|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the regulation of certain aggregate production |
|
operations by the Texas Commission on Environmental Quality; |
|
authorizing an increase in the amount of a fee. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Chapter 28A, Water Code, is amended by adding |
|
Subchapter D to read as follows: |
|
SUBCHAPTER D. RECLAMATION |
|
Sec. 28A.151. APPLICABILITY. This subchapter applies only |
|
to an aggregate production operation: |
|
(1) that is first required to be registered on or after |
|
January 1, 2016; and |
|
(2) the site of which: |
|
(A) occupies at least 10 acres; and |
|
(B) is located inside the boundaries or |
|
extraterritorial jurisdiction of a municipality. |
|
Sec. 28A.152. REGISTRATION. (a) The initial application |
|
filed by the responsible party for the registration of an aggregate |
|
production operation, or the first renewal application filed after |
|
September 1, 2023, in the case of an aggregate production operation |
|
that was first required to be registered before that date, must: |
|
(1) include a reclamation plan that complies with |
|
Section 28A.154; and |
|
(2) be accompanied by a performance bond that complies |
|
with Section 28A.155. |
|
(b) If the reclamation plan is amended, the first renewal |
|
application for registration filed by the responsible party after |
|
the date the plan is amended must include the amended plan. |
|
(c) Notwithstanding Section 28A.051(b), the requirements of |
|
this subchapter apply to an aggregate production operation until |
|
the commission determines that the responsible party has |
|
successfully complied with all reclamation requirements of this |
|
subchapter and the reclamation plan. |
|
Sec. 28A.153. REGISTRATION FEE. Notwithstanding Section |
|
28A.101(b), the commission shall set the fee for an initial or |
|
renewal application for the registration of an aggregate production |
|
operation that is required to include a reclamation plan in an |
|
amount not to exceed $1,900. |
|
Sec. 28A.154. RECLAMATION REQUIREMENTS. (a) A reclamation |
|
plan must: |
|
(1) specify which parts of the aggregate production |
|
operation will be reclaimed for forest, pasture, crop, |
|
horticultural, homesite, recreational, industrial, or other uses, |
|
including use by wildlife for food, shelter, or ground cover; |
|
(2) require any ridge or peak of overburden created by |
|
surface mining to be graded to a rolling topography traversable by |
|
machines and equipment customarily used in connection with the use |
|
to be made of the land after reclamation, except that: |
|
(A) the slope of a ridge or peak of overburden is |
|
not required to be reduced to a grade less than the original grade |
|
of the area before mining; and |
|
(B) the slope of the ridge of overburden |
|
resulting from a box cut is not required to be reduced to less than |
|
25 degrees from the horizontal; |
|
(3) if the extraction activities have exposed the face |
|
of a mineral seam in which significant concentrations of |
|
acid-forming materials are present, require the operator to cover |
|
the exposed face of the seam: |
|
(A) to a depth of not less than three feet with |
|
earth that will support plant life; or |
|
(B) with a permanent water impoundment; |
|
(4) require the operator to grade down the bank of any |
|
pit or depression created by the removal of aggregates by surface |
|
mining to a degree of slope determined in accordance with |
|
commission rules, taking into consideration: |
|
(A) the natural topography of the land affected |
|
by the extraction activities and of the adjacent land; |
|
(B) the composition of the bank; and |
|
(C) the most beneficial use of the pit or |
|
depression after reclamation; |
|
(5) require that all land affected by the extraction |
|
activities, except land that is to be covered with water or used for |
|
homesite or industrial purposes, be revegetated by the planting of |
|
seeds, trees, shrubs, or other plantings that are appropriate to |
|
the use to be made of the land after reclamation as determined by |
|
the operator; and |
|
(6) require that all mining equipment, including |
|
dredges, drag lines, crushers, screens, conveyors, on-site mining |
|
vehicles, haul trucks, and loaders, be removed from the site. |
|
(b) Subsection (a)(2) does not apply to a surface mining |
|
operation conducted in an area that is in the floodplain of a river |
|
or stream and is subject to periodic flooding. |
|
(c) A reclamation plan may allow an operator to construct an |
|
earthen dam for the purpose of forming a lake in a pit that results |
|
from surface mining operations if the formation of the lake does |
|
not: |
|
(1) interfere with another mining operation; or |
|
(2) damage the property of another person. |
|
(d) Notwithstanding Subsection (a)(4), if the pit or |
|
depression created by the removal of aggregates by surface mining |
|
is deeper than 10 feet, the reclamation plan may allow the operator |
|
to bench the highwall as long as the benches do not exceed 10 feet in |
|
height. |
|
(e) The commission by rule may prescribe the required |
|
density of planting for purposes of Subsection (a)(5) and, if the |
|
operator elects to reclaim in stages different parts of the |
|
aggregate production operation as extraction activities on those |
|
parts cease, may require replanting of those parts as necessary |
|
before planting of the entire operation is completed. |
|
(f) Notwithstanding Subsections (a)(5) and (e), planting is |
|
not required on land affected by extraction activities at an |
|
aggregate production operation if the chemical and physical |
|
characteristics of the soil of the land are so toxic or deficient in |
|
plant nutrients, or the soil of the land is composed of sand, |
|
gravel, shale, or stone to such an extent, as to seriously inhibit |
|
plant growth. |
|
(g) Except as otherwise provided by this subsection, an |
|
operator must complete all required grading not later than six |
|
months after extraction activities at the aggregate production |
|
operation cease. If the operator is unable to complete the required |
|
grading by the deadline because of weather conditions, the |
|
commission shall grant the operator an extension of time until |
|
weather conditions permit completion of the required grading. |
|
(h) Except as otherwise provided by this subsection, an |
|
operator must begin planting seeds, trees, shrubs, or other |
|
plantings on the land affected by extraction activities at the |
|
aggregate production operation at the first appropriate time after |
|
completion of the required grading. If the operator is unable to |
|
acquire sufficient planting stock of appropriate species from local |
|
nurseries or to acquire sufficient stock from other sources at |
|
comparable prices, the commission shall grant the operator an |
|
extension of time until sufficient stock at such prices is |
|
available to plant the land in accordance with the reclamation |
|
plan. |
|
Sec. 28A.155. PERFORMANCE BOND. (a) A performance bond |
|
must: |
|
(1) be payable to this state and conditioned on the |
|
faithful performance of the requirements of this subchapter and the |
|
reclamation plan; |
|
(2) cover the area to be affected by the extraction |
|
activities at the aggregate production operation; |
|
(3) be in an amount equal to $2,500 for each acre to be |
|
affected by the extraction activities at the aggregate production |
|
operation; and |
|
(4) be executed by the responsible party and a |
|
corporate surety licensed to do business in this state. |
|
(b) Liability under a performance bond is for the duration |
|
of the activities at the aggregate production operation, including |
|
the activities necessary and incidental to the reclamation of the |
|
land affected by the extraction activities at the operation. |
|
(c) The commission may release all or part of a performance |
|
bond if the commission is satisfied that the reclamation covered by |
|
the bond or part of the reclamation, as applicable, has been |
|
accomplished as required by this subchapter and the reclamation |
|
plan. |
|
(d) The commission shall declare a performance bond |
|
forfeited if the operator fails to comply with the requirements of |
|
this subchapter or the reclamation plan. |
|
Sec. 28A.156. INSPECTION BY COMMISSION. The commission may |
|
periodically inspect an aggregate production operation after |
|
extraction activities at the operation have ceased to verify that |
|
the operator is complying with the requirements of this subchapter |
|
and the reclamation plan. |
|
Sec. 28A.157. NOTICE OF COMPLETION OF RECLAMATION; |
|
INSPECTION AND DETERMINATION BY COMMISSION. (a) After reclamation |
|
activities at an aggregate production operation have been |
|
accomplished as required by this subchapter and the reclamation |
|
plan, the operator shall notify the commission in writing that the |
|
activities have been completed. |
|
(b) The commission shall inspect the aggregate production |
|
operation to determine whether the operator has completed |
|
reclamation of the operation as required by this subchapter and the |
|
reclamation plan. If the commission determines that the |
|
reclamation of the aggregate production operation has been |
|
completed as required by this subchapter and the reclamation plan: |
|
(1) the commission shall release any remaining part of |
|
the performance bond; and |
|
(2) the requirements of this subchapter are no longer |
|
applicable to the operation. |
|
Sec. 28A.158. WAIVER BY MUNICIPALITY OF RECLAMATION |
|
REQUIREMENTS. (a) If the reclamation activities required by a |
|
reclamation plan conflict with a potential reasonable future use of |
|
the aggregate production operation on cessation of extraction |
|
activities at the operation, the responsible party may submit a |
|
proposal to the governing body of the municipality inside the |
|
boundaries or extraterritorial jurisdiction of which the operation |
|
is located to amend the plan. |
|
(b) The governing body of the municipality shall approve the |
|
proposed amendment to the reclamation plan if, after a public |
|
meeting on the proposal, the governing body determines that the |
|
proposed amendment appears to be in the best interest of the |
|
municipality, the county in which the aggregate production |
|
operation is located, and this state. |
|
(c) If the governing body of the municipality approves the |
|
proposed amendment to the reclamation plan, the governing body |
|
shall notify the responsible party and the commission. The |
|
commission shall give effect to the proposed amendment to the plan |
|
and shall release all or part of the performance bond, as |
|
applicable. |
|
SECTION 2. This Act takes effect September 1, 2023. |