|
certain transmission projects. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 37.052, Utilities Code, is amended by |
|
adding Subsection (c) to read as follows: |
|
(c) An electric utility is not required to amend the |
|
utility's certificate of public convenience and necessity to |
|
construct a transmission line that connects the utility's existing |
|
transmission facilities to a load-serving substation or metering |
|
point if: |
|
(1) the transmission line does not exceed three miles |
|
in length; |
|
(2) each landowner whose property would be directly |
|
affected by the transmission line, as provided by commission rules, |
|
provides written consent for the transmission line; and |
|
(3) all rights-of-way necessary for construction of |
|
the transmission line have been purchased. |
|
SECTION 2. Section 37.056(d), Utilities Code, is amended to |
|
read as follows: |
|
(d) The commission by rule shall establish criteria, in |
|
addition to the criteria described by Subsection (c), for granting |
|
a certificate for a transmission project that serves the ERCOT |
|
power region, that is not necessary to meet state or federal |
|
reliability standards, and that is not included in a plan developed |
|
under Section 39.904(g) [does not serve a competitive renewable |
|
energy zone]. The criteria must include a comparison of the |
|
estimated cost of the transmission project for consumers and the |
|
estimated cost savings for consumers that may result from the |
|
transmission project. The commission shall include with its |
|
decision on an application for a certificate to which this |
|
subsection applies findings on the criteria. |
|
SECTION 3. The changes in law made by this Act apply only to |
|
a proceeding affecting a certificate of public convenience and |
|
necessity that commences on or after the effective date of this Act. |
|
A proceeding affecting a certificate of public convenience and |
|
necessity that commenced before the effective date of this Act is |
|
governed by the law in effect on the date the proceeding is |
|
commenced, and that law is continued in effect for that purpose. |
|
SECTION 4. This Act takes effect September 1, 2021. |
|
|
|
* * * * * |